Discusses Arrangements Made for Administration of Operator Licensing Exams at Kansas State Univ Scheduled for Week of 990517 & Requests Licensee Furnish One Set of Reference Matl Listed in Encl 1
ML20204H028
Person / Time
Site: Kansas State University
Issue date: 03/22/1999
From: Eresian W
NRC (Affiliation Not Assigned)
To: Ryan B
KANSAS STATE UNIV., MANHATTAN, KS
References
NUDOCS 9903260369
Download: ML20204H028 (11)


Text

_

w =.

[p/gf y-j#* "%g?% UNITED STATES i

e E l

NOCLEAR REGULATORY COMMISSION i f WASHINGTON, D.C. 20555-0001

          • f March 22, 1999 Mr. Brendan Ryan, Manager Nuclear Reactor Facility _

112 Ward Hall

. Kansas State University Manhattan, Kansas 66506-2503 Dear Mr. Ryan; i

in a telephone conversation between Mr. Wanen Eresian and yourself, arrangements were made for the administration of operator licensing cxaminations at the Kansas State University. l

)

The examinations are scheduled for the week of May 17,1999. I in order for us to meet this schedule, please furnish one set of the reference materiallisted in

~

Enclosure 1, as applicable, " Reference Material for Reactor / Senior Reactor Operator Licensing Examinations" at least 60 days prior to the examination date to the following address:

U. S. Nuclear Regulatory Commission Washington, D.C. 20555 ATTN: Warren J. Eresian, Mail Stop O-11-D-19 You are responsible for providing adequate space and accommodations in order to properly conduct the written examinations. Enclosure 2, " Administration of Written Examinations,"

describes our process for conducting these examinations.

, Enclosure 3 contains the Rules and Guidelines that will be in effect ouring the administration of the written examination. Please ensure that all applicants are aware of these rules. I Ycur review of the written examination will be conducted in accordance with the procedures specified in Enclosure 4, " Facility Review of Written Examinations."

Preliminary reactor operator and senior reactor operator license applications should be submitted at least 30 days before the first examination dates so that we will be able to review the training and experience of the candidates, process the medical certifications, and prepare final examiner assignments after applicant eligibility has been determined. Final signed applications certifying that all training has been completed must be submitted at least 14 days before the examination date in order to process the license application. If our review cannot be completed in time to make a determination of applicant eligibility, the candidate may not be permitted to sit for the examination, fherefore, it is recommended that license applications be provided as soon as possible to ensure an aopropriate level of review. '

t yfo\ \

9903260369 #90322 PDR ADOCK 05000188 V PDR a

~~

n. . - - e ~ ~J f"
v p m {1 -) C I._,u

Mr. Brendan Ryan March 22, 1999 This request is covered by Office of Management and Budget (OMB) Clearance Number 3150 -

0101, which expires April 30,2000. The estimated average burden is 7.7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> per response, including gathering; xeroxing and mailing the required material. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Information and Records Management Branch, MNBB-7714, Division of information Support Services, Office of Information Resources Management, U.S.

Nuclear Regulatory Commission, Washington, D.C. 20555; and to the Paperwork Reduction Project (3150-0101), Office of Information and Regulatory Affairs, NEOB-3019, Office of Management and Budget, Washington, D.C. 20503.

If you have any questions regnrding the examination procedures and requirements, please contact Mr. Warren J. Eresita at (301) 415-1833.

Sincerely, ORIGINAL SIGNED BY Warren J. Eresian, Chief Examiner Non-Power Reactors and Decommissioning Project Directorate Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket No. 50-188

Enclosures:

1. Reference Material for Reactor / Senior Reactor Operator Licensing Examinations
2. Adminietration of Written Examinations  ?
3. Procedures for Administration cf -

Written Examinations ,

4. Facility Review of Written Examinations l DISTRIBUTION:

Docket File 50-188 PDR/LPDR Facility File (DMcCain)

TMichaels, PM DOCUME.NT NAME: G:\SECY\ERESIAN\KSU90.WPD

  • See previous concurrence "E' = Copy with attachtnentlenclosue ? "N* = No copy To receive e cert of this document, indicate in the boa: "C" - Copy without attrahrnenL nciosure l

PDND:PM y l HOLB:Le , lf PDND:QrE1l l OFFICE-NAME WEresian M, DMcCF SWeisR F

/ l DATE 03/22/99 03/22/99 03/11/99 I

OFFICIAL RECORD COPY )

i

Mr. Brendan Ryan March 22, 1999 This reauest is covered by Office of Management and Budget (OMB) Clearance Number 3150-0101, which expires April 30,2000. The estimated average burden is 7.7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> per response, including gathering, xeroxing and mailing the required material. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Information and Records Management Branch, MNBB-7714, Division of Information Support Services, Office of Information Resources Management, U.S.

Nuclear Regulatory Commission, Washington, D.C. 20555; and to the Paperwork Reduction Project (3150-0101), Office of Information and Regulatory Affairs, NEOB-3019, Office of Management and Budget, Washington, D.C. 20503.

If you have any questions regarding the examination procedures and requirements, please contact Mr. Warren J. Eresian at (301) 415-1833.

