f THE CLEVELAND ELECTR P.O BOX 5000 - CLEVELAND. oHlo 44101 - TELFPHONE (216) 622-9800 - ILLUMINATING BLDG.
- 55 PUBLIC SOUARE Serving The Best iocation in tte Vation psO PRIORITY ROUTING First li ud_-
MURRAY R. EDELMAN August 28, 1986 53 P
PY-CEI/01E-0231 L 4 7/
10_Z uc 6
uRS i4L h
VM FILE j y Mr. James G. Keppler Director, Region III office of Inspection and Enfoecement U.S.
Nuclear Regulatory Commission 799 roosevelt Road Glen Ellyn, Illinois 60137 Perry Nuclear Power Plant Docket No. 50-440 Report of 10 CFR 50.59 Changes to the Initial Test Program
Dear Mr. Keppler:
Enclosed is a report of changes to the Initial Test Program made in accordance with Operating License Condition 2.C(4) and 10 CFR 50.59.
This report includes all such changes made since July 29, 1986 and through August 24, 1986.
If you have any questions, please feel free to call.
ery truly yours, 49.Mulm MIsrray Edelman Senior Vice President Nuclear Group MRE:njc Enclosure cc:
J. M. Taylor (39)
H. R. Denton J. Stefano J. Silberg K. A. Connaugnton Document Control Desk (USNRC) 4 9
i I
8609080274 860828 PDR ADOCK 0500 0
M2 c
s
Attcchment PI-CEI/01E-0231 L SAFETY EVALUATION MONTHLY
SUMMARY
I.
GENERAI, INFORMATION FINAL APPROVAL FSAR DOCUMENT DATE SECTION STI-001 07/31/86 TABLE 14.2-2, 14.2.12.2.1 II.
DESCRIPTION This safety evaluation was performed to evaluate a difference between STI-P35-001, Chemical and Radiochemical, Rev. 2,and the Section 14.2.12.2.1 and Table 14.2-2, Startup Tests.
STI-P35-001, Chemical and Radiochemical was changed to include Level 2 acceptance criteria on moisture carryover for testing performed in the Maximum Extended Operating Domain (MEOD).
Table 14.2-2 states that the Startup Test Instruction is performed at Test Conditions OV, HU, 1, 2, 3, 5, and 6.
The STI has been changed to add additional testing in the increased flow region at Test Condition 3 and in the extended load region at Test Condition 8.
FSAR Table 14.2-2 will be changed to indicate testing of Chemical and Radiochemical during Test Conditions OV, HU, 1, 2, 3, 5, 6, and 8.
FSAR 14.2.12.2.1 does not list any specific Level 2 acceptance criteria. The STI has been changed to include Level 2 acceptance criteria on moisture carryover in the increased flow region of Test Condition 3 and the extended load region of Test Condition 8.
FSAR 14.2.12.2.1 will be changed to indicate testing of moisture carryover Level 2 acceptance criteria.
SSER 8 Section 15.1 approved operation in this extended operation domain for plant startup testing.
III.
SUMMARY
A change is required in Table 14.2-2 and FSAR 14.2.12.2.1 to reflect additional test conditions and acceptance criteria required for teating in the Maximum Extended Operation Domain (MEOD) to comply with the latest GE Test Specifications.
p m.g y
Attachment PY-CEI/01E-0231 L SAFETY EVALUATION MONTHLY
SUMMARY
I.
GENERAL INFORMATION FINAL APPROVAL FSAR DOCUMENT DATE SECTION STI-020 08/21/86 TABLE 14.2-2 II.
DESCRIPTION This safety cvaluation was performed to evaluate a difference between STI-B21-020, Steam Production, Rev. 2 and FSAR Table 14.2-12, Startup Tests.
FSAR Table 14.2-2 states that the Startup Test Instruction is performed in Test Condition 6.
The STI has been revised to schedule testing in Test Condition 8.
The initial conditions for this test have not changed.
FSAR Table 14.2-2 will be changed to indicate performance of the Steam Production test during Test Condition 8.
SSER 8 Section 15.1 approved operation in this extended operating domain for plant startup testing.
III.
SUMMARY
A change is required in Table 14.2-2 to reflect the scheduling change required for testing in the Maximum Extended Operating Domain (MEOD) to comply with the latest GE Test Specifications.
