Submits Schedule for Implementing ATWS Rule.Implementation of ATWS Rule for Unit 2 Will Be Delayed by One Refueling Outage.Unit 2 in Anticipation of Shift to 24-month Fuel Cycle to Be Implemented W/Spring 1987 Refueling
ML20207R287
Person / Time
Site: Calvert Cliffs  
Issue date: 03/12/1987
From: Tiernan J
BALTIMORE GAS & ELECTRIC CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 8703170064
Download: ML20207R287 (2)


Text

..

A BALTIMORE GAS AND ELECTRIC CHARLES CENTER P. O. BOX 1475 BALTIMORE, MARYLAND 21203 JOSEPH A.TIERNAN Vict PntssotNT NUCLEAR ENERGY March 12,1987 U. S. Nuclear Regulatory Commission Washington, DC 20555 ATTENTION:

Document Control Desk

SUBJECT:

Calvert Cliffs Nuclear Power Plant Unit Nos.1 & 2; Docket Nas. 50-317 & 50-318 Schedule for Compliance with 10 CFR 50.62, Reduction of Risk from ATWS Event

REFERENCES:

(a)

Letter from Mr. S. A. McNeil (NRC), to Mr. 3. A. Tiernan (BG&E),

dated February 10,1987, same subject Gentlemen:

In Reference (a), you asked us to provide our schedule for implementing the ATWS rule in light of the deadillie extension. For the reasons cited in your letter, we will be delaying implementation of the ATWS rule for Unit 2 by one refueling outage. The schedule for Unit I is unchanged.

Our schedule for implementing the ATWS rule is now:

Unit 1............................ Spring 19 88 Unit 2............................ Spring 1989 The Unit 2 date is in anticipation of our shif t to a 24-month fuel cycle to be implemented with the spring 1987 refueling.

Please contact us if you have any questions regarding this matter.

Very truly yours,

/de f$

JAT/ WPM / dim O

t\\0 07@3170064 870312 PDR ADOCK 05000317 P