Forwards Crdr Implementation Plan, Per NRC 840612 Order Confirming Util Commitments Re Implementation of Suppl 1 to NUREG-0737.CRDR Summary Rept Will Be Submitted by 890228
ML20207R535
Person / Time
Site: Millstone 
Issue date: 03/02/1987
From: Mroczka E
NORTHEAST NUCLEAR ENERGY CO., NORTHEAST UTILITIES
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20207R536 List:
References
RTR-NUREG-0737, RTR-NUREG-737 A04135, A4135, NUDOCS 8703170342
Download: ML20207R535 (2)


Text

NORTHEAST UTILITIES c nor.i onic... s io n sir..t. Boriin. connecticut 1

Ir'eU.

iIsEcw.~."

P.o. Box 270 HARTFORD. CONNECTICUT 06141-0270 I,o I[,',*.,7,* ",,c, c~,,,,

(203) 665-5000 2

.c es..o.ca.

March 2, 1987 Docket No. 50-245 A04135 Re: NUREG-0737, Supplement 1 U.S. Nuclear Regulatory Commission Attn:

Document Control Desk Washington D.C.

20555 Gentlemen:

Millstone Nuclear Power Station, Unit No.1 Supplement 1 to NUREG-0737 Control Room Design Review Implementation Plan In a lett.er dated June 12, 1984'*',

the NRC Staff issued an Order confirming various commitments made by Northeast Nuclear Energy Company (NNECO) on behalf of Millstone Unit No. I regarding the implementation of Supplement 1

to NUREG-0737.

This Order requires the submittal by March 2,

1987 of the Control Room Design Review (CRDR) program plan and a

schedule for the submittal of the CRDR Summary Report.

Accordingly, NNECO hereby submits fifteen (15) copies of the Control Room Design Review Implementation Plan for Millstone Unit No. 1.

d In addition, NNECO commits to submitting the CRDR Summary Report for Millstone Unit No.

1 by February 28, 1989.

The time scheduled for this CRDR takes into account the time required to properly prepare a

full scale mockup of the control room.

Previous CRDR's conducted by NNECO have demonstrated the benefits of having a full scale mockup.

Facility limitations at the No. 1 Millstone site prevented preparation of the Millstone Unit control room mock-up until this time.

l I

A schedule for performing the various phases of the CRDR is included in the CRDR Implementation Plan.

In accordance with (1) D.M.Crutchfield letter to W.G.Counsil,

" Orders Confirming Licensee Commitments on Emergency

Response

Capability (Generic Letter 82-33, NUREG-0737)", dated June 12, 1984.

I w 0703170342 870302

{

PDR ADOCK 05000245 PDR p

U.S. Nuclear Regulatory Commission A04135/Page 2 March 7, 1987 Supplement 1 to NUREG-0737, no NRC Staff approval of this CRDR Implementation Plan is necessary prior to the initiation of the CRDR for. Millstone Unit No.

1.

However, we trust that any deficiencies in this plan perceived by the NRC Staff will be brough.t to the attention of NNECO in a timely manner.

Should you have any questions, please c'ontact us.

Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY W 9&/

E.T.pr6c'zka /~

Senror Vice President cc: Dr.T.E.Murley, Region I Administrator J.J.Shea,NRC Project Manager, Millstone Unit No. 1 T.Rebelowski, Resident Inspector, Millstone Unit Nos. 1 and 2 Attachment