p UNITED STATES NUCLEAR REGULATORY COMMISSION o{
wAssewoTow, o.c. sosswooi April 30,1999 g*****
l LICENSEE: FirstEnergy Nuclear Operating Company FACILITY:
Davis-Besse Nuclear Power Station, Unit 1 Perry Nuclear Power Plant, Unit 1
SUBJECT:
SUMMARY
OF MARCH 18,1999 MEETING ON QUALITY ASSURANCE TOPICAL REPORTS On March 18,1999, NRC staff met with representatives of the FirstEnergy Nuclear Operating Company in Rockville, Maryland. The purpose of the meeting was to discuss the review schedule and content of a proposed quality assurance (QA) topical report for both the Davis-Besse and Perry facilities. A list of the meeting participants is included as Enclosure 1. There were no meeting handouts.
This was a pre-filing neeting to discuss FirstEnergy's intent to submit a QA topical report to encompass both the Davis-Besse and Perry facilities. It was pointed out that FirstEnergy will benefit from develop:ng a common QA program for all their sites. The effort is being modeled after the Entergy topical report which has previously been reviewed and approved by the staff.
Once the proposed asset transfer between FirstEnergy and Duquesne Light Company takes place (resulting in the license transfer of the Beaver Valley Power Station to FirstEnergy), the QA topical report will also encompass Beaver Valley.
The submittal of the topical report and the implementation dates will be influenced by the ongoing proposed rulemaking for 10 CFR 50.54(a). The proposed rulemaking, which will enable licensees to make certain changes to their QA plans without prior staff review and approval, was still out for public comment at the time of the meeting. The public comment period ended on March 25,1999, and, absent any negative comments, the revised rule is scheduled for implementation on April 26,1999.
The staffs review will focus on reductions in commitments to the QA program and will not look at the overall QA program. It was generally believed that if the new rule is published as currently written, only a small fraction (e.g.,10-20%) of the changes would be considered a reduction in commitment that must be reviewed and approved by the staff. Due to the benefits gained from the Entergy review, the staff anticipates a much shorter review schedule for this effort. The licensee indicated that Perry will be the lead plant for this review.
The licensee's implementation schedule has not been finalized. As previously indicated, aspects may change depending on the outcome of the ongoing rulemaking efforts. Revisions are expected for the Updated Safety Analysis Reports for both facilities.
Y l
9905040165 990430 PDR ADOCK 05000346 P
PM j
.___---~__m.__
1 i
. During closing statements, both the licensee and staff agreed to frequent communications during the review process. With respect to fee billing and how to equitably separate the fees between the two facilities, the staff indicated it would reexamine how the plant specific billing was handled during the Entergy review.
Original signed by Douglas V. Pickett, Senior Project Manager, Section 2 Project Directorate ill Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-346, 50-440
Enclosure:
List of meeting attendees cc w/ encl: See next page DISTRIBUTION:
Hard Coov w/enci E-mail w/ encl y~ DocketFileF SCollins (SJC1)
TQuay PD lli Reading RZimmerman MBugg PUBLIC THiltz WLong GGrant, Rill JZwolinski/SBlack OGC CThomas/AMendiola ACRS DOCUMENT NAME: G:\\PD3-3\\ PERRY \\3 18MTG.WPD To receive a copy of this document, indicate in the box: "C" = Copy without enclosures "E" = Copy with enclosures "N" = No copy PM PD35 6
LA:PD31 9/
SC:PD32 8
BC:IOMB 0FFICE 1
NAME DPidett EBarnhill O M DATE 04/2 \\/99 04/11 /99
~
AMendiola W n / T0uay W 04 % /99 /\\\\ P 04/%/99 0FFICIAL RECOP,0 COPY bfb $l%
c10363 1
\\
?.
e I
l Davis-Besse Nuclear Power Station, Unit 1 Toledo Edison Company I
cc:
Mary E. O'Reilly Robert E. Owen, Chief FirstEnergy Bureau of Radiological Health 76 South Main Street Service Akron, OH 44308 Ohio Department of Health P.O. Box 118 Columbus, OH 43266-0118 James L. Freels Manager - Regulatory Affairs Attorney General Toledo Edison Company Department of Attorney General Davis-Besse Nuclear Power Station 30 East Broad Street 5501 North State - Route 2 Columbus, OH 43216 Oak Harbor, OH 43449-9760 Donna Owens, Director Jay E. Silberg, Esq.
Ohio Department of Commerce Shaw, Pittman, Potts Division of Industrial Compliance
& Trowbridge Bureau of Operations and Maintenance 2300 N Street, NW.
6606 Tussing Road Washington, DC 20037 P.O. Box 4009 ReynoldP5urg, OH 43068-9009 Regional Administrator U.S. NRC, Region ill Ohio E' anmental Protection Agency 801 Warrenville Road DERR-s.,mpliance Unit Lisle, IL 60523-4351 ATTN:
ick A Clayton P.O. Box 1049 Robert B. Borsum Columbus, OH 43266-0149 Babcock & Wilcox Nuclear Power Generation Division State of Ohio 1700 Rockville Pike, Suite 525 Public Utilities Commission Rockville, MD 20852 180 East Broad Street Columbus, OH 43266-0573 Resident inspector U.S. Nuclear Regulatory Commission James R. Williams 5503 North State Route 2 Chief of Staff Oak Harbor, OH 43449 Ohio Emergency Management Agency 2855 West Dublin Granville Road James H. Lash, Plant Manager Columbus, OH 43235-2206 FirstEnergy Nuclear Operating Company Davis-Besse Company Guy G. Campbell 5501 North State Route 2 Vice President - Nuclear, Davis-Besse Oak Harbor, OH 43449-9760 FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station President, Board of County 5501 North State Route 2 Commissioners of Ottawa County Oak Harbor, OH 43449-9760 Port Clinton, OH 43452
1 y.,.
MEETING ATTENDEES NRC AND FIRSTENERGY NUCLEAR OPERATING COMPANY SUBMITTAL OF QA TOPICAL REPORTS MARCH 18,1999 FIRSTENERGY NUCLEAR OPERATING COMPANY DAVIS-BESSE PERRY Ted Myers Henry Hegrat Joseph Sturdivant R. G. Collins Marcy Beier Mark Levering NBC Robert Gramm Michael Bugg Allen Hansen Doug Pickett MEMBERS OF THE PUBLIC Sidney Crawford Enclosure l