Ltr Contract,Task Order 7,mod 4 Entitled, Snap Nodalization Knowledge-Based Expert System, Under Contract NRC-04-97-046
ML20205K216
Person / Time
Issue date: 04/01/1999
From: Pool S
NRC OFFICE OF ADMINISTRATION (ADM)
To: Rodriguez E, White M
PURDUE RESEARCH FOUNDATION
References
CON-FIN-W-6749, CON-NRC-04-97-046, CON-NRC-4-97-46 NUDOCS 9904130046
Download: ML20205K216 (3)


Text

. -~

, , ~ --

_....-..a p scero y 't UN'lTED STATES g j t

NUCLEAR REGULATORY COMMISSION WASHINGT,0N, D.C. 200660001 q%

9.....l -

w. . . .. .-

2 Purdue Research Foundation ATTN: Ed Rodriguez 1021 Hovde Hall, Purdue University Nest Lafayette, IN 47907-1021 s

Dear Mr. Rodriguez:

(

SUBJECT:

TASK ORDER NO. 7 MODIFICATION NO. 4 ENTITLED " SNAP NODALIZATION KNOWLEDGE-BASED EXPERT SYSTEM" UNDER CONTRACT NO. NRC 97-046 In accordance with Section G.4, Task Order Procedures, of the subject contract, this letter definitizes Task Order No. 7 Modification No. 4. This effort shall be performed in accordance with the enclosed Statement of Work for Mod 4 (Tasks 10,11 and 12).

The period of performance for Task Order No. 7 is changed to run from January 14,1998 through March 31,2000. The total estimated cost for fu!! performance of this task order is increased by $132,156 from $154,089 to $286,245. Funds obligated on this task order are increased by $53,000 from $154,089 to $207,089. The Contractor shall not incur costs for this task order which exceed the cumulative obligated amount of $207,089. All other terms and conditions remain unchanged.

Accounting data for Task Order No. 7 Modification No. 4 is as follows: I B&R No.: 960-15-11-010-5 l Job Code: W-6749 BOC Code: 252A 4 RES ID: RES-C99-396 Appropriation No.: 31X0200 Obligated Amount This Action: $53,000 FY 98 Obligations: $129,729 FY 99 Obligations: $g7,360.. ~, ,; j Cumulative Obligations: $207,089 l

z

\

t 9904130046 990401 PDR CONTR

, . , NRC-04-97-046 PDR '

.v s3

____ o Purdue 'i z. Contract No. NRC-04-97-046

~

l .

Tas'k Order No. 7 MOD 4 l Page 2 of 2 The issuance of this task order does not amend any terms or conditions of the subject contract.

Your contacts during the course of this task order are:

Technical Matters: Jennifer Uhle, Project Officer (301) 415-6023 Contractual Matters: Stephen Pool, Contract Specialist l (301) 415-8168 Please indicate your acceptance of this task order by having an official, authorized to bind your organization, execute three copies of this document in the space provided and return two copies to the Contract Specialist. You should retain the third copy for your records.

Sincerely, ,

)

I l

ll Stephen M. Pool, Co acti g Officer Contract Management Bra ch No.1 ~

Division of Contracts and Property '

Management

Enclosure:

As stated ACCEPTED: TASK ORDER NO. 7 MODIFICATION NO. 4 Punlee Research Foundsson JMdb NAME iIdk 4l 19 9 DATE tadele L Whha.

Asnwant TreasurufAssising temutw TITI.E

T

. _ __,m MODIFICATIOkTO TASK ORDER #7 The period of performance will be extended lo anuary 1d1998 -March 31,2000.

WORK REQUIREMENTS Task 10: Software Design and implementation Document I A chapter in the SNAP Design Document shall be prepared describing in detail the manner in which the requirements will be fulfilled. The code (s) for which the system will be developed will be decided by NRC before the work begins.

Estimated Completion Date: 5 months after initiation of the modification ,

Estimated Level of Effort: 1 s/m l Task 11: Implementation Once accepted by NRC, the design approach developed in the last task shall be implemented and the coding performed if directed by the NRC, This task may invoive modifying and expanding the knowledge-base developed under the first six tasks raf this contract if the system 1 I

is designed for TRAC-M as well as RELAPS.

Estimated Completion Date: 12 months after initiation of the modification Estimated Level of Effort: 6 s/m  ;

Task 12: Documentation Chapters for the SNAP User's Guide and Programmer Appendix shall be prepared and submitted to NRC in both text and electronic format if directed by the NRC.

Estimated Completion Date: 13 months after initiation of the modification Estimated Level of Effort: 1 s/m MEETINGS AND TRAVEL For successful completion of the work required in this contract, it is anticipated that the contractor shall travel to the NRC office in Rockville, MD. The contractor may propose additional travel deemed necessary for the successful completion of this effort. All travel shall be approved in advance by the Project Manager, be specifically performed in support of.this contract ans be in compliance with Federal Transportation Regulations.

Task 11 In support of Task 11, one two-day meeting for two people.