MONTHYEARML20206L4921999-05-10010 May 1999 Summary of 990416 Meeting with Util in Rockville MD to Discuss Matter Re SG Operational Assessments for Current Operating Cycle at Plant,Unit 1 ML20206G1181999-05-0505 May 1999 Summary of 990419-20 Meeting with Southern Nuclear Operating Co,Inc in Rockville,Md Re Matters Related to Implementation of Improved Standard TSs at Farley Nuclear Plant,Units 1 & 2 ML20198S2581998-12-31031 December 1998 Summary of 981215 Meeting with Southern Nuclear Operating Co in Rockville,Md to Discuss Technical Issues Associated with Kaowool Fire Barriers Installed at Farley Nuclear Plant, Units 1 & 2 ML20198M7031998-12-29029 December 1998 Summary of 981215 Meeting with Southern Nuclear Operating Co,Inc in Rockville,Md Re Matters Related to Current Steam Generator Tube Insp at Farley Nuclear Plant,Unit 1.List of Attendees & Meeting Handouts,Encl ML20195J1361998-11-17017 November 1998 Summary of 981026 Meeting with Util in Rockville,Md to Discuss Plant Analysis of Replacement SG & Evaluation of Other Small Changes for FNP Units 1 & 2 Best Etimate Large Break loss-of-coolant Accident ML20155C2451998-10-29029 October 1998 Summary of 981008 Meeting with Southern Nuclear Operating Co in Rockville,Md Re Util Repair of Joseph M Farley Nuclear Plant,Unit 1 B SG Tubes & Eddy Current Test Data for Tube R25C51 Submitted by .List of Attendees Encl ML20155C4141998-10-29029 October 1998 Summary of 981014 Meeting W/Southern Nuclear Operating Co, Inc in Rockville,Md Re Justification of Certain TS Changes Needed to Implement Improved Std TS & NRC Staff Request for Addl Info, .List of Attendees Encl ML20203C5501997-12-0505 December 1997 Summary of 971120 Meeting W/Southern Nuclear Operating Co to Discuss Matters Related to Steam Generator Replacement Projects Proposed for Both Farley Nuclear Units.List of Attendees Enclosed ML20199A0161997-10-30030 October 1997 Summary of 971022 Meeting W/Util in Rockville,Md Re Initiatives That Focus on Planned Licensing Actions & Corrective Measures Re Problems Considered by Mgt to Warrant Special Attention ML20217E1531997-09-25025 September 1997 Summary of 970916 Meeting W/Southern Nuclear Operating Co, Inc in Rockville,Maryland Re Licensees Improved Std TS Conversion Application & Schedule for Submittal.List of Meeting Attendees & Meeting Handouts Encl ML20217L8701997-08-14014 August 1997 Summary of 970731 Meeting W/Southern Nuclear Operating Co, Inc in Birmingham,Al Re Plant Status,Major Problems & Other Topics at Farley,Hatch & Vogtle Nuclear Plants.List of Attendees & Presentation Handouts Encl ML20134K7521997-02-12012 February 1997 Summary of 970205 Meeting W/Util & W for Initial Discussion of Utils Plans & Schedule for Submitting Proposed TS Amend Request Re Use of Direct Tube Repair in Repair of SG Tubes. List of Participants & Matl Presented Encl ML20056C5231993-06-18018 June 1993 Summary of 930602 Meeting W/Util Re Plant Proposal for Removing 2C Emergency Diesel Generator from TS as Part of Farley Implementation of Station Blackout Rule.List of Attendees Encl ML20056D6661993-06-0101 June 1993 Summary of Operating Reactors Events Briefing 93-19 on 930526 ML20128C1261992-11-25025 November 1992 Summary of 921026 Meeting W/Util in Houston County,Al Re Future Submittals Planned by Util,Status of NRC Review of Previous Submittals,Responses to Generic Communications,Nrc Concerns & General Coordination of Licensing Activities ML20128A0111992-11-25025 November 1992 Summary of 920727 Meeting W/Util,Westinghouse & Pnl in Rockville,Md