g DCS PHILADELPHIA ELECTRIC COMPANY 2301 M ARKET STREET P.O. BOX 8699 PHILADELPHI A. PA.19101 12158841 4000 December 24, 1986 Mr. James M. Taylor, Director
~
Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission
)
E Washington, D.C.
20555
SUBJECT:
Peach Bottom Atomic Power Station Unit 3 Order of December 12, 1986 - EA 86-59 7
Dear Mr. Taylor:
I Your letter dated December 12, 1986 forwarded an Order which imposed on Philadelphia Electric Company civil penalties in
..L-the amount of Two Hundred Thousand Dollars ($200,000).
The civil penalties stem from an event that occurred at Peach Bottom Unit 3 on March 17-18, 1986 involving the withdrawal of a control rod during reactor startup in a sequence different from that specified in the control rod program.
Please find enclosed a check payable to the Treasurer of the United States in the amount of Two Hundred Thousand Dollars
&g in payment of the aforementioned civil penalties in compliance M
with the Order.
Should you have any questions or require additional information, please do not hesitate to contact us.
g b
k Very truly yours, fog j
J. S. Kemper i
Senior Vice President Engineering and Production I