Attcch,sent PY-CEI/01E-0231 L SAFETY EVALUATION MONTHLY
SUMMARY
I.
GENERAL INFORMATION FINAL APPROVAL FSAR DOCUMENT DATE SECTION STI-022 07/31/86 14.2.12.2.19, TABLE 14.2-2 II.
DESCRIPTION This safety evaluation was' performed to evaluate a difference between STI-C85-022, Pressure Regulator, Rev. 2. and FSAR Section 14.2.12.2.19 and Table 14.2-12, Startup Tests.
2' FSAR 14.2.12.2.19 states that a plot of power versus the peak variable values along the 100% rod line will be maintained. The Startup Test i
Instruction'has been changed to obtain this plot along the bounding licensed rod line. This change was made to support testing the in Maximum Extended Operating Domain (MEOD).
FSAR 14.2.12.2.19 will be changed to indicate the acquisition of this-plot along the bounding licensed rod lines.
4 FS'AR Table 14.2-2 states that the Startup Test Instruction will be performed at Test Conditions 1 through 6, inclusively. The STI has been changed to schedule testing for Test Conditions 1,2,3,4,6,7, and 8.
3 FSAk Table 14.2-2 will be changed to indicate testing of Pressure Regulator in Test Conditions 1, 2, 3, 4, 6, 7, and 8.
SSER 8 Section 15.1 approved operation is this extended operating domain for plant startup testing.
1 III.
SUMMARY
A change is required in Table 14.2-2 and FSAR 14.2.12.2.19 to reflect changes required for testing in the Maximum Extended Operating Domain j
(MEOD) to comply with the latest GE Test Specifications.
P 4
P k
4
-m*
r---- - +
--n..--,.,-
-.-e-5
-,v i
..%4,
--.m.,,,,---e-
- ,.,--ee~,-w,om-,w--,~.i,-,+-,e.-w-,---as
,e isv~.-
Attcchment PY-CEI/01E-0231 L SAFETY EVALUATION MONTHLY
SUMMARY
I.
GENERAL INFORMATION FINAL APPROVAL FSAR DOCUMENT DATE SECTION STI-023A 07/30/86 TABLE 14.2 II.
DESCRIPTION This safety evaluation was performed to evaluate those differences between STI-N27-023A, Feedwater Master Reactor Level Controller, Rev. 2 and FSAR Table 14.2-2, Startup Tests.
FSAR Table 14.2-2 states that the Startup Test Instruction is performed at Test Conditions HU, 1, 2, 3, 4, 5, and 6.
The STI has been changed to schedule testing at Test Conditions HU, 1, 2, 3, 4, 5, 6, 7, and 8.
The testing in Test Condition 7 and 8 has been added to verify plant operating parameters in the extended operating domain.
FSAR Table 14.2-2 will be changed to indicate testing of the Feedwater Master Reactor Level Controller at Test Conditions HU, 1, 2, 3, 4, 5, 6, 7, and 8.
SSER 8 Section 15.1 approved operation in this extended operating domain for plant startup testing.
III.
SUMMARY
A change is required in Table 14.2-2 to reflect changes required for testing in the Maximum Extended Operating Domain (MEOD) to comply with the latest GE Test Specifications.
~.
Attcchment PY-CEI/01E-0231 L SAFETY EVALUATION MONTHLY
SUMMARY
I.
GENERAL INFORMATION FINAL APPROVAL FSAR DOCUMENT DATE SECTION STI-024 08/20/86 14.2.12.2.21, TABLE 14.2-2 11.
DESCRIPTION This safety evaluation was performed to evaluate the differences between STI-N31-024, Turbine Valve Surveillance, Rev. 2. and the FSAR Section 14.2.12.2.21 and Table 14.2-2, Startup Tests.
FSAR 14.2.12.2.21 states that valve testing will be perfomred at increasing power levels along the 100% load line. The Startup Test Instruction has been changed to include valve testing along the bounding licensed load line.
FSAR 14.2.12.2.21 will be changed to state that valve testing will be performed at increasing power levels along the 100% load line.and the bounding licensed load line.
FSAR Table 14.2-2 states that the Startup Test Instruction is performed at Test conditions 2, 5, and 6.
