MONTHYEARML20209A5252020-08-19019 August 2020 Temporary Exemption from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel (EPID L-2020-LLE-0122 (COVID-19)) Project stage: Approval 2020-08-19
[Table View] |
|
---|
Category:Exemption from NRC Requirements
MONTHYEARML24107A9232024-05-0808 May 2024 CBS Exemption (Attachment) ML24096A1372024-04-0505 April 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Limerick Generating Station – Holtec MPC-89CBS ML24044A0732024-02-28028 February 2024 Federal Register Notice - Issuance of Multiple Exemptions Regarding 10 CFR Part 73 - January 2024 ML24004A0342024-01-17017 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0026 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) LG-23-097, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-13013 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23052A0232023-02-17017 February 2023 License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the Digital Modernization Project Installation ML21078A0502021-04-0606 April 2021 Exemption from Specific Requirements of 10 CFR Part 26 (EPID L-2021-LLE-0017 (COVID-19)) ML21064A0022021-03-0404 March 2021 COVID-19 Related Request for Exemption from Part 26 Work Hours Requirements ML20353A3442020-12-18018 December 2020 Exemption Request for NRC Review Fees for the License Amendment Request for the Limerick Digital Modernization Project ML20330A2952020-12-10010 December 2020 Exemption from Annual Force-on-Force Exercise Requirement of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel, Subsection VI.C.3.(l)(1) (EPID L-2020-LLE-0201 (COVID-19)) NMP1L3362, Request for an Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding 2020 Annual Force-on-Force (FOF) Exercises Due to COVID- 19 Public Health Emergency2020-11-13013 November 2020 Request for an Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding 2020 Annual Force-on-Force (FOF) Exercises Due to COVID- 19 Public Health Emergency ML20243A0002020-09-23023 September 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for August 2020 ML20209A5252020-08-19019 August 2020 Temporary Exemption from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel (EPID L-2020-LLE-0122 (COVID-19)) ML20090B4102020-06-0202 June 2020 Issuance of Relief Request GVRR-9 Associated with Pandemic-Related Issues - Inservice Testing Interval Extension for Motor Operated Valves (EPID L-2020-LLR-0046 (COVID-19)) ML20119A5242020-05-0707 May 2020 FRN: Notice of Issuance of Multiple Exemptions Regarding 10 CFR Part 26 (COVID-19) ML0614302462006-06-27027 June 2006 TMI and Zion - Exemption from the Requirements of 10 CFR 50.54(a)(3) Re Submittal of Changes to Quality Assurance Topical Report ML0233805992002-11-25025 November 2002 Exemption Request from the Requirements of 10 CFR 50.36(c)(1) ML0037819842001-03-15015 March 2001 Exemption from the Requirements of 10 CFR Part 50, Section 50.60(a) and Appendix G 2024-05-08
[Table view] Category:Letter
MONTHYEARIR 05000352/20240122024-10-17017 October 2024 Commercial Grade Dedication Inspection Report 05000352/2024012 and 05000353/2024012 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24274A2372024-10-0707 October 2024 – Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding Primary Containment Leakage Technical Specifications ML24278A3022024-10-0404 October 2024 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10 CFR 50.62 ATWS Rule to Support the Digital Modernization Project Installation - Rev Unit 2 Technical Spec ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24263A0032024-09-27027 September 2024 Generation Station, Units 1 and 2 – Regulatory Audit Plan Supporting Review of the Component Interface Module System of the Limerick Digital Instrumentation and Controls License Amendment Request (EPID L-2022-LLA-0140) (Redacted) ML24243A0482024-09-19019 September 2024 Generation Station, Unit Nos. 1 and 2 - Schedule Update for License Amendment Request to Replace Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System ML24215A4042024-09-18018 September 2024 Request for Withholding Information from Public Disclosure IR 05000352/20244202024-09-16016 September 2024 – Security Baseline Inspection Report 05000352/2024420 and 05000353/2024420 RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds IR 05000352/20250102024-09-10010 September 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000352/2025010 and 05000353/2025010 ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification IR 05000352/20230022024-09-0404 September 2024 Reissued Integrated Inspection Report 05000352/2023002 and 05000353/2023002 IR 05000352/20240052024-08-29029 August 2024 Updated Inspection Plan for Limerick Generating Station, Units 1 and 2 (Report 05000352/2024005 and 05000353/2024005) ML24241A1952024-08-28028 August 2024 License Amendment Request for Modification to Technical Specification 3.6.1.2 and Main Steam Isolation Valve Leakage Rate Requirements ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 ML24163A3902024-08-14014 August 2024 Request for Withholding Information from Public Disclosure IR 05000352/20240022024-08-12012 August 2024 Integrated Inspection Report 