ML20205C914
| ML20205C914 | |
| Person / Time | |
|---|---|
| Site: | Beaver Valley |
| Issue date: | 09/13/1985 |
| From: | Carey J DUQUESNE LIGHT CO. |
| To: | Knighton G Office of Nuclear Reactor Regulation |
| References | |
| 2NRC-5-131, NUDOCS 8509230348 | |
| Download: ML20205C914 (1) | |
Text
dVt
'Af 2 m 131 DuquesneLidit
,,,,,,,,::::n:t;:::
~,..,c...,_, _._
Sn*.Iu' g"nfl'is*2$l** *""'
September 13, 1985 p
United States Nuclear Regulatory Conunission Washington, DC 20555 ATTENTION:
Mr. George W. Knighton, Chief Licensing Branch 3 Office of Nuclear Reactor Regulation
SUBJECT:
Beaver Valley Power Station - Unit No. 2 Docket No. 50-412 Control Room Design Review (CRDR) Summary Report
REFERENCE:
2NRC-5-107, July 24,1985 Gentlemen:
The CRDR Meeting Summary, dated June 6,1985, states that the appli-cant will provide the CRDR package by the end of June,1985.
The actual submittal date is Decenber 1,1985, as reported in the referenced letter and agreed to by the Human Factors Engineering Branch reviewer.
DUQUESNE LIGHT OMPANY Z
By _, _
~ __
J VJ L4'arey Vice President MED/wjs cc:
Mr. B. K. Singh, Project Manager Mr. G. Walton, NRC Resident Inspector 8509230340 850913 h@4 ADOCK 0 % y2 1 0 PDR F
I