9, y:
~
Center for Nuclear Waste Regulatory Analyses 6220 CUI.EBRA ROAD + P.O. DRAWER 28510
- FAX (210) 522 5155 February 26,1999 Contract No. NRC-02-97-009 Account No. 20-1402-158 U.S. Nuclear Regulatory Commission Attn: Mr. John J. Linehan, Director Office of Nuclear Material Safety and Safeguards Program Management, Policy Development and Analysis Staff Mail Stop 8-A23 Washington, DC 20555
Subject:
CNWRA Program Manager's Periodic Report on Activities of the Center for Nuclear Waste Regulatory Analyses for Period 5-FY1999
)
i
Dear Mr. Linehan:
The enclosed " Program Manager's Periodic Report" (PMPR) documents the progress and financial status of the Center for Nuclear Waste Regulatory Analyses for the period January 16-February 12,1999. Its contents comply with the requirements of section F.1.5. of the referenced contract. A diskette containing the PMPR in Wordperfect 8 format is also enclosed.
Cost variance analyses are provided for the Division of Waste Management (D1035), Tank Waste Remediation System (J5164), Three Mile Island Unit 2 Independent Spent Fuel Storage Installation (i5186), Dry Transfer System (J5206), Centralized Interim Storage Facility (D1035), Private Fuel Storage Facility (J5226), and Savannah River Site Aluminum-Based Spent Fuel (J5210) Job Codes, as well as for composite spending on this contract. All variances are expressed with regard to the current operations plans.
During period 5, one new intermediate milestone was introduced and five schedule changes were made as reflected in table 2. Four deliverables were transmitted as indicated in table 3.
,j Please contact me or Mr. Henry Garcia if you have questions regarding this epo 7
/
~ gg Sincer y.
rs, f ' 4/16 A
f Wesley C. Patrick
,g President HFG/lg Enclosures cc:
B. Meehan J. Greeves S. Shankman C. Paperiello J. Holonich S. Bahadur D. DeMarco E. Ten Eyck M. Federline B. Stiltenpole (38)
E. Brach CNWRA Directors / Element Managers W. Kane F. Miraglia S. Boyanowski (SwRI Contracts) enn<nn 9903110189 990226 PDR WASTE tm wM-11 PDR g.