Proposes Schedule for Submitting Info Requested in NRC Re 870304 License Amend Application.Util Will Submit Info by 881216,except Results of Corrosion Protection Study
ML20206E746
Person / Time
Site: Peach Bottom 
Issue date: 11/15/1988
From: Gallagher J
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To: Erickson P
Office of Nuclear Reactor Regulation
References
NUDOCS 8811180182
Download: ML20206E746 (1)


Text

PHILADELPHI A ELECTRIC COf4 PANY 2301 MARKET STREET P.O. 00X 8699 PHIL AURLPHI A. PA 19101 laisi set sooi sosem w. cauronen November 15, 1988

.MI.",'J E/,,

00cket No. 50 171 Mr. Peter B. Erickson, Project Manager Standardization and Non-Power Reactor Project Directorate Division of Reactor Projects U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555

Subject:

Peach Boctom Atomic Power Station Unit 1 NRC Request for Information

Reference:

(1)CrwespondencedatedSeptember7,1988 P. s. Erickson, NRC to W. M. Alden, PECo (2) Peach Bottom Atomic Power Station Unit 1 License Amendment Application filed March 4, 1987

Dear Mr. Erickson:

This letter proposes a schedule for sunmitting the information Application (reference (2))).

requested in reference (1 regarding the March 4, 1987 License Amendment The Application proposed a 40 year extension of the expiration date for the Peach Bottom Unit 1 possession only License.

The infomation requested involves (1) an engineering analysis of below ground structures with respect to providing corrosion protection, (2) installation of a water level monitoring system in the Unit 1 containment, and (3) revisions to the March 4,1987 License Amendment A 911 cation. The revisions requested by the NRC to the Application would incorporate reporting and record-keeping requirements, and liquiti and gaseous effluent release and water entry limits into the Unit 1 License.

We will submit the requested information, except for the results of the corrosion protection study, by December 16,1M8. An engineering work request to parform a corrosion protection study of the Unit 1 containment structure has been issued with work commencing in early 1989. x ;;rcche schedule for addressing this request will be identified in tne December 16, 1988 submittal.

I The schedule reflects the time needed to complete an engineering analysis and assess modifications to the decownissioned facility.

1 i

If you have any questions regarding the proposed schedule, please do j

not hesitate to contatt us.