ML20205C848

From kanterella
Jump to navigation Jump to search
Notification of 990413-14 Meeting with NEI & CP&L in Burr Ridge,Il,To Discuss EPRI Technical Basis Rept Pertining to GL-96-06, Assurance of Equipment Operability & Containment Integrity Design Basis Accident Conditions
ML20205C848
Person / Time
Issue date: 03/30/1999
From: Wetzel B
NRC (Affiliation Not Assigned)
To: Thomas C
NRC (Affiliation Not Assigned)
References
GL-96-06, GL-96-6, NUDOCS 9904020038
Download: ML20205C848 (6)


Text

E yg N14 30,1999 MEMORANDUM TO: C:cil O. Thom:s, Dir;ctor Projict Directorate 111

-t FROM:

Beth A. Wetzel, Senior Project Manager Project Directorate ill

SUBJECT:

MEETING WITH INDUSTRY TO DISCUSS TECHNICAL BASIS DOCUMENT PERTAINING TO GENERO LETTER (GL) 96-06,

" ASSURANCE OF EQUIPMENT OPERABILITY AND CONTAINMENT INTEGRITY DURING DESIGN BASIS ACCIDENT CONDITIONS" DATE & TIME:

April 13-14,1999 8:00 a.m. - 5:00 p.m.

LOCATION:

Best Western inn of Burr Ridge 300 S. Frontage Road j

Burr Ridge, IL 60521 PURPOSE:

Members of the NRC steff will meet with utility representatives and industry experts on April 13 and 14,1999, to discuss the EPRI technical basis report (TBR) that is being developed by the industry which will be used to address questions raised by the staff pertaining to analyses of the j

waterhammer issue raised in GL 96-06. A preliminary agenda for this meeting is attached.

  • PARTICIPANTS:

NRC participants are from the Of' ice of Nucirr. Reactor Regulation (NRR).

j NR_Q CP&L G. Hubbard (NRR)

V. Wagoner J. Tatum (NRR)

C. Hammer (NRR)

NE K. Cozens

/

cc:

Kurt Cozens Nuclear Energy Institute 1776 l Street, NW Suite 400 Washington, DC 20006-3708

. CONTACT: Beth Wetzel, (301) 415-1355

  • Meetings between NRC technical staff and applicants or licensees are open for interested members cf the public, petitioners, intervenors, or othar parties to attend as observers pursuant to " Commission Policy Statement on Staff Meetings Open to the Public" (59 Federal Reaister 4E240,9/20/94). However, all or a significant portion of this j

meeting mav 61 closed to the public to protect proprietary information. Members of the public who wish to attend should cot

. Beth Wetzel at (301) 415-1355.

DOCUMENT NAME: PTBEACH\\APR99MTG C23010 OFC PD3-1:PM EL PD3-1:LA E

BWetzel[6th M

THarris NAME 63/ /99

'Yh/%g Y

DATE 3 99/99 OFFICIAL RECORD COPY X 70$/

E ?f [b 2

9904020038 990330 461 -p 6 C

~ DR REVQP ERONUMRC

//

YS8 FE.E CENP31 CGPV eaa

y#*"%g\\

UNITED STATES j

3 s

NUCLEAR REGULATORY COMMISSION WAsNINGToN, D.C. 30ess-0001 e..

e April 30, 1999 MEMORANDUM TO: Cecil O. Thomas, Director Project Directorate 111 i

FROM-Beth A. Wetzel, Senior Project Manager d

Project Directorate lli

SUBJECT:

MEETING WITH INDUSTRY TO DISCUSS TECHNICAL BASIS DOCUMENT PERTAINING TO GENERIC ; ETTER (GL) 96-06,

" ASSURANCE OF EQUIPMENT OPERA.u.i I AND CONTAINMENT j

INTEGRITY DURING DESIGN BASIS ACCIDENT CONDITIONS" j

l DATE & TIME:

April 13-14,1999 E:00 a.m. - 5:00 p.m.

LOCATION:

Best Westem Inn of Burr Ridge 300 S. Frontage Road Burr Ridge, IL 60521 PURPOSE:

Members of the NRC staff will meet with utility representatives and industry experts on April 13 and 14,1999, to discuss the EPRI technical basis report (TBR) that is being developed by the industry which will be used to address questions raised by the staff pertaining to analyses of the waterhammer issue raised in GL 96-06. A prelimina y agenda for this meeting is attached.

  • PARTICIPANTS:

NRC participants are from the Office of Nuclear Reactor Regulation (NRR).

N8G 2 41.

G. Hubbard (NRR)

V. Wagoner J. Tatum (NRR)

C. Hammer (NRR)

NEl K. Cozens cc:

Kurt Cozens Nuclean Energy Institute 1776 i Street, NW Suite 400 Washington, DC 20006-3708 CONTACT: Beth Wetzel, (301) 415-1355 j

  • Meetings between NRC technical staff and applicants or licensees are open for interested members of the public, petiboners, sir &r.erse, or other parties to attend as observers pursuant to " Commission Policy Statement on Staff 1

Meetings Open to the Public" (5A Federal ReaiMar 4834C,9/20/94)._ However, oh or a significant portion of this meeting may be closed to the public to protect rWary information. Members of the public who wish to attend should curh: 3eth Wetzel at (301) 41J-1355.

s s

[Beth Wetni-W6 VEP Agenda 4-13a. doc Page1 Preliminary Agenda for the Third Meeting of the Waterhammer Expert Panel First Day,4/13/99 Time i

Tople Presenter l

8:03 A M Introduction and Objectives of the Project and V. Wagoner Expert Panel-Update 8:30 AM Thermal Layer & Steam Air Content Testing R. Henry Solution Approach Testing Results Status 10:15 AM Break 10:30 AM TBR Outline / Contents / Status T. Esselman "What will it containT' "How will I use it?"