Re Discussions on Steam Line Break Leakage Issues Relating to Licensees SG Tube Alternate Plugging Criteria Proposal.List of Attendees Encl ML20058K1841990-12-0404 December 1990 Summary of 901107 Meeting W/Util in Rockville,Md Re Steam Generator Tube Collapse Under Combined LOCA & Safe Shutdown Earthquake Loads ML20247R0161989-09-21021 September 1989 Summary of Operating Reactors Events Meeting 89-34 on 890920 to Brief Senior Managers & Regional Offices on Selected Events That Occured Since Last Meeting ML20247K0901989-05-23023 May 1989 Summary of 890517 Meeting W/Inpo Re Similarities & Differences Between Performance Indicator Programs.Detailed Discussion Encl ML20247K1011989-05-16016 May 1989 Summary of 890517 Meeting W/Inpo in Bethesda,Md Re Similarities & Differences Between INPO & NRC Performance Indicators ML20150B2131988-07-0505 July 1988 Summary of 880601 Meeting W/Util in Rockville,Md Re Antitrust 2.206 Petition.Attendance List Encl ML20153B0061988-06-17017 June 1988 Summary of CRGR Meeting 137 on 880608 Re Proposed Draft Rule 10CFR52 Concerning Site Permits,Design Certifications & Combined Licenses & Proposed NRC Bulletin Regarding Thermal Stresses in Piping.List of Attendees Encl ML20153B0011988-06-17017 June 1988 Summary of CRGR Meeting 137 on 880608 Re Proposed Draft Rule 10CFR52 Concerning Site Permits,Design Certifications & Combined Licenses & Proposed NRC Bulletin Regarding Thermal Stresses in Piping.List of Attendees Encl.W/O Stated Encl ML20151C9691988-04-0808 April 1988 Summary of 880406 Meeting W/Util & Alabama Electric Power Cooperative in Rockville,Md Re Status of Settlement Proposal Presented to NRC in Jan 1988,per 2.206 Antitrust Proceeding. List of Attendees Encl ML20148L1801988-03-25025 March 1988 Summary of 880318 Meeting W/Utils in Rockville,Md Re Info That Would Be Required in Submittal of Amends to Licenses & CP Held by Utils.Attendees List & Viewgraphs Encl ML20196J7851988-03-10010 March 1988 Summary of Operating Reactors Events Meeting 88-10 on 880308.List of Attendees & Significant Elements of Events Discussed Encl ML20150C7261988-03-0909 March 1988 Summary of 880302 Meeting W/Utils in Rockville,Md Re Formation of Separate Operating Organization.List of Attendees & Viewgraphs Encl ML20149M1771988-02-0808 February 1988 Summary of 880115 Meeting W/Util Discussing Generic Implications of Cracked 6-inch Safety Injection Pipe at Plant.Meeting Attendees & Agenda Encl ML20196B1461988-01-11011 January 1988 Summary of CRGR Meeting 127 on 871223 Re Proposed Resolution of USI A-47, Safety Implications of Control Sys in LWR Nucl Nuclear Power Plants. Committee Recommended Forwarding Ofc Package to EDO Following Incorporation of CRGR Comments ML20149F4741988-01-0707 January 1988 Summary of Operating Reactors Events Meeting 88-01 on 870105 Re Events That Occurred Since 871222.List of Attendees & Viewgraphs Encl ML20237F2471987-12-18018 December 1987 Summary of Operating Reactor Events Meeting 87-44 on 871215. List of Attendees,Events Discussed,Significant Elements of Events & Summary of Reactor Scrams Encl ML20236P2841987-11-0505 November 1987 Summary of Operating Reactors Events Meeting 87-38 on 871103.List of Attendees,Viewgraphs & Summary of Reactor Scrams Encl ML20236L3201987-11-0505 November 1987 Summary of 870924 Meeting W/Util,Bechtel & Rl Cloug Assoc Re Problems Concerning Qualification of V-Type Electrical Splices at Facility.Attendance List Encl NUREG-1192, Summary of Operating Reactor Events Meeting 87-37 on 871027. Viewgraphs & Summary of Reactor Scrams Encl1987-10-28028 October 1987 Summary of Operating Reactor Events Meeting 87-37 on 871027. Viewgraphs & Summary of Reactor Scrams Encl ML20235W9431987-10-13013 October 1987 Summary of Operating Reactors Events Meeting 87-32 on 870922.Notes That Meeting 87-31 Did Not Occur.List of Attendees & Events Discussed & Significant Elements of Events Encl ML20216J4431987-06-26026 June 1987 Summary of 870619 Meeting W/Util & Southern Co Svcs to Discuss Commission Policy Statement for Tech Spec Improvements on Plant Specific Basis.List of Attendees & Pilot Application of Commission Interim Policy... Encl ML20214S9971987-06-0202 June 1987 Summary of 870505 Meeting W/Util Re Planned Safeguards Mods at Facility ML20236S4401986-12-30030 December 1986 Summary of 861120 Meeting W/Util Re Proposed Tech Spec Changes to Snubber Surveillance Insp Intervals ML20212E3601986-12-23023 December 1986 Summary of 861120 Meeting W/Bechtel,Southern Co,Svcs & Alabama Power Co in Bethesda,Md Re Proposed Tech Spec Changes to Snubber Surveillance Insp Intervals.Meeting Agenda,List of Attendees & Viewgraphs Encl ML20206L9081986-08-11011 August 1986 Summary of Operating Reactor Events Meeting 86-27 on 860804 W/Ofc Director,Div Directors & Representatives Re Briefing on Events Which Occurred Since Last Meeting on 860728.List of Attendees & Viewgraphs Encl ML20211P1361986-07-16016 July 1986 Summary of 860707 Operating Reactor Events Meeting 86-23 W/ Div Directors & Representatives Re Events Since Last Meeting on 860630.Notification of Inability to Meet Assigned Target Completion Dates for Actions Requested.Viewgraphs Encl ML20211G7781986-06-13013 June 1986 Summary of Operating Reactor Events Meeting 86-19 on 860609. List of Attendees,Events Discussed & Status of Previous Assignments Encl ML20154P0071986-03-12012 March 1986 Summary of Operating Reactor Events 860303 Meeting 86-06 W/Ornl Re Events Occurring Since 860224 Meeting.Followup Review Assignments,Status of Previous Assignments,List of Attendees & Viewgraphs Encl ML20154C9931986-02-24024 February 1986 Summary of Operating Reactors Event Meeting 86-04 on 860210.List of Attendees,Briefing & Reactor Scram Summaries Encl ML20132C3761984-08-0808 August 1984 Trip Rept of 840618-20 Site Visit to Observe INPO Accreditation Team to Determine Adequacy of Process as Means of Implementing Sys Approach to Training in Commercial Nuclear Power Industry ML20126L2331981-05-0101 May 1981 Summary of 810429 Meeting W/Pwr Owners Group Re Thermal Shock to Reactor Pressure Vessels.All Parties Agree That Thermal Shock W/Subsequent Repressurization Is Safety Concern Needing Prompt Evaluation ML20062K3241980-11-28028 November 1980 Summary of 801030 Meeting W/Util & Bechtel Re Means by Which Power Cables in Containment Are Protected from Overcurrent. Draft Response to NRC Position 040.15 Encl 1999-05-05
[Table view] Category:MEETING SUMMARIES-INTERNAL (NON-TRANSCRIPT)
MONTHYEARML20206L4921999-05-10010 May 1999 Summary of 990416 Meeting with Util in Rockville MD to Discuss Matter Re SG Operational Assessments for Current Operating Cycle at Plant,Unit 1 ML20206G1181999-05-0505 May 1999 Summary of 990419-20 Meeting with Southern Nuclear Operating Co,Inc in Rockville,Md Re Matters Related to Implementation of Improved Standard TSs at Farley Nuclear Plant,Units 1 & 2 ML20198S2581998-12-31031 December 1998 Summary of 981215 Meeting with Southern Nuclear Operating Co in Rockville,Md to Discuss Technical Issues Associated with Kaowool Fire Barriers Installed