Discusses Applicability of Surveillance Requirement 4.0.2b to 18 Months & Refueling Interval Surveillance Requirements. Util Expects to Submit Tech Spec Change to Surveillance Requirement by 890301
ML20207L666
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 10/10/1988
From: Shelton D
TOLEDO EDISON CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
1581, NUDOCS 8810170393
Download: ML20207L666 (2)


Text

'

TOLEDO

%s EDISON u - a.., :r..,

OcNato C. S-ELTON Docket tio. 50-346

  • l;p p "

License No. tiPF-3 Serial fio. 1581 Oc tober 10, 1988 United States fluelear Regulatory Commission Document Control Desk Vashington, D. C.

20555 Subj ec t : Applicability of Surveillance Requirement 4.0.2b to 18-month and Refueling Interval Surveillances Gentlemen During a telephone conference call betveen Tol(do Edison personnel and !!RC Staff (A. V. DeAgazio and T. Dunning) on September 7, 1988, Toledo Edison discussed the applicability of Surveillance Requirement (SR) 4.0.2b to 18-month and refueling interval surveillance requirements.

SR 4.0.2 states:

"4.0.2 Each Surveillance Requirement shall be performed within the specified time interval vith a.

A maximum allovable extension not to exceed 25% of the surveillance interval, and b.

A total maximus co'obined interval time for any 3 consecutive tests not to exceed 3.25 times the specified stirveillance interval."

Due ;rimarily to the Davis-Besse shutdovn (non-tefueling outage) in 1985 for an extended period of time, SR 4.0.2b vould require a shutdovn specifically for performing approximately 23 of these surveillance tests before the planned Cycle 6 refueling outage.

In the telephone conference call, Toledo Edison explained that an evaluation of the above situation has determined that thete is sufficient justification to pursue a technical specification change to delete the applicability of the SR *.0.2b requireeent from 18-month and 1

refueling interval SRs. The Davis-Besse Cycle 6 refueling outage is presently scheduled to com ence in February, 1990.

The need to shutdovn and perform a refueling surveillance vould first be encountered in Augt.st. 1989.

To support planning efforts. ToleJo Edison intends to request that a change to this SR be issued by the h'KC by March 1,1989.

i;RC Staff personnel briefly described a tGC Ceneric Letter which is presently being prepared for issuance no later than December, 1988 vhich vould encourage i

fI, 00 T*,E Tc.ECO E: 30'. c:W1M E r 3:', r; A; A 3:e W.:3

,:.,o, c

Tc, Era c- ; a u 0810170393 001010 l

i DR ADOCK 05000346 i

PNU

Dockot No. 50-346 License No. NPF-3 Serial 1581 Page 2 action similar to that Davis-Besse intends to pursue for the refueling interval SRs.

Toledo Edison recommends that the Generic Letter also address those SRs which state... "at least once per 18 months..." and "... as least once per 18 months, during shutdown..." similar to the refueling SRs.

Additionally, Toledo Edison requests that the NRC expedite issuance of the Generic Letter in order to support expeditious NRC Staff reviev and approval of the Davis Besse technical specification change request when it is submitted.

Should you require additional information, please contact Mr. R. V. Schrauder, Nuclear Licensing Manager, at (419) 249-2366.

Very truly yours, j'i f Lu CAB /dlm cca P. Byron, DB-1 NRC Resident Inspector A. V. DeAgazio, DB-1 NRC Senior Project Manager A. B. Davis, Regional Administrator, NRC Region III i