ML20207T922

From kanterella
Jump to navigation Jump to search
Insp Repts 50-424/87-11 & 50-425/87-07 on 870126-30. Violations Noted:Failure to Follow Design Manual for Psar/ FSAR as-built Changes & Failure to Provide Adequate Rept of Significant Const Deficiency
ML20207T922
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 02/06/1987
From: Blake J, Kleinsorge W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20207T919 List:
References
50-424-87-11, 50-425-87-07, 50-425-87-7, NUDOCS 8703240425
Download: ML20207T922 (9)


See also: IR 05000424/1987011

Text

,

,._m

-

. _ .

. _._

. . , . . _ -

. . . _ . _

4

.m_

._

.

. _ _ _ _ _ .

_

t

.

,

r:

< i

'

'

j

paso

,

UNITED STATES

.7 f

.

[

..

NUCLEAR REGULATORY COMMISSION

'

n

.

REGION il

.3

1j

101 MARIETTA STREET, N.W.

- *

ATLANTA, GEORGI A 30323

L

. . . . . . *

Report Nos.:

50-424/87-11 and 50-425/87-07

.

Licensee: Georgia Power Company',

-

P. O. Box 4545

'

L

Atlanta, GA. 30302

..

,.

'

.

,

~

Docket Nos.:

50-424 and 50-425

'

License Nos.:

NPF-61 and CPPR-109

l -

Facility Name: .Vogtle

.

'

i-

L

' Inspection Co

d: Jan ary 26 - 30,

1987.2

"'

~

h

2-

/

7

. Inspect r:

~r

Dite si ned

u

_

W. P.

'

,

6 F 7 -'

Appro ed by-

-

J. J B ke, Section Chief

Date Signed "

~

En ne ring Section

l

DJ is, on of Reactor Safety

SUMMARY

l

. Scope:

This routine, unannounced inspection was conducted in -the areas of

l-

licensee actions on previous enforcement matters (92701B)(92702B), housekeeping

(548348), material identification and control (4290213) material

control

(42940B),. safety-related heating ventilating and air conditioning (HVAC)- systems

!

'

(50100) (Unit 2), steel structures and supports (Units 2), and licensee iden-

tified items.

Results: Two violations were identified

" Failure to Follow Design Manual For

'

. PSAR/FSAR As-Built Changes"

paragraph 3f and " Failure to Provide Adequate '

L

Report of Significant Construction Deficiency"

paragraph

-8.

L

,

k-

P

P

G

.

>--aa -

.

- -- .- .-

.

.

REPORT DETAILS

.

1.

Persons Contacted

'

Licensee Employees

  • C. W. Hayes, Vogtle QA Manager
  • T. Greene, Plant Manager
  • E. D. Groover, Quality Assurance (QA) Site Manager Construction

Other licensee employees contacted included construction craftsmen,

engineers, technicians, operators, mechanics, security force members, and

office personnel.

Other Organizations

  • F. B. Marsh, Project Engineering Manager , Bechtel Power Corporation (BPC)

NRC' Resident Inspectors

  • A. H. Livermore, Senior Resident Inspector (SRI), Construction

J, Rogge, SRI Operations

R. Shepens, RI

  • Attended exit interview

2.

Exit Interview (307038)

.

The inspection scope and findings were summarized on January 30, 1987, with

those persons indicated in paragraph 1 above. The inspector described the

areas inspected and discussed in detail the inspection findings listed

below. No dissenting comments were received from the licensee.

(0 pen) Violation 50-424/87-11-01 and 50-425/87-07-01:

" Failure to Follow

,

'

Design Manual for PSAR/FSAR As-Built Changes

" paragraph 3f.

2

(0 pen) Violation 50-424/87-11-02 and 50-425/87-07-02:

" Failure to Provide

i

Adequate Report of Significant Construction Deficiency"

paragraph 8.

The licensee did not identify as proprietary any of the materials provided

to or reviewed by the inspector during this inspection.

3.

Licensee Action on Previous Enforcement Matters (92701B)(92702B)

a.

(Closed) Violaticn 50-424/86-59-01:

" Failure to Procure HVAC Systems

That Were Fabricated, Installed and Inspected In Accordance With

Procedures and Drawings"

Georgia Power Company (GPC) letter of response dated September 25, 1986

has been reviewed and determined to be acceptable by Region II.

The

.

.

.

.

.

.

.

.

. .

. .

. .

.

.

.

.

.

.

.

.

.

.

. - .

. .

.

.

.

.

