ML20206T593

From kanterella
Jump to navigation Jump to search
Responds to 851203-06 Regulatory Effectiveness Review Rept .Discusses Possibility of Extending Response Period by Addl 30 Days.Response Expected by 861027
ML20206T593
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 09/16/1986
From: Zach J
WISCONSIN ELECTRIC POWER CO.
To: Lear G
Office of Nuclear Reactor Regulation
References
NUDOCS 8610070081
Download: ML20206T593 (1)


Text

,

l Wisconsin Electnc ma cower l\\\\l POINT BEACH NUCLEAR PLANT 6610 NUCLEAR ROAD TWO RIVERS. WISCONSIN 54241 (414) 755-2321 September 16, 1986 Mr. George Lear, Director PWR Project Directorate #1 Division of PWR Licensing -A Office of Nuclear Reactor Regulation Bethesda, MD 20014

Dear Mr. Lear:

The report of the Regulatory Effectiveness Review conducted December 3-6, 1985, was dated August 7, 1986. You requested that we respond within 45 days.

On September 3, 1986, Mr. R. Krukowski, our Security Supervisor, discussed with Mr. Timothy Colburn the possiblity of extending the response period by an additional 30 days.

Mr. Colburn requested that we advise Mr. Herbert Berkow of our intention to respond, and the fact we will need at least an additional 30 days to develop an appropriate reply. We intend to have our response to you by October 27.

Your cooperation is appreciated.

Very truly yours, C C Jame J. Zach Manager yce cc:

Mr. R. L. Hague gf (f

lGO 6

)

P ia

_ _ _ _ _ _ _ _ _ _