The STI has been changed to schedule testing at Test Condtions 2, 5, 6, 7, and 8.
FSAR Table 14.2-2 will be changed to indicate testing of the Turbine Valve Surveillance at Test Conditions 2, 5, 6, 7, and 8.
SSER 8 Section 15.1 approved operation in this extended operating domain for plant startup testing.
III.
SUMMARY
A change is required in FSAR 14.2.12.2.21 and. Table 14.2-2 to reflect changes required for testing in the Maximum Extended Operating Domain (MEOD) to comply with the latest GE Test Specifications.
.1 l
i 4
Attachment.
PY-CEI/01E-0231 L SAFETY EVALUATION MONTHLY
SUMMARY
I.
GENERAL INFORMATION FINAL APPROVAL FSAR DOCUMENT DATE SECTION STI-029A 08/20/86 FIGURE 14.2-4 II.
DESCRIPTION This safety evaluation was performed to evaluate the differences between STI-B33-029A, Recirculation Flow Control - Valve Position Loop, Rev. 2 and FSAR Figure 14.2-4.
FSAR Figure 14.2-4 defines Test Conditions 3 and 6 to be limited by 100% core flow. There is no defined region for Test Condition 8.
The STI has been changed to perform testing in the increased flow regions of Test Conditions 3 and 6 and the extended load region of Test Condition 8.
FSAR Figure 14.2-4 will be changed to reflect the extended regions as defined in the Maximum Extended Oparating Domain (MEOD).
SSER 8 Section 15.1 approved operation in this extended operating domain for plant startup testing.
III.
SUMMARY
A change is required to Figure,14.2-4 to reflect changes required for testing in the Maximum Extended Operating Domain (MEOD) to comply with the latest GE Test Specifications.
4 f
i 1
-_..,-,.,--_...,....,-,.nn.-.-
--_,,_-,m--..,,__
. ~.
Attachment PY-CEI/01E-0231 L i
SAFETY EVALUATION MONTHLY
SUMMARY
I.
GENERAL INFORMATION FINAL APPROVAL FSAR DOCUMP.NT DATE SECTION STI-030A 07/30/86 FIGURE 14.2-4 II.
DESCRIPTION This safety evaluation was performed to evaluate a difference between STI-B33-030B, RPT Trip of Two Pumps, Rev. 2 and FSAR Figure 14.2-4.
The Startup Test Instruction has been developed to allow testing above 95% core flow within Test Condition 6.
FSAR Figure 14.2-4 defines a maximum core flow limit of 100% for Test Condition 6.
FSAR Figure 14.2-4 will be changed to indicate a maximum core flow limit of 105% for Test Condition 6.
SSER 8 Sec' tion 15.1 approved operation in this extended operating domain for plant startup testing.
III.
SUMMARY
A change is required in Figure 14.2-4 to reflect changes required for testing in the Maximum Extended Operating Domain (MEOD) to comply with the latest GE Test Specifications.
l i
i I
i i
i I
r I
i
~
Attachment PY-CEI/01E-0231 L SAFETY EVALUATION MOLTHLY
SUMMARY
I.
GENERAL INFORMATION FINAL APPROVAL FSAR DOCUMENT DATE SECTION' STI-133 07/30/86 TABLE 14.2-2 II.
DESCRIPTION 1
This safety evaluation was performed to evaluate the differenceb between STI-R63-133, Loose Parts Monitoring System, Rev. 2 and FSAR Table 14.2-2, Startup Tests.
FSAR Table 14.2-2 states that the Startup Test Instruction is performed at Test Conditions HU, 1, 2, 3, 4, 5, and 6.
The STI has been changed 4
to schedule testing at Test Conditions HU, 1, 2, 3, 4, 5, 6, 7, and 8.
The testing in Test Condition 7 and 8 was added to verify plant operating parameters in MEOD.
FSAR Table 14.2-2 will be changed to indicate testing at Test Conditions HU, 1, 2, 3, 4, 5, 6, 7, and 8.
SSER 8 Section 15.1 approved operation in this extended operating domain for plant startup testing.
III.
SUMMARY
A change is required in Table 14.2-2 to reflect changes required for testing in the Maximum Extended Operating Domain (MEOD) to comply with the latest GE Test Specifications.
-.. -.