2

inspector held discussions with the cognizant engineer and examined the

corrective actions as stated in the letter of response. The inspector

concluded that GPC had determined the full extent of the subject

violation, performed the necessary survey and followup actions, to

correct the present conditions and developed the necessary corrective

actions to preclude recurrence of similar circumstances.

The

corrective actions identified in the letter of response have been

implemented.

b.

(Closed) Deviation 50-424/86-59-02 and 425/86-26-02:

" Failure To

Procure Explosion Proof Motors As Committed"

GPC letters of response dated September 25, 1986 and October 31, 1986,

have been reviewed and determined to be acceptable by Region II. The

inspector held discussions with the cognizant engineer and examined the

corrective actions as stated in the letter of response. The inspector

concluded that GPC had determined the full extent of the subject

deviation, performed the necessary survey and followup actions, to

correct the present conditions and developed the necessary corrective

actions to preclude recurrence of similar circumstances.

The

corrective actions identified in the letter of response have been

1

implemented.

c.

(Closed) Deviation 50-424/86-59-03 and 50-425/86-26-03:

" Failure to

Install Electrically Interlocked and Alarmed Control Room Doors as

Committed"

GPC letters of response dated September 25, 1986 and October 31, 1986

'

have been reviewed and determined to be acceptable by Region II. The

inspector held discussions with the cognizant engineer and examined the

corrective actions as stated in the letter of response. The inspector

concluded that GPC had determined the full extent of the subject

deviation, performed the necessary survey and follow-up actions, to

correct the present conditions and developed the necessary corrective

actions to preclude recurrence of similar circumstances.

The

corrective actions identified in the letter of response have been

implemented.

d.

(Closed) Violation 50-424/86-72-01 and 50-425/86-34-01:

" Failure to

Establish Adequate Measures to Protect Installed Materials and

Equipment from Temporary Construction Loads"

GPC letter of response dated October 31, 1986 has been reviewed and

determined to be acceptable by Region II.

The inspector held

discussions with the cognizant engineer and examined the corrective

actions as stated in the letter of response. The inspector concluded

that GPC had determined the full extent of the subject violation

performed the necessary survey and followup actions, to correct the

present conditions and developed the necessary corrective actions to

preclude recurrence of similar circumstances. The corrective actions

identified in the letter of response have been implemented.

1

.

-

-

.

.

.

3

e.

(Closed) Viola' tion 50-425/86-72-02 and 50-425/86-34-02:

" Failure to

Assure Applicable Requirements are Included in Procurement Documents"

GPC letters of response dated October 31, 1986 has been reviewed and

determined to be acceptable by Region II.

The inspector held

discussions with the cognizant engineer and examined the corrective

actions as stated in the letter of response. The inspector concluded

that GPC had determined the full extent of the subject nonconformance

performed the necessary survey and follow-up actions, to correct the

present conditions and developed the necessary corrective actions to

preclude recurrence of similar circumstances.

The corrective actions

identified in the letter of response have been implemented.

f.

(Closed) Unresolved Item 50-424/86-59-04 and 50-425/86-26-04: " Design

Control for Control Room Doors"

This matter concerns the fact that FSAR Section 6.4.2.2.2 states: "To

minimize inleakage, the control room access doors are equipped with

self-closing devices that shut the doors automatically following the

passage of personnel. Alarms are also provided to annunicate if any of

the doors are open after a changeover to emergency operation. Two sets

of electrically interlocked doors with a vestibule between acting as an

airlock, are provided at each of the two entrances and the emergency

exit to the combined control room and associated spaces."

This

however, is not the as-built condition. The doors to the control room

are installed in pairs, but they are not electrically interlocked and

alarms are not provided to annunciate if any of the doors are open

after a changeover to emergency operation.

At the time of the inspection reported in 50-424/86-59 and 50-425/

86-26, it appeared that the above was the result of a failure of

the design control system to establish adequate measures to assure

selection and review for suitability of application of materials,

parts, and equipment that are essential to the safety-related functions

of structures, systems, and components, but this could not be solidly

substantiated.

The licensee indicated they would investigate the

matter.

The licensee determined that the root cause of the above is as follows:

Control

building floor plan drawing AX1011A04, Rev. 9,

issued

November 12, 1981, showed that the two sets of doors at the entrances

are electrically interconnected and the one set of doors at the

emergency exit is locked and alarmed. On revision ten of the same

drawing, issued August 11, 1982, the interlock / alarm requirements were

removed from the drawing. The original design included the interlock

fiature and this feature was removed from the design drawing during the

l

- .