at Farley Nuclear Plant, Units 1 & 2 ML20198M7031998-12-29029 December 1998 Summary of 981215 Meeting with Southern Nuclear Operating Co,Inc in Rockville,Md Re Matters Related to Current Steam Generator Tube Insp at Farley Nuclear Plant,Unit 1.List of Attendees & Meeting Handouts,Encl ML20195J1361998-11-17017 November 1998 Summary of 981026 Meeting with Util in Rockville,Md to Discuss Plant Analysis of Replacement SG & Evaluation of Other Small Changes for FNP Units 1 & 2 Best Etimate Large Break loss-of-coolant Accident ML20155C2451998-10-29029 October 1998 Summary of 981008 Meeting with Southern Nuclear Operating Co in Rockville,Md Re Util Repair of Joseph M Farley Nuclear Plant,Unit 1 B SG Tubes & Eddy Current Test Data for Tube R25C51 Submitted by .List of Attendees Encl ML20155C4141998-10-29029 October 1998 Summary of 981014 Meeting W/Southern Nuclear Operating Co, Inc in Rockville,Md Re Justification of Certain TS Changes Needed to Implement Improved Std TS & NRC Staff Request for Addl Info, .List of Attendees Encl ML20203C5501997-12-0505 December 1997 Summary of 971120 Meeting W/Southern Nuclear Operating Co to Discuss Matters Related to Steam Generator Replacement Projects Proposed for Both Farley Nuclear Units.List of Attendees Enclosed ML20199A0161997-10-30030 October 1997 Summary of 971022 Meeting W/Util in Rockville,Md Re Initiatives That Focus on Planned Licensing Actions & Corrective Measures Re Problems Considered by Mgt to Warrant Special Attention ML20217E1531997-09-25025 September 1997 Summary of 970916 Meeting W/Southern Nuclear Operating Co, Inc in Rockville,Maryland Re Licensees Improved Std TS Conversion Application & Schedule for Submittal.List of Meeting Attendees & Meeting Handouts Encl ML20217L8701997-08-14014 August 1997 Summary of 970731 Meeting W/Southern Nuclear Operating Co, Inc in Birmingham,Al Re Plant Status,Major Problems & Other Topics at Farley,Hatch & Vogtle Nuclear Plants.List of Attendees & Presentation Handouts Encl ML20134K7521997-02-12012 February 1997 Summary of 970205 Meeting W/Util & W for Initial Discussion of Utils Plans & Schedule for Submitting Proposed TS Amend Request Re Use of Direct Tube Repair in Repair of SG Tubes. List of Participants & Matl Presented Encl ML20056C5231993-06-18018 June 1993 Summary of 930602 Meeting W/Util Re Plant Proposal for Removing 2C Emergency Diesel Generator from TS as Part of Farley Implementation of Station Blackout Rule.List of Attendees Encl ML20056D6661993-06-0101 June 1993 Summary of Operating Reactors Events Briefing 93-19 on 930526 ML20128C1261992-11-25025 November 1992 Summary of 921026 Meeting W/Util in Houston County,Al Re Future Submittals Planned by Util,Status of NRC Review of Previous Submittals,Responses to Generic Communications,Nrc Concerns & General Coordination of Licensing Activities ML20128A0111992-11-25025 November 1992 Summary of 920727 Meeting W/Util,Westinghouse & Pnl in Rockville,Md Re Discussions on Steam Line Break Leakage Issues Relating to Licensees SG Tube Alternate Plugging Criteria Proposal.List of Attendees Encl ML20058K1841990-12-0404 December 1990 Summary of 901107 Meeting W/Util in Rockville,Md Re Steam Generator Tube Collapse Under Combined LOCA & Safe Shutdown Earthquake Loads ML20247R0161989-09-21021 September 1989 Summary of Operating Reactors Events Meeting 89-34 on 890920 to Brief Senior Managers & Regional Offices on Selected Events That Occured Since Last Meeting ML20247K0901989-05-23023 May 1989 Summary of 890517 Meeting W/Inpo Re Similarities & Differences Between Performance Indicator Programs.Detailed Discussion Encl ML20247K1011989-05-16016 May 1989 Summary of 890517 Meeting W/Inpo in Bethesda,Md Re Similarities & Differences Between INPO & NRC Performance Indicators ML20150B2131988-07-0505 July 1988 Summary of 880601 Meeting W/Util in Rockville,Md Re Antitrust 2.206 Petition.Attendance List Encl ML20153B0011988-06-17017 June 1988 Summary of CRGR Meeting 137 on 880608 Re Proposed Draft Rule 10CFR52 Concerning Site Permits,Design Certifications & Combined Licenses & Proposed NRC Bulletin Regarding Thermal Stresses in Piping.List of Attendees Encl.W/O Stated Encl ML20153B0061988-06-17017 June 1988 Summary of CRGR Meeting 137 on 880608 Re Proposed Draft Rule 10CFR52 Concerning Site Permits,Design Certifications & Combined Licenses & Proposed NRC Bulletin Regarding Thermal Stresses in Piping.List of Attendees Encl ML20151C9691988-04-0808 April 1988 Summary of 880406 Meeting W/Util & Alabama Electric Power Cooperative in Rockville,Md Re Status of Settlement Proposal Presented to NRC in Jan 1988,per 2.206 Antitrust Proceeding. List of Attendees Encl ML20148L1801988-03-25025 March 1988 Summary of 880318 Meeting W/Utils in Rockville,Md Re Info That Would Be Required in Submittal of Amends to Licenses & CP Held by Utils.Attendees List & Viewgraphs Encl ML20196J7851988-03-10010 March 1988 Summary of Operating Reactors Events Meeting 88-10 on 880308.List of Attendees & Significant Elements of Events Discussed Encl ML20150C7261988-03-0909 March 1988 Summary of 880302 Meeting W/Utils in Rockville,Md Re Formation of Separate Operating Organization.List of Attendees & Viewgraphs Encl ML20149M1771988-02-0808 February 1988 Summary of 880115 Meeting W/Util Discussing Generic Implications of Cracked 6-inch Safety Injection Pipe at Plant.Meeting Attendees & Agenda Encl ML20196B1461988-01-11011 January 1988 Summary of CRGR Meeting 127 on 871223 Re Proposed Resolution of USI A-47, Safety Implications of Control Sys in LWR Nucl Nuclear Power Plants. Committee Recommended Forwarding Ofc Package to EDO Following Incorporation of CRGR Comments ML20149F4741988-01-0707 January 1988 Summary of Operating Reactors Events Meeting 88-01 on 870105 Re Events That Occurred Since 871222.List of Attendees & Viewgraphs Encl ML20237F2471987-12-18018 December 1987 Summary of Operating Reactor Events Meeting 87-44 on 871215. List of Attendees,Events Discussed,Significant Elements of Events & Summary of Reactor Scrams Encl ML20236P2841987-11-0505 November 1987 Summary of Operating Reactors Events Meeting 87-38 on 871103.List of Attendees,Viewgraphs & Summary of Reactor Scrams Encl ML20236L3201987-11-0505 November 1987 Summary of 870924 Meeting W/Util,Bechtel & Rl Cloug Assoc Re Problems Concerning Qualification of V-Type Electrical Splices at Facility.Attendance List Encl NUREG-1192, Summary of Operating Reactor Events Meeting 87-37 on 871027. Viewgraphs & Summary of Reactor Scrams Encl1987-10-28028 October 1987 Summary of Operating Reactor Events Meeting 87-37 on 871027. Viewgraphs & Summary of Reactor Scrams Encl ML20235W9431987-10-13013 October 1987 Summary of Operating Reactors Events Meeting 87-32 on 870922.Notes That Meeting 87-31 Did Not Occur.List of Attendees & Events Discussed & Significant Elements of Events Encl ML20216J4431987-06-26026 June 1987 Summary of 870619 Meeting W/Util & Southern Co Svcs to Discuss Commission Policy Statement for Tech Spec Improvements on Plant Specific Basis.List of Attendees & Pilot Application of