ML20205G382

From kanterella
Jump to navigation Jump to search
Deficiency Rept Re Potentially Defective Welds on Kaman Instrumentation Radiation Monitor Display Panels.Initially Reported on 840710.Safety-related Monitors Downgraded for Use as Spares.New Monitors Purchased
ML20205G382
Person / Time
Site: Washington Public Power Supply System
Issue date: 03/13/1987
From: Holmberg B
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
GO1-87-0028, GO1-87-28, NUDOCS 8703310444
Download: ML20205G382 (1)


Text

~

y 1

RE gm, WASHINGTON PUBLAIPOWER SUPPLY SYSTI$3 P.O. Box 968

  • 3000 Gehe&sbln8gtQ Hjay Richiar&Qigong9352 u

i March 13, 1987 BEGIONylag G01-87-0028 aggyONyggg Mr. J. B. Martin Regional Administrator Nuclear Regulatory Commission Region V 1450 Maria Lane, Suite 210 Walnut Creek, California 94596

Subject:

NUCLEAR PROJECT NO. 1 DOCKET NO. 50-460 P0TENTIALLY REPORTABLE CONDITION 10CFR50.55(e)

DEFECTIVE WELDS ON RADIATION MONITOR DISPLAY PANELS

References:

1. Telecon; CR Edwards, Supply System, to DJ Willet, NRC; subject same; dated July 10, 1984
2. Letter G01-84-209; RW Root to JB Martin; subject same; dated August 7, 1984 In reference 1 the Supply System informed your office of a potentially reportable deficiency under 10CFR50.55(e). Reference 2 provides a statement of the identified condition and a brief description of our planned actions to correct the identified deficiency. The purpose of this letter is to inform your office that we have eliminated the deficient condition for safety-related radiation monitors supplied to us by Kaman Instrumentation.

Although the Supply System WNP-1 Project has thirty-seven (37) monitors with the potential of having defective weld studs for the display panel boxes, only eight (8) of these monitors were intended to perform a safety-related function.

For non-technical reasons we took formal action on September 5, 1985 to downgrade the eight (8) safety-related monitors to QC II with the intent of using them as spare parts for the other non-safety related monitors. Upon restart of construction activities, we plan to purchase eight (8) new monitors from another supplier for the safety-related fonctions. As a prudent course of action, we still plan to perform the vendor recommended test on monitors used in non-safety related functions, and if needed, take corrective action.

However, we consider the potentially reportable condition resolved since the potentially defective safety-related monitors are no longer involved.

If you have questions, please advise.