Killona, LA 70066 Te! 504 739 6242 C. Ewing, lil Nuclear Safety & Regulatory Affairs W3F1-99-0046 A4.05 PR March 11,1999 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555
Subject:
Waterford 3 SES Docket No. 50-382 License No. NPF-38 15 Day Special Report on the Inservice inspection of the Waterford 3 Steam Generators (SR-99-001-00)
Gentlemen:
Attached is Special Report (SR) Number SR-99-001-00 for Waterford Steam Electric Station Unit 3. This report provides the Refuel 9 Inservice inspection summary of steam generator tube plugging or sleeving. Since Waterford 3 has not installed sleeves, no sleeving information is provided in the attachment. This condition is being reported pursuant to 10CFR50.36(c)(2) and Technical Specifications 4.4.4.5.a and 6.9.2.
Very truly yours,
,/
j f
f 4oq E.C. Ewing Director Nuclear Safety & Regulatory Affairs ECE/TMM/ssf 160017 Attachment
~
9903160263 990311 PDR ADOCK 05000302 e
PDR.3 g
15 Day Special Report on the Inservice inspection of the Waterford 3 Steam. Generators (SR-99-001-00)
W3F1-99-0046 Page 2 March 11,1999 cc:
E.W. Merschoff, NRC Region IV C.P. Patel, NRC-NRR A.L. Garibaldi P. Lewis -INPO Records Center J. Smith N.S. Reynolds NRC Resident inspectors Office Administrator - LRPD
g...._
._m__.._
Special Report i
e SR-99-001-00 Steam Generator Eddy Current Examination (9th Refueling)
On March 6,1999, Waterford 3 completed a 100% inservice eddy current bobbin coil full length examination of each Steam Generator (S/G) and a 100% hot leg top of the tubesheet. This report is submitted in accordance with Technical Specification (TS) 4.4.4.5.a, which requires reporting the number of tubes plugged or sleeved in each S/G within 15 days of completing inservice inspection (ISI) of S/G tubes pursuant to TS 6.9.2. A follow-up report will be submitted in accordance with TS 4.4.4.5.b by March 6,2000.
The total number of tubes, which have been plugged in each S/G, is shown below:
SIG #1 SIG #2 Manufacturing /Preservice 6
20 Batwing (Preventive Plugging) 149 149 First Refueling 0
1 Second Refueling 3
0 Third Refueling 10 9
i Fourth Refueling
- Preventive Plugging as a result of ECT 4
5
- Batwing Preventive Plugging 156 156 Fifth Refueling 4
5
~ Sixth Refueling
- Preventive Plugging as a result of ECT 1
2
- 40% Thru-WallIndications 2
0 1
1
{
(Eont'd.)
SIG #1 SIG#2 Seventh Refueling
- Preventive Plugging as a result of ECT 6
3
- > 40% thru-wallindications 2
0
- Single circumferentialindications 6
1 Eighth Refueling
- Top of the tubesheet Loose Part Indications 3
3 Multiple Circumferential Indications 2
0 Single Volumetric Indications 2
1 Multiple AxialIndications 1
0 Single CircumferentialIndication 12 7
Single AxialIndications 9
7
- Wear Indications 240% Thru Wall 0
7 Ninth Refueling
- Top of the tubesheet:
Single Volumetric Indications 0
1 Single CircumferentialIndication 2
3 Single AxialIndication=
3 0-Indications at Eggerates:
Single AxialIndications 5
3 Single Circumferential Indications 0
1
- Wear Indications 240% Thru Wall 1
1
- Wear Indications <40% Preventively Plugged 1
1 The total number of tubes which have been plugged in each S/G:
SIG #1 S/G#2 Total:
390 386 s
2 f
)