Commission Interim Policy... Encl ML20214S9971987-06-0202 June 1987 Summary of 870505 Meeting W/Util Re Planned Safeguards Mods at Facility ML20236S4401986-12-30030 December 1986 Summary of 861120 Meeting W/Util Re Proposed Tech Spec Changes to Snubber Surveillance Insp Intervals ML20212E3601986-12-23023 December 1986 Summary of 861120 Meeting W/Bechtel,Southern Co,Svcs & Alabama Power Co in Bethesda,Md Re Proposed Tech Spec Changes to Snubber Surveillance Insp Intervals.Meeting Agenda,List of Attendees & Viewgraphs Encl ML20206L9081986-08-11011 August 1986 Summary of Operating Reactor Events Meeting 86-27 on 860804 W/Ofc Director,Div Directors & Representatives Re Briefing on Events Which Occurred Since Last Meeting on 860728.List of Attendees & Viewgraphs Encl ML20211P1361986-07-16016 July 1986 Summary of 860707 Operating Reactor Events Meeting 86-23 W/ Div Directors & Representatives Re Events Since Last Meeting on 860630.Notification of Inability to Meet Assigned Target Completion Dates for Actions Requested.Viewgraphs Encl ML20211G7781986-06-13013 June 1986 Summary of Operating Reactor Events Meeting 86-19 on 860609. List of Attendees,Events Discussed & Status of Previous Assignments Encl ML20154P0071986-03-12012 March 1986 Summary of Operating Reactor Events 860303 Meeting 86-06 W/Ornl Re Events Occurring Since 860224 Meeting.Followup Review Assignments,Status of Previous Assignments,List of Attendees & Viewgraphs Encl ML20154C9931986-02-24024 February 1986 Summary of Operating Reactors Event Meeting 86-04 on 860210.List of Attendees,Briefing & Reactor Scram Summaries Encl ML20126L2331981-05-0101 May 1981 Summary of 810429 Meeting W/Pwr Owners Group Re Thermal Shock to Reactor Pressure Vessels.All Parties Agree That Thermal Shock W/Subsequent Repressurization Is Safety Concern Needing Prompt Evaluation ML20062K3241980-11-28028 November 1980 Summary of 801030 Meeting W/Util & Bechtel Re Means by Which Power Cables in Containment Are Protected from Overcurrent. Draft Response to NRC Position 040.15 Encl 1999-05-05
[Table view] |
Text
May 5, 1999 LICENSEE: Southern Nuclear Operating Company, Inc. l l
FACILITY: Joseph M. Farley Nuclear Plant (FNP), Units 1 and 2 l
SUBJECT:
SUMMARY
OF MEETING HELD ON APRIL 19 AND 20,1999 l l
The U.S. Naclear Regulatory Commission (NRC) held a meeting with Southern Nuclear Operating Company, Inc. (SNC), on April 19 and 20,1999, at NRC Headquarters in Rockville, Maryland. The purpose of the meeting was to discuss matters related to implementation of the ;
improved standard technical specifications at Farley Nuclear Plant, Units 1 and 2. l l
Enclosed is a list of attendees.
In accordance with Section 2.790 of NRC's " Rules of Practice," Part 2, Title 10 of the Code of l Federal Reaulations, a copy of this meeting summary and its enclosure will be placed in the NRC's Public Document Room.
l Original signed by:
Jacob 1. Zimmerman, Project Manager, Section 1 Project Directorate 11 Division of Licensing Project Management l Office of Nuclear Reactor Regulation Docket Nos. 50-348 and 50-364
Enclosure:
As stated cc w/encis: See next page Distribution:
See next page E W @BVTB1ggpv 9905070078 990505 PDR ADOCK 05000348 P PDR 070015 s
\
DOCUMENT NAME: C:\FARLEY\lSTS\MTG0419.WPD O\
To receive a copy of this document, Indicate in the box C= Copy w/o attachment / enclosure E= Copy with attachment /qnclosure N = No copy OFFICE PDil- f d PDll-1/LA PDil/SC NAME JZin an:cn CHaweh REmc DATE [/ f/99 5 / 4 /99 f / 6 99 OFFICIAL RECORD COPY
E p r.rog
[
0' .
