VERMONT YANKEE NUCLEAR POWER CORPORATION
't RD 5, Box 169, Ferry Road, Brattleboro, VT 05301
,,,Ly,g
. ENGINEERING OFFICE 1671 WORCESTER ROAD June 9, 1986 FRAMINGHAM. MASSACHUSETTS 01701 FVY 86-54 retsesost eir-ara-aioo United States Nuclear Regulatory Commission Washington, DC 20555 Attention:
Office of Reactor Regulation Mr. Vernon L. Rooney, Senior Project Manager BWR Project Directorate No. 2 Division of BWR Licensing i
References:
(a) License No. DPR-28 (Docket No. 50-271)
(b) Letter, VYNPC to USNRC, FVY 86-22, Proposed Change No. 132, dated March 12, 1986 (c) Letter, VYNRC to USNRC, FVY 86-40, dated May 9, 1986
Subject:
Single-Leop Operation and Thermal-Hydraulic Stability Proposed Technical Specification Change:
Response to Request for Information
Dear Sir:
The purpose of this letter is to respond to your recent request for information regarding the analysis of a one-pump seizure event for
-l Vermont Yankee under single loop operation.
The recirculation pump seizure event was analyzed by General Electric for the Vermont Yankee Nuclear Power Station. The analysis assumes that the reactor is operating initially under single loop operation at 73.3% power and 3
at thermally limiting conditions.
t The Minimum Critical Power Ratio (MCPR) calculated for this event was more than 0.14 above the fuel cladding integrity safety limit. Thus, there is no threat posed to fuel thermal limits and no fuel failures are calculated.
i The consequences of this event also do not result in any temperature or pressure transient in excess of the criteria for which the reactor vessel or containment are designed.
These results support our conclusion that the fuel thermal limits established for two-loop operation are also applicable to single loop operation, and that the pressure barrier integrity is maintained under single loop operation.
8606160052 860609 Very truly yours, PDR ADOCK 05000271 P
PDR VERMONT YANKE N CLEAR POWER CORPORATION
/
\\
R. W. Capstick Licensing Engineer 1