ML20206R986

From kanterella
Jump to navigation Jump to search
Advises That Fuel Will Be Loaded in Unit on or About 861015, Per 851118 Fuel Load Schedule
ML20206R986
Person / Time
Site: Braidwood Constellation icon.png
Issue date: 09/16/1986
From: Reed C
COMMONWEALTH EDISON CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
2114K, NUDOCS 8609220002
Download: ML20206R986 (1)


Text

-

Commonwealth Edison 1

72 West Adams Streat. Chicago, Illinois

) Address Reply to: Post Office Box 767

\\d Chicago, Illinois 60690 - 0767 September 16, 1986 Mr. Harold R. Denton U.S. Nuclear Regulatory Commission

-Office of Nuclear Reactor Regulatory Washington, DC. 20555

Subject:

Revision to the Expected Fuel Load Date for Braidwood Station Unit 1 NRC Docket No. 50-456 Reference (a):

Cordell Reed letter to H.R. Denton dated November 18, 1985

Dear Mr. Denton:

Reference (a) provided you with Commonwealth Edison load schedule for Braidwood Company's best estimate of the fuelIt stated that the unit would be ready to load fuel Station Unit 1.

no later than September 30, 1986.

We have completed a detailed review of the activities remaining to support fuel load which indicates that an additional two weeks will be required to complete critical path activities.

Thus, we estimate that fuel can be loaded in the subject unit on or about October 15, 1986.

Should any contingencies arise to cause fuel load to occur later than this date, I will keep you advised.

Very truly yours,

(

Cordell Reed Vice President DHS/klj cc:

J. G. Keppler 2114K 8609220002 860916 PDR ADOCK0500g6 8om