~qs 2 UNITED' STATES g g NUCLEAR REGULATORY COMMISSION o
- WASHINGTON, D.C. 2055Mm01 May 5,1999 LICENSEE: Southern Nuclear Operating Company, Inc.
FACILITY: Joseph M. Farley Nuclear Plant (FNP), Units 1 and 2
SUBJECT:
SUMMARY
OF MEETING HELD ON APRIL 19 AND 20,1999 The U.S. Nuclear Regulatory Commission (NRC) held a meeting with Southern Nuclear Operating Company, Inc. (SNC), on April 19 and 20,1999, at NRC Headquarters in Rockville, !
Maryland. The purpose of the meeting was to discuss matters related to implementation of the improved standard technical specifications at Farley Nuclear Plant, Units 1 and 2.
Enclosed is a list of attendees. l In accordance with Section 2.790 of NRC's " Rules of Practice," Part 2, Title 10 of the Code of Federal Reaulations, a copy of this meeting summary and its enclosure will be placed in the i NRC's Public Document Room.
x , W Jacob 1. Zim erman, Project Manager, Section 1 '
Project Directorate 11 Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-348 and 50 364
Enclosure:
As stated cc w/encls: See next page l
Joseph M. Farley Nuclear Plant cc:
Mr. L. M. Stinson Rebecca V. Badham General Manager - SAER Supervisor .
Southern Nuclear Operating Company Southern Nuclear Operating Company Post Office Box 470 P. O. Box 470 Ashford, Alabama 36312 Ashford, Alabama 36312 Mr, Mark Ajiuni, Licensing Manager Mr. D. N. Morey Southern Nuclear Operating Company Vice President - Farley Project Post Office Box 1295 Southern Nuclear Operating l Birmingham, Alabama 35201-1295 Company, Inc.
Post Office Box 1295
)i Mr. M. Stanford Blanton Birmingham, Alabama 35201-1295 I Balch and Bingham Law Firm <
Post Office Box 306 l 1710 Sixth Avenue North i' Birmingham, Alabama 35201 Mr. J. D. Woodard l
Executive Vice President . '
Southern Nuclear Operating Company Post Office Box 1295
{
Birmingham, Alabama 35201 State Health Officer Alabama Department of Public Health j 434 Monroe Street l Montgomery, Alabc- '?130-1701 Chairman i Houston County Coinmission '
Post Office Box 6406 Dothan, Alabama 36302 Resident inspector l U.S. Nuclear Regulatory Commission 7388 N. State Highway 95 1 Columbia, Alabama 36319
(,
- . ~ s LIST OF ATTENDEES i
- Aoril 19.1999 l
U.S. Nuclear Reaulatory Commission Ramin Assa, NRR/DLPM/LPD2 l
Carl Schulten, NRR/ DRIP /RTSB Nanette Gilles, NRR/ DRIP /RTSB Maggalean Weston, NRR/ DRIP /RTSB Southern Nuclear Ooeratina Comoanv. Inc.. et al,
, Mark Ajluni y
Wes Sparkman
)
i i
April 20.1999 U.S. Nuclear Reaulatory Commission '
. Karen Cotton, NRR/DLPM/LPD2 Carl Schulten, NRR/ DRIP /RTSB Tommy Le, NRR/ DRIP /RTSB Ed Tomlinson, NRR/ DRIP /RTSB i Maggalean Weston, NRR/ DRIP /RTSB Southern Nuclear Ooeratina Comoanv. Inc.. et al.
Mark Ajiuni-Wes Sparkman 4 Enclosure i
I
p s
l Distribution for Meetina Summary dated May 5,1999 l HARD COPY l CDooket %%:
PUBLIC PD 111 R/F
. _J. Zimmerman OGC (w/o encl.)
ACRS (w/o encl.)
E-MAIL S. Collins /R. Zimmerman (SJC1/RPZ)
J. Zwolinski/SBlack H. Berkow O.Hawes B Gilles, RTSB C. Schulten, RTSB M. Weston, RTSB T. Lee, RTSB ,
E. Tomlinson, RTSB l R. Assa, LPD2 K. Cotton, LPD2 M. Satorius, Rll T. Martin (SLM3)
P. Skinner, Rll l
l