11:15 AM TBR Introductory Sections Altran Describe the following TBR Sections:

Corporation Introduction System Descriptions Postulated Event Description Waterhammer Occurrence Plant Experience with Waterhammers 12:00 Noon Lunch 1:00 PM TBR Section on Plan Development /Prioritization T. Esselman Include PIRT and Uncertainty Discussion 2:00 PM TBR Information on Column Closure Waterhammer Altran Testing Result Update Corporation Comparison to Analysis Update Methods of Characteristics Update Scaling Howis it applied?

Plan for Completion 5:00 PM Adjourn

[Beth WetzIl - WB WEP Agend s 4;13a. doc Paga 2 Preliminary Agenda for the Third Meeting of the Waterhammer Expert Panel Second Day,4/14/99 l

1 Time Topic J

8:00 AM Discussion Session

' Expert Panel, All 9:00 AM TBR Section on Condensation Induced Altran Waterhammer Corporation l

Test Result Update Plan for Comparisor to Analysis and Status l

Scaling l

Plan for Close-Out 10:15 AM Break 10:30 AM TBR Section on Wave Propagation Altran l

Sonic Velocity Corporation Fluid Structure Amplification Fluid Structure Attenuation Wave Reflection 12:00 Lunch 1:00 PM Support / Component Reactions Altran Comparison of Test and Analysis Corporation j

2:00 PM Support / Component Qualification T. Esselman j

Tying it all together

~

3:00 PM Caucus All 1

3:30 PM Discussion and Comments All

)

4:00 PM Summary / Upcoming Work Plan Review / Meeting A. Singh/V.

)

Schedule Wagoner 4:30 PM Adjourn l

i i

i 3

Aprk1~30,1999 c

e ; MEMORANDUM TO: CIcil O. Thomis Director.

ProjIct Directorats lil' 1

Fi ' M:

Beth A. Wetzel, Senior Project Manager Project Directorate ill

SUBJECT:

MEETING WITH INDUSTRY TO DISCUSS TECHNICAL BASIS DOCUMENT PERTAINING TO GENERIO LETTER (GL) 96-06,

" ASSURANCE OF EQUIPMENT OPERABILITY AND CONTAINMENT INTEGRITY DURING DESIGN BASIS ACCIDENT CONDITIONS" DATE & TIME:

April 13-14,1999 8:00 a.m. - 5:00 p.m.

LOCATION:

_ Best Westem Inn of Burr Ridge

)

300 S. Frontage Road Burr Ridge, IL 60521 PURPOSE:

Members of the NRC staff will meet with utility representatives and industry experts on April 13 and 14,1999, to discuss the EPRI technical basis report (TBR) that is being developed by the industry which will be used to address questions raised by the staff pertaining to analyses of the waterhammer issue raised in GL 96-06. A preliminary agenda for this meeting is attached.

  • PARTICIPANTS:

NRC participants are from the Office of Nuclear Reactor Regulation (NRR),

NRC CP&L G. Hubbard (NRR)

V. Wagoner J. Tatum (NRR)

C. Hammer (NRR)

NEl K. Cozens cc:

Kurt Cozens Nuclear Energy Institute i

1776 l Street, NW Suite 400 Washington, DC 20006-3708

' CONTACT: Beth Wetzel,- (301) 415-1355

  • Meetings between NRC technical staff and applicants or licensees are open for interested members of the public, petitioners, intervenors, or other parties to attend as observers pursuant to "Oommission Policy Statement on Staff Meetings Open to the Public" (59 Federal Reaister 48340,9/20/94). However, all or a significant portion of this meeting may be closed to the public to protect proprietary information. Members of the public who wish to attend should contact Beth Wetzel at (301) 415-1355.

1 DOCUMENT NAME: PTBEACH\\APR99MTG OFC' PD3-1:PM 15 ' PD3-1:LA' E

I NAME BOetzel Oh THarrisM DATE-3 /;Y)/99i 03/N99 OFFICIAL RECORD COPY

8 April 30, 1999 Notice of 4/13-14 meetings with the nuclear industry to discuss an EPRI technical basis report on GL 96-06 E! Ball S. Collins /R. Zimmerman (SJC1/RPZ)

J. Zwolinski(JAZ)

S. Black (SCB)

C. Thomas (COT)

OPA (OPA)

G. Grant, R3 (GEG)

T. Hiltz (TGH)

J. Strasma, R3 (RJS2)

G. Hubbard l

J. Tatum PMNS (Meeting Announcement Coordinator)

Hard Coov Central Files l

PUBLIC PD31 R/F l

OGC ACRS OWFN and TWFN Receptionist l

,