-

-

_ _ _ _ _ _ _ _

_ - _ _

.

4

design evolution' process.

The original input for the VEGP FSAR was

developed in part based on the FSAR descriptions utilized by previously

licensed Bechtel plants of similar design.

This input was then

modified as necessary to reflect the specifics of the VEGP design. The

review process failed to identify the inconsistency between the VEGP

design detail and that described in the input with respect to the

interlock and alarm features.

The Vogtle Nuclear Project Design Manual, Section 3.4.6, requires

the following:

Every design criteria dealing with safety-related

structures, systems, or components shall include a separate section

entitled, "PSAR Comparison."

In this section, every substantive

difference between PSAR commitments and the current design shall be

identified and briefly described.

These comparisons will form the

basis for preparation of the FSAR.

Clearly the above difference was

not identified in the "PSAR Comparison" section which caused the

defacto false statement to be carried over in to the FSAR.

The

licensee stated that had the NRC not identified the above difference,

the plant would become operational with the defacto false statement

unidentified.

The above is of concern to the commission because the FSAR is the

official vehicle by which construction permit holders report the

as-built configuration of power reactor facilities to the commission

for consideration of operations licensing.

In view of the above it is evident that the licensee failed to follow

procedure (Vogtle Nuclear Project Design Manual Section 3.4.6).

For

activities affecting quality failure to follow procedure is a violation

of 10 CFR 50 Appendix B Criterion V.

This matter will be closed as

an unresolved item and opened as violation 50-424/87-11-01/and

50-425/87-07-01:

" Failure to Follow Design Manual for PSAR/FSAR

As-Built Changes."

Within the areas examined no violations or deviations were identified except

as noted in paragraph 3f.

4.

Unresolved Items

Unresolved items were not identified during this inspection.

5.

Independent Inspection Effort

Housekeeping (548348), Material Identification and Control (429028) and

Material Control (429408)

The inspector conducted a general inspection of the Unit 2 Containment, and

both auxiliary control and fuel buildings to observe activities such as

housekeeping, material identification and control; material control, and

storage.

-

-

- -

-

-

-

-

<

.

~

5

Within the. areas examined no violations or deviations were identified.

6.

Safety-Related Heating, Ventilating, and Air Conditioning (HVAC) Systems

(50100)

Observation of Work and Work Activities

a.

Personnel Interviews (Installation Practices)

The inspector interviewed four craftsmen engaged in the fabrication /

installation of seismic supports, ductwork, isolation dampers or

additional safety-related HVAC equipment to confirm the following:

Predefined and approved procedures are followed when it becomes

-

necessary to relocate any seismic support or other safety-related

equipment from its original location specified on drawings.

Any preinstallaticn field repairs or adjustments to the HVAC

-

equipment are performed in accordance with the manufacturer's

instructions and specifications to ensure that proper materials,

replacement parts, and supplies are used, performance requirements

are met and are reviewed by engineering for acceptance.

Personnel engaged in the installation and inspection of safety-

-

related supports, ductwork,

and other safety-related HVAC

equipment have received adequate training to understand and

perform work contained in relevant work and inspection procedures

and instructions.

b.

Installation Activities

The inspector witnessed portions of the installation activities

indicated below to verffy the following:

The latest issue (revision) of applicable drawings or procedures

-

is available to the installers and is being used.

Modifications to supports are approved by appropriate personnel

-

before implementation.

Activity

Component

Welding

Duct Section A-2575A

Welding

Duct Support DS-2072104-35

Within the areas examined, no violations or deviations were identified.

.

w

F

hm-

-

.

.

.

. .

.

.

6

7.

Steel Stiactures and Supports (Unit 2)

The inspector observed welding work activities for steel structures and

supports as described below to determine whether applicable code and

procedure requirements were being met.

The applicable code for the

activities examined was AWS D1.1-1975 and AWS D9.1-1980.

a.

Welding

The below listed welds were examined in process to determine work

conducted in accordance with traveler; welder identification and

,

location; welding procedure assignment; welding technique and sequence;

!

materials identity; weld geometry; fit-up; temporary attachments; gas

purging; preheat; electrical characteristics; shielding gas; welding

equipment condition; interpass temperature; interpass cleaning; process

control systems; identify of welders; qualification of inspection

personnel; and weld history records.

Welding Examined

Duct Section

A-2575A

Duct Support

D5-2072104-35

b.

