Informs NRC of Current Status of Mark I Torus Attached Piping Program & Plans for Completion of Associated Mods. Mods Progressing Slower than Anticipated Due to Conceptual Designs Developed Into Mods Difficult to Install
ML20207T331
Person / Time
Site: Peach Bottom  
Issue date: 03/18/1987
From: Kowalski S
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To: Muller D
Office of Nuclear Reactor Regulation
References
NUDOCS 8703230447
Download: ML20207T331 (2)


Text

'(-*

4 PHILADELPHIA ELECTRIC COMPANY 23O1 M ARKET STREET P.O. BOX 8699 PHILADELPHI A. PA.19101 MAR 181987 S. J. KOWALSKI VIC E-PR E SID E N T ruesnammeNG A88D RESS ARCM Mr. Daniel R. Muller, Director Docket Nos.: 50-277 BWR Project ' Directorate #2 50-278 Division of BWR Licensing Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555

Subject:

Peach Bottom Atomic Power Station Units 2 & 3 Torus Attached Piping Modifications - Mark I Program Mod 842

References:

(1)

J. F. Stolz (NRC) letter to E. G. Bauer.(PECo),

dated March 6, 1984 (2)

J. S. Kemper (PECo) letter to J. F. Stolz (NRC),

dated June 13, 1985 (3)

J. S. Kemper (PECo) letter to J. F. Stolz (NRC),

dated December 31, 1985 (4) Telephone Conference between J. F. O'Rourke et al (PECo),

and G. Gears et al (NRC), on January 28, 1986 File:

EQUIP 3-1 (Containment (CSC) Mods)

Dear Mr. Muller:

This letter is to inform you of the current status of the Mark I torus attached piping program (Mod 842) and our plans for completion of the associated modifications.

The reference (1) letter transmitted the Safety Evaluation Report (SER)/ Technical Evaluation Report (TER) on PECo's Plant Unique Analysis Report (PUAR). The reference (2) letter reported that all original work scope was complete and that the 'As-Built' Reconciliation program and equipment nozzle evaluation was underway and might lead to additional modifications. The reference (3) letter transmitted the PUAR addendum and described our remaining work and expectation to be complete by the end of the first quarter of 1987. The reference (4) telephone conference resolved staff question regarding both the reference (3) letter and the continuing modification program.

8703230447 870318 of PDR ADOCK 05000277 pf P

PDR

,do

r --

z. 'ib 1 The work of implementing the modifications is progressing but has been-slower than anticipated because the conceptual designs mentioned in the reference (3) letter developed into modifications which were very complex and difficult.to install. Also, availability of resources

.and difficulties in working on equipment with the units operating has limited work progress.. For example, the newly. implemented. required 5-year security clearance check for craftsmen has caused delays in processing the paperwork for getting craft personnel into the plant.

Because of.these conditions, our_ plans for completing the' modifications have been updated and are as follows. Unit 2 is scheduled to come off-line March 14, 1987 for a refueling outage. All work on-the Unit 2 Modifications is expected to be completed by the end of the refueling outage. The work for Unit 3 is expected to be completed by the end of-the 2nd quarter of this year.

Should_you require any further information do not hesitate to contact us.