l MEMORANDUM TO: File April 15,1999 FROM:
Thomas W. Alexion, Project Manager, Section 1 ORIG SIGNED BY:
Project Directorate IV & Decommissioning Division of Licensing Project Management
SUBJECT:
DISCUSSIONS WITH LICENSEE ON ITS MARCH 9,1999, PROPOSED CHANGES TO TECHNICAL SPECIFICATIONS ON THE 1
INDEPENDENT SAFETY ENGINEERING GROUP,(ISEG), SOUTH TEXAS PROJECT, UNITS 1 AND 2 During an April 7,1999, phone call between the NRC staff and tho acensee (STP Nuclear Operating Company), the staff informed the licensee that its March 9,1999 (ACN 9903180318),
proposed technical specification change appeared to be acceptable, but that the supporting i
change to the Operations Quality Assurance Plan (OOAP) tvas not. The staff position is that as a minimum, the discussion of a function equivalent to the current ISEG function should be retained in the OOAP.
In order to facilitate future discussions between the licensee and the staff, the licensee provided the information in the attachment. The purpose of this memorandum is to place the attachment in the Public Document Room.
Docket Nos. 50-498 and 50-499
Attachment:
As stated DISTRIBUTION:
Docket Files (50-498 and 50-499)
PUBLIC DOCUMENT NAME: 1:\\STPFINAL\\MEMA4995.WPD To receWe a copy of this document. Indicato in the box C= Copy w/o attachment /or. closure E= Copy wilh attachment / enclosure N = No copy OFFICE PM/PDlW1.
E LA/PDIV-1 E
SC/PDIV-1 I
Tale 6h CJamerson 0 RGrammI2dp NAME r
L / lL
/99 Y/((/99
- / k /99 DATE O' y
[)\\
OFFICIAL RECORD COPY 210015 i
P l
I e nn o
t UNITED STATES j
NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 30666 0001
%*****/
April 15, 1999 MEMORANDUM TO: File FROM:
Thomas W. Alexion, Project Manager, Section 1 Project Directorate IV & Decommissioning Division of Licensing Project Management
SUBJECT:
DISCUSSIONS WITH LICENSEE ON ITS MARCH 9,1999 PROPOSED l
CHANGES TO TECHNICAL SPECIFICATIONS ON THE INDEPENDENT SAFETY ENGINEERING GROUP (ISEG), SOUTH TEXAS PROJECT, UK7S 1 AND 2 During an April 7,1999, phone call between the NRC staff and the licensee (STP Nuclear Operating Company), the staff informed the licensee that its March 9,1999 (ACN 9903180318),
proposed technical specification change appeared to be acceptable, but that the supporting change to the Operations Quality Assurance Plan (OOAP) was not. The staff position is that as a minimum, the discussion of a function equivalent to the current ISEG function should be retained in the OOAP.
In order to facilitate future discussions between the licensee and the staff, the licensee providcd the information in the attachment. The purpose of this memorandum is to place the attachment in the Public Document Room.
Docket Nos. 50-498 and 50-499
Attachment:
As stated
e sam.
SOUTH TEXAS PROJECT ELECTRIC @ENERATING STATION NUMsER REV.
no.
OPERATIONS QUALITY ASSURANCE PLAN INDEPENDENT TECHNICAL REVIEW EFFECTWE DATE 044UU99 1.0 Ptmpose 1.1 The purpose of this chapter is to describe the requirements and responsibilities for independent technical review fo:: the South Texas Project Electric Generating Station (STPEGS).
2.0 ECQP.E 2.1 This chapter describes the independent technical review activities within the scope of the Operations Quality Assurance Plan (OQAP).
i 3.0 DEFINITIONS 3.1 None
4.0 REFERENCES
4.1 OQAP Chapter 1.0, Organization 4.2 OQAP Chapter 2.0, Program Description 4.3 OQAP Chapter 4.0, Qualification, Training, and Certification of Personnel 4.4 OQAP Chapter 13.0, Deficiency Control 4.5 OQAP Chapter 14.0, Records Control 4.6 OQAP Chapter 15.0, Quality Oversight Activities 5.0 RESPONSIBILTTIES 5.1 The Vice President, Nuclear Engineering & Technical Services is responsible for implementing quality program requirements including independent technical review.
5.2 The Director, Quality & Licensing is responsible for independent oversight activities performed to accomplish the independent technical reviews.
6.0 REOUIREMENTS 6.1 Independent oversight activities, as described in Reference 4.6, shall be performed in accordance with implementing procedures to ensure the completion of independent technical reviews.
m m
n c7
}
p QA f ATTAC1DfENT Wa-
w m an==
SOUTH TEXAS PROJECT ELECTRIC GENERAT8NG STATION NUX85R REV.
no.
OPERATIONS QUALITY AS8URANCE PLAN INDEPENDENT TECHNICAL REVIEW EFFECTIVE m@
u DATE 04130UD9 Q) W ^ ~
6.2 Independent technical reviews shall be used to observe and verify that activities are performed correctly and that human errors are reduend as much as practical.
6.3 Independent technical reviews shall include, but not bu i
limited to, the following activities:
l 6.3.1 Unit-operating characteristics l
l 6.3.2 Nuclear Regulatory Commission issuances 6.3.3 Industry advisories l
l 6.3.4 Licensee Event Reports l
l 6.3.5 Other sources of unit design and operating I
experience information, including units of similar design, which may indicate areas for improving unit safety.
6.3.6 Plant operations 6.3.7 Maintenance activities l
6.3.8 Equipment raciifications 1
6.4 As determined by Quality management, several personnel performing independent technical reviews will be required l
to have a degree in engineering or related science and at l
1 east 3 years of professional level experience in the nuclear field.
6.5 The results of independent technical reviews will be periodically transmitted to appropriate line and senior management, the Nuclear Safety Review Board, and the President and Chief Executive Officer for revied and/or action and advise management on the overall quality and safety of operations.
6.6 Conditions adverse to quality and recommendations identified during the perfo rance of independent technical reviews shall mee's the requirements of Reference 4.4 m
m n C7 D
RA@
W-
- gmf p
L)u Ull 11d if U
i COUTH TEXAS PROJECT ELECTRIC GENERATING STATION woussa nav.
no.
OPERATIONS QUALITY ASSURANCE PLAN INDEPENDENT TECHNICAL REVIEW PAGE s OF 3 EFFECTIVE DATE Occups 7.0 Doctn4rNTATYou 7.1 Procedures which are generated as required by this chapter shall identify the records which are required to implement and~ document those activities.
The records shall be controlled in accordance with Reference 4.5.
i I
8.0 ATTAcuMRNTn 8.1 None m}
r3 l
J l
TOTAL P.04