05000352/2024002 and 05000353/2024002 ML24220A2392024-08-12012 August 2024 Correction to Technical Specification Page 3/4 3-11 in Amendment No. 225 ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24204A0712024-07-29029 July 2024 Issuance of Amendment Nos. 263 and 225 Technical Specifications for Main Steam Line Tunnel Temperature ML24208A1592024-07-25025 July 2024 Regulatory Audit Plan Supporting Review of the System Development Portion of Limerick Digital Instrumentation and Controls License Amendment Request (EPID L-2022-LLA-0140) - Non-Proprietary ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24201A1662024-07-19019 July 2024 Response to Request for Additional Information for License Amendment Request for Proposed Changes to the Technical Specification Isolation Actuation Instrumentation Tables and New Turbine Enclosure Main Steam L ML24199A1842024-07-15015 July 2024 RAI-LAR for Limerick EPID: L-2024-LLA-0079- Use This Version RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions ML24180A1572024-06-28028 June 2024 Request to Return and Replace WEC Documents (EQ-EV-386-GLIM, EQ-QR- 433-GLIM, and APP-GW-GLR-611), to Meet 10CFR2.390 Request to Withdraw from Public Disclosure Requirements ML24170A7702024-06-20020 June 2024 Individual Notice of Consideration of Issuance of Amendments to Renewed Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, Opportunity for Hearing(Epid L-2024-LLA-0079) LTR ML24166A1142024-06-14014 June 2024 Response to Requests for Additional Information (RAIs 15 Through 23) for License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24165A2642024-06-13013 June 2024 License Amendment Request for Proposed Changes to the Technical Specification Isolation Actuation Instrumentation Tables and New Turbine Enclosure Main Steam Line Tunnel Temperature TS 3/4.7.9 ML24151A2012024-06-10010 June 2024 Request for Withholding Information from Public Disclosure ML24151A2882024-06-10010 June 2024 Request for Withholding Information from Public Disclosure ML24150A0242024-05-29029 May 2024 Notification of Commercial Grade Dedication Inspection (05000352/2024012 and 05000353/2024012) and Request for Information ML24149A2112024-05-28028 May 2024 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFR50.62 ATWS Rule to Support the Digital Modernization Project Installation ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 IR 05000352/20243022024-05-20020 May 2024 Revised Initial Operator Licensing Examination Report 05000352/2024302 and 05000353/2024302 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report IR 05000352/20240012024-05-0707 May 2024 Integrated Inspection Report 05000352/2024001 and 05000353/2024001 ML24124A0432024-05-0303 May 2024 Response to Requests for Additional Information (RAIs 9 Through 14) for License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with RS-24-038, Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-05-0202 May 2024 Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24114A3222024-04-23023 April 2024 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System (PPS) - Pivot to Unit ML24109A0702024-04-18018 April 2024 Supplement to License Amendment Request to Revise Technical Specifications and Exemption Request from Requirements of 10CFRC50.52 ATWS Rule to Support the Digital Modernization Project Installation . ML24093A0912024-04-17017 April 2024 Revised Estimated Review Completion Date Concerning License Amendment Request to Replace Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System ML24106A1832024-04-15015 April 2024 Submittal of Changes to Technical Specifications Bases ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24096A1372024-04-0505 April 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Limerick Generating Station – Holtec MPC-89CBS RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report IR 05000352/20244012024-03-19019 March 2024 Security Baseline Inspection Report 05000352/2024401 and 05000353/2024401 2024-09-06
[Table view] |
Text
7 August 19, 2020 Mr. Bryan C. Hanson Senior Vice President Exelon Generation Company, LLC President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
LIMERICK GENERATING STATION, UNITS 1 AND 2 - TEMPORARY EXEMPTION FROM CERTAIN REQUIREMENTS OF 10 CFR PART 73, APPENDIX B, GENERAL CRITERIA FOR SECURITY PERSONNEL, SECTION VI (EPID L-2020-LLE-0122 [COVID-19])
Dear Mr. Hanson:
The U.S. Nuclear Regulatory Commission (NRC or the Commission) has approved the below temporary exemption from specific requirements of Title 10 of the Code of Federal Regulations (10 CFR) Part 73, Appendix B,Section VI, Nuclear Power Reactor Training and Qualification Plan for Personnel Performing Security Program Duties, for the Limerick Generating Station, Units 1 and 2 (Limerick). This action is in response to Exelon Generation Company, LLCs (Exelon or the licensee) application dated July 29, 2020 (Agencywide Documents Access and Management System Accession No. ML20211L699 (non-public, withheld under 10 CFR 2.390)),
that requested a temporary exemption from 10 CFR Part 73, Appendix B, Section VI, subsection C.3.(l)(1), regarding annual force-on-force (FOF) exercises at Limerick.