Welding Filler Material Control (551528)

' The inspector reviewed the licensee's program for control of welding

,

materials to determine whether materials were being purchased,

accepted, stored, and handled in accordance with QA procedures and

applicable code requirements.

The following specific areas were

examined:

Purchasing,

receiving,

storing,

distribution

and

handling

-

procedures, material identification

Welding material, purchasing and receiving records for the

-

following materials were reviewed for conformance with applicable

procedures and code requirements:

Type

Size

Heat / Control No.

ER-705-2

0.035"

F7164

E-7018

3/32"

MM081

E-7018

1/8"

MM070

c.

Welder Qualification (551578)

The inspector reviewed the licensee's program for qualification of

welders and welding operators for compliance with QA procedures and

ASME Code requirements. The applicable code for welding qualification

l

1s ASME B&PV Code Section IX as invoked by GpC Specification X2AG06

Rev. 4 and X4AZ01, Section P.1, Revision 8.

- - -

___

_ - _

.

.

_ _ - _ - _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _

_ - _____ _ _ _ _ _

_ - _ _ - _ _ _ - _ _ _ - _ - _ _ - - _ _ _ _ .

)

1

-

l

7

l

l

.

The following welder qualification status records and " Records of

i

Performance Qualification Test" were reviewed relative to the weld

!

joints listed in paragraph 7a.

!

Weld Symbol

'

36

98

1020

Within the areas examined, no violations or deviations were identified.

8.

Licensee Identified Items

(Closed) Item 424, 425/COR-82-32:

"HVAC Duct Support-Design Inconsist-

encies" (10 CFR 50.55(e))

On September 30, 1982, the licensee notified IE:II of a 50.55(e) item

concerning inconsistencies in HVAC duct support drawings. The final report

was submitted on August 15, 1983.

The inspector of record for report

l

50-424, 425/87-05 noted that the final report indicated that 120 duct

supports were identified as having significant deficiencies.

Further that

modification of these supports had not occurred as of the date of the final

report but was intended after additional correction of the pCI drawings to

conform to design requirements. Cognizant licensee personnel were unable to

locate quality data confirming proof of modification of the 120 supports

during that inspection.

The licensee informed this inspector that the CDR reported 120 defective

drawings which represented 120 supports.

Not all the 120 supports

represented had been fabricated or installed prior to issuance of Stop Work

Notice SW-M-06 in September 1982.

Conditions for the release to continue work were that HVAC contractor only

work to Bechtel Power Corporation (BpC) statused (reviewed for compliance to

design) DS drawings. BpC began statusing all DS drawings in September,

1982.

Design Evaluation Report DER-025 was issued to track this initial statusing

effort which addressed approximately 4700 drawings.

Upon completion of

this statusing effort, BPC identified 120 drawings which had significant

discrepancies from the design drawings.

The licensee was unable to provide the inspector of record for report

50-424, 425/87-05 quality data conforming the acceptability of the 120

supports.

This inspector discussed the above with the licensee noting that the

licensee's final report did not include sufficient information to permit the

evaluation of the corrective actions as the supports requiring corrective

actions could not be identified. The preceeding is clearly contrary to, and

-

- -

-

-

-

- - -

-

-

_ _ _ - _

.

.

8

'therefore, in violation of 10 CFR 50.55(e)(3) which requires the holder of a

construction permit to submit a written report on a reportable deficiency

'

within thirty (30) days. The report shall include a description of the

deficiency, an analysis of the safety implications and the corrective action

'

taken, and sufficient information to permit analysis and evaluation of the

deficiency and of the corrective action. This matter will be identified as

violation 50-424/87-11-02, 50-425/87-07-02:

" Failure to Provide Adequate

Report of Significant Construction Deficiency"

The licensee was finally able to provide this inspector a partial list (51

of the reported 120) of supports. This list was gleaned from private notes

,

of the BPC Engineer in California who identified the 120 deficient drawings.

Of the 51 deficient drawings gleaned, only 16 supports had been fabricated

or installed prior to the stop work notice.

This inspector reviewed

drawings, and inspection documentation for all 16 supports, made a field

)

inspection, and found no deviations from design requirements. Based on the

above inspection and other inspections made by this inspector, of the HVAC

contractor, performed after the stop work notice, and prior to this inspec-

-

j

tion, this matter will be closed as a licensee identified item and opened as

l

violation 50-424/87-11-02 and 50-425/87-07-02: " Failure To Provide Adequate

l

Report Of Significant Construction Deficiency."

i

Within the areas examined no deviations or violations were identified except

j

as noted above.

l

4

L

I

a

i

j

j

l

1