(@n pnneouqk p
UNITED STATES g
j NUCLEAR REGULATORY COMMISSION o
R WASHINGTON, D.C. 20066 4001
- %, *sss**/
NAY 051999.
Purdue Research Foundation ATTN: Ed Rodriguez 1021 Hovde Hall, Purdue University West Lafayette, IN 47907-1021
Dear Mr.' Rodriguez:
SUBJECT:
MODIFICATION NO. 5 TO TASK ORDER NO. 2 ENTITLED "MODULARIZATION OF TRAC-P" UNDER CONTRACT NO. NRC-04-97-046 In accordance with Section G.4, Task Order Procedures, of the subject contract, this letter definitizes Task Order No. 2 Modification No. 5. This effort shall be performed in accordance with the enciesed Statement of Work.
The period of performance for Task Order No. 2 is changed to run from September 30,1997 to May 31,2000. The total estimated cost for full performance of this task order is increased by
$66,788 from $1,178,955 to $1,245,743. $34,574.60 in incremental funding is hereby allotted to Task Order No. 2. This action changes the total cumulative funds obligated for performance of this task order from $905,987 to $940,561.60. The Contractor shall not incur costs for this task order which exceed the cumulative obligated amount of $940,561.60. All other terms and conditions of Task Order No. 2 remain unchanged.
Accounting data for Task Order No. 2 mod 5 is as follows:
B&R No.: 96015110105 Job Code: W-6749 I
BOC Code: 252A RES ID: RES-C99-426 I
Appropriation No.: 31X0200 Amount Obligated by This Action: $34,574.60 l
FY 97 Obligated Amount:$ 162,000 l
FY 98 Obligated Amount:$ 300,012 j
FY 99 Obligated Amount:$ 478,549.60 i
Total Cumulative Obligations:$940,561.60 r V
)
(O i
i
-,-4 n4 9905050131 990505 y
PDR CONTR lj NRC-04-97-046 PDR m
1
Purdue Contract No. N_RC-04-9.7-046 Task Order No. 2 Mod 5 Page 2 of 2 The issuance of this task order does not amend any terms or conditions of the subject contract.
Your contacts during the course of this task order are:
Technical Matters:
James Han, Project Officer (301) 415-6773 Contractual Matters: Stephen Pool, Contract Specialist (301) 415-8168 Sincerely, t ph n M. Pool, Con ctin Officer Contract Management Bran h No.1 Division of Contracts and Property Management Office of Administration
j' k.y 1
l l
i ji MODIFICATION TO TASK ORD.ER 2. 9.h (!l zation of TRAC-P" The puipose of this modification is: (1) to add the foll+ N Subtasks 6.13 through 6.19 to the
{
Statement of Work, (2) to provide additional $66,788 in incremental funding to cover the added subtasks, (3) to extend the period of performance from November 30,1999 to May 31,2000, I
and (4) to allow the planning of up to three person-trips.
r i
- Statement Of Work T'
Subtask 6.13. Test Advanced Linear Solver Test the advanced linear solver. The work involves performing the TRAC-M test problem suite and special test problems (e.g., AP600, ROSA, etc.).
Deliverable: A letter report in both test and electronic format.
Estimated level of efforts:
2 student-months (on half time basis, equivalent to one full month)
Estimated completion date: August 31,1999.
Subtask 6.14. Develop Linear Solver Selector Develop an intelligent algorithm to allow the TRAC-M code to intemally decide at run time which linear solver is most appropriate for the specific problem.
Estimatedlevelof efforts:
2 student-months Estimated completion date: October 31,1999.
Subtask 6.15. Parallelization of New Linear Solver The new linear solver will be ad Apted to parallel computation. Specifically, a threads-based parallel programming mocel will be used because of the fine-grain parallelisrn available in a direct solver. The threads programming will be integrated into the existing PVM message passing modelin TRAC-M.
Estimatedlevelof efforts:
2.5 student months Estimated completion date: January 31,2000 Subtask 6.16 Prepare Documentation Prepare sections of the TRAC-M Software Requirements Specification (SRS), the Software Design and implementation Document (SDiD), and the Test Plan for the new linear solver in accordance with the NRC Sof tware Qualification Assurance (SOA) Plan.
Estimated level of etforts:
2 student-menths Estimated completion date: March 31,2000 1
1
%..; y
?
i l
l Subtask 6.17.
Convert PVM SiE) routines to the New Interprocess Communication Protocol Convert the existing PVM subroutines to the new interprocess Communication Protocol developed at Penn State University under' Subtasks 6.1 through 6.4.
Estimatedlevelof efforts:
2.5 student-months Estimated completion date: : April 30,2000 --
Subtask 6.18.
Convert 3D Kinetics Unkage to the New Interprocess Communication Protocol Convert the existing 3Dkinetics linkage in TRAC M to the new Interprocess Communication Protocol developed at Penn State University.
Estimated level of efforts:
0.5 student-month Estimated completion date: May 31,2000 Subtask 6.19.
Integration of Automatic Data Assignment Algorithm into TRAC-M An automatic data assignment algorithm will be developed by L. Liebrock of Liebrock/ Hicks Associates. This subtask will assist in the integration of that algorithm into the TRAC-M code.
Estimatedlevelof efforts:
0.5 student-month Estimated complet;on date: May 31,2000 MEETINGS AND TRAVEL The contractor should plan to attend two meetings a year in Washington, D.C. for contract review and technical discussions, ACRS meetings, and the Water Reactor Safety information Meeting. For planning purpose, each meeting may be attended by one person from the contractor organization at a duration of two days. Also for planning purpose, the contractor may also attend one additional technical meeting at other locations, sponsored by ASME, ANS, or ACRS; each meeting may be attended by one person at a duration of three days. Prior approval from the NRC Project Officer is needed for any domestic or foreign travel. For foreign travel, the contractor must also submit an NRC Form 445 to the NRC for approval at 10ast 60 days prior to the travel date.
F 2