The requirements in 10 CFR Part 73, Appendix B, Section VI, subsection C.3.(l)(1), state, in part:
Each member of each shift who is assigned duties and responsibilities required to implement the safeguards contingency plan and licensee protective strategy participates in at least . . . one (1) force-on-force exercise on an annual basis.
Force-on-force exercises conducted to satisfy the NRC triennial evaluation requirement can be used to satisfy the annual force-on-force requirement for the personnel that participate in the capacity of the security response organization.
The purpose of the annual licensee-conducted FOF exercises is to ensure that the site security force maintains its contingency response readiness. Participation in the annual FOF exercise also supports the requalification of security force members.
On January 31, 2020, the U.S. Department of Health and Human Services declared a Coronavirus Disease 2019 (COVID-19) public health emergency (PHE) for the United States.
Subsequently, the Centers for Disease Control and Prevention issued recommendations (e.g.,
social distancing, limiting assemblies) to limit the spread of COVID-19.
B. Hanson Exelons July 29, 2020, application states the following:
This temporary exemption supports isolation restrictions (e.g., social distancing, group size limitations, self-quarantining, use of personal protective equipment, etc.) necessary to protect required site personnel in response to the COVID-19 virus.
These restrictions are needed to ensure personnel are isolated from the COVID-19 virus and remain capable of maintaining plant security.
Exelon began implementing isolation restrictions after the Governor of the State of Pennsylvania issued a disaster declaration on March 6, 2020.
Exelon will continue performing the quarterly tactical response drills/exercises and is not requesting an exemption from these requirements at this time.
Exelon will maintain a list of the names of the individuals who will not meet the requalification requirements and will include the dates of the last qualification.
Exelon will ensure contingency response readiness of security personnel not participating in an annual FOF exercise by conducting a lessons-learned review of past exercise and will complete the FOF exercise within the time period in this request when isolation restrictions are ended.
Exelon will schedule and complete any missed FOF exercise within the time period in this request when isolation restrictions are ended.
Exelon will begin implementing COVID-19 PHE controls for managing personnel performing Security Program duties upon NRC approval of its request.
This temporary exemption is to specific Limerick security personnel who have previously demonstrated proficiency and are currently qualified in accordance with the requirements of 10 CFR Part 73, Appendix B, Section VI. Exelon also stated that given the rigorous nature of Limericks nuclear security personnel training programs, which consist of regularly scheduled training activities to include weapons training, contingency response drills and exercises, and demonstrated acceptable performance of day-to-day job activities (e.g., detection and assessment, patrols, searches, and defensive operations), it is reasonable to conclude that security personnel will continue to maintain their proficiency even though the requalification periodicity is temporarily exceeded. Additionally, the July 29, 2020, request identified site-specific COVID-19 PHE controls listed above that will be implemented at Limerick, consistent with those outlined in the NRC staffs April 20, 2020, letter discussing planned activities related to the requirements for 10 CFR Part 73, Appendix B, Section VI, during the PHE (ADAMS Accession No. ML20105A483). Exelon requested that the duration of the exemption be in effect for 90 days after the PHE is ended, or until December 31, 2020, whichever occurs first, consistent with the NRC staffs April 20, 2020.
Pursuant to 10 CFR 73.5, Specific exemptions, the Commission may, upon application by any interested person or upon its own initiative, grant exemptions from the requirements of 10 CFR Part 73 when the exemptions are authorized by law, will not endanger life or property or the common defense and security, and are otherwise in the public interest.
B. Hanson In accordance with 10 CFR 73.5, the Commission may grant an exemption from the regulations in 10 CFR Part 73 that is authorized by law. The NRC staff has reviewed the exemption request and finds that granting the proposed exemption will not result in a violation of the Atomic Energy Act of 1954, as amended, or other laws. Therefore, the NRC staff finds that the exemption is authorized by law.
In accordance with 10 CFR 73.5, the Commission may grant an exemption from the regulations in 10 CFR Part 73 when the exemption will not endanger life or property or the common defense and security. This exemption will only apply to licensee security personnel who are already satisfactorily qualified on the security requirements in 10 CFR Part 73, Appendix B, Section VI.
Based on this fact and its review of the controls Exelon will implement for the duration of the exemption, including continuing to conduct required quarterly tactical response drills, a lessons-learned review of past exercises, and completing any missed annual FOF exercise within the time period in this request, the NRC staff has reasonable assurance that the security force at Limerick will maintain its proficiency and readiness to implement the licensees protective strategy and adequately protect the site. Therefore, the NRC staff concludes that the proposed exemption would not endanger life or property or the common defense and security.
In accordance with 10 CFR 73.5, the Commission may grant an exemption from the regulations in 10 CFR Part 73 when the exemption is in the public interest. Participation in annual FOF exercises places site security personnel in close proximity to one another. Such proximity has the potential to increase the likelihood of security personnel being exposed to the COVID-19 virus. The NRC staff finds that the temporary exemption from the annual FOF requirement in 10 CFR Part 73, Appendix B, Section VI, subsection C.3.(l)(1), would facilitate the licensees efforts to maintain a healthy workforce capable of operating the plant safely and implementing the sites protective strategy by isolating security personnel from potential exposure to the COVID-19 virus. The NRC staff concludes that granting the temporary exemption is in the public interest because it allows the licensee to maintain the required security posture at Limerick, while enabling the facility to continue to provide electrical power to the Nation.
Environmental Considerations NRC approval of this exemption request is categorically excluded under 10 CFR 51.22(c)(25),
and there are no special circumstances present that would preclude reliance on this exclusion.
The NRC staff determined, per 10 CFR 51.22(c)(25)(vi)(E), that the requirements from which the exemptions are sought involve education, training, experience, qualification, requalification, or other employment suitability requirements. The NRC staff also determined that approval of this exemption request involves no significant hazards consideration because it does not authorize any physical changes to the facility or any of its safety systems, nor does it change any of the assumptions or limits used in the facility licensees safety analyses or introduce any new failure modes. There is no significant change in the types or significant increase in the amounts of any effluents that may be released offsite because this exemption does not affect any effluent release limits as provided in the facility licensees technical specifications or by the regulations in 10 CFR Part 20, Standards for Protection Against Radiation. There is no significant increase in individual or cumulative public or occupational radiation exposure because this exemption does not affect limits on the release of any radioactive material or the limits provided in 10 CFR Part 20 for radiation exposure to workers or members of the public.
There is no significant construction impact because this exemption does not involve any changes to a construction permit. There is no significant increase in the potential for or consequences from radiological accidents because this exemption does not alter any of the assumptions or limits in the facility licensees safety analysis. In addition, the NRC staff
B. Hanson determined that there would be no significant impacts to biota, water resources, historic properties, cultural resources, or socioeconomic conditions in the region. Therefore, pursuant to 10 CFR 51.22(b), no environmental impact statement or environmental assessment need be prepared in connection with the approval of this exemption request.
Conclusions Accordingly, the NRC has determined that pursuant to 10 CFR 73.5, the exemption is authorized by law, will not endanger life or property or the common defense and security, and is otherwise in the public interest. Therefore, the Commission hereby grants the licensees request to temporarily exempt Limerick from the annual FOF exercise requalification requirement of security personnel in subsection C.3.(l)(1) of 10 CFR Part 73, Appendix B, Section VI.
This exemption expires 90 days after the end of the PHE, or December 31, 2020, whichever occurs first.
If you have any questions, please contact the Limerick project manager, V. Sreenivas, at 301-415-2597 or by e-mail to V.Sreenivas@nrc.gov.
Sincerely, Digitally signed by Craig Craig G. G. Erlanger Date: 2020.08.19 Erlanger 11:25:54 -04'00' Craig G. Erlanger, Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-352 and 50-353 cc: Listserv
ML20209A525 OFFICE NRR/DORL/LPL1/PM NRR/DORL/LPL1/LA NSIR/DPCP/RSB/BC NAME VSreenivas LRonewicz ABowers DATE 07/29/2020 07/29/2020 08/07/2020 OFFICE OGC - NLO NRR/DORL/LPL1/BC NRR/DORL/D NAME JBielicki JDanna CErlanger DATE 08/13/2020 08/19/2020 08/19/2020