Sincerely, ORIGINAL SIGNED BY Warren J. Eresian, Chief Examiner Non-Power Reactors and Decommissioning Project Directorate Division of Regulatory improvement Programs Office of Nuclear Reactor Regulation Docket No. 50-188

Enclosures:

1. Reference Material for Reactor / Senior Reactor Operator Licensing Examinations
2. Administration of Written Examinations
3. Procedures for Administration of Written Examinations
4. Facility Review of Written Examinations DISTRIBUTION:

Docket File 50-188 PDR/LPDR Facility File (DMcCain)

TMichaels, PM DOCUMENT NAME: G:\SECY\ERESIAN\KSU90.WPD

'See previous concurrence Ta receive a copy of thh docunnent. Indicate in the bour "C* = Copy without ett.2 sent/ enclosure "E" = Copy with attachment /nnelosure "N* = No copy OFFICE PDND:PM V l HOLB:LA , [f PDND:W ,7 NAME WEresian tkfj DMcCaF SWeisf)OM DATE 03/22/99 03/22/99 03M499 i OFFICIAL RECORD COPY

q'.

  • i Mr. Brendan Ryan This request is covered by Office of Management and Budget (OMB) Clearance Number 3150-0101, which expires April 30, 2000. The estimated average burden is 7.7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> per response, including gathering, xeroxing and mailing the required material. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for ,

reducing this burden, to the Information and Records Management Branch, MNBB-7714, Division of Information Support Services, Office of information Rescurces Management, U.S.

Nuclear Regulatory Commission, Washington, D.C. 20555; and to the Paperwork Reduction Project (3150-0101), Office of Information and Regulatory Affairs, NEOB-3019, Office of Management and Budget, Washington, D.C. 20503.

If you have any questions regarding the examination procedures and requirements, please <

contact Mr. Warren J. Eresian at (301) 415-1833.  !

Sincerely, ,

W D44 Q j Warren J. Eresian, Chief Examiner Non-Power Reactors and Decommissioning 1 Project Directorate Division of Regulatory improvement Programs Office of Nuclear Reactor Regulation Docket No. 50-188

Enclosures:

1. Reference Material for Reactor / Senior Reactor Operator Licensing Examinations
2. Administration of Written Examinations
3. Procedures for Administration of Written Examinations
4. Facility Review of Written Examinations

. .p Kansas State University Docket No. 50-188 cc:

Office of the Governor State of Kansas Topeka, KS 66612 Mayor of Manhattan P. O. Box 748 Manhattan, Kansas 66502 1

I l

l l

l i

^

1 i

s. . \

l l

REFERENCE MATERIAL FOR REACTOR / SENIOR REACTOR OPERATOR l 1.lCENSING EXAMINATIONS (NON-POWER}

1. Existing learning objectives, students handouts and lesson plans (including training j manuals, plant orientation manual, system aescriptions, reactor theory, thermodynamics, etc.).

Training materials should include all substantive written materia! used for preparing applicants for initial RO and SRO licensing. The written material should include learning objectives if available and the details presented during lectures, rather than outlines.

Training materials should be identified, bound, and indexed. Training materials which l include the following should be provided: 1 System descriptions including descriptions of a'l operationally relevant flow '

paths, components, controls and instrumentation. System training material should draw parallels to the actual procedures used for operating and applicable system.

Complete and operationally useful descriptions of all safety-system interactions, secondary interactions under emergency and abnormal conditions, including consequences of anticipated operator error, maintenance error, and equipment failure.

Training material used to clarify and strengthen understanding of emergency operating procedures.

2. Complete Procedure Index (including temporary procedures).
3. All administrative procedures as applicable to reactor operation or safety.
4. Allintegrated plant procedures, normal or general operating procedures and procedures for experiments.
5. All emergency procedures, emergency instructions, abnormal or special procedures.
6. Standing orders or procedures changed by reactor supervision and important orders or changes that are safety related and may supercede the regular precedures.
7. Applicable procedures (procedures that are run frequently).
8. Fuel-handling and core-loading procedures and initial core-loading procedure, when appropriate.
9. Any annunciator / alarm procedurcs, as applicable.
10. Radiation protection manual, radiation control manual or procedures.
11. Emergency plan implementing procedures.

ENCLOSURE 1

2-

12. Safety Analysis Report, Technical Specifications and interpretations, if available.
13. System operating procedures, including experiments
14. Piping and instrumentation diagrams, electrical single-line diagrams, or flow diagrams, as applicable.
15. Technical Data Book, and/or plant curve information as used by operators and facility precautions, limitations, and set points for the facility.
16. Questions and answers specific to the facility training program which may be used in the written or operating examinations (voluntary by facility licensee).
17. Additional mate-ial as requested by the examiners to develop examinations that meet the requirements of the Non-Power Reactor Examiner Standards and Regulations The above reference material should be approved finalissues and so marked. If a facility has not finalized some of the material, the Chief Examiner should veri'y with the facility that the
most complete, up-to-date material is available and that agreement has been reached with the licensee for limiting changes before the administration of the examination.

l

)

ENCLOSURE 1

.e .

l e

ADMINISTRATION OF WRITTEN EXAMINATIONS i 1

1. A single room must be provided for administration of the written examination. The I location of this room and supporting restroom facilities should be such as to prevent  !

contact with all other facility personnel during the written examination. )

2. Minimum spacing is necessary to ensure examination integrity as determined by the Chief Examiner (i.e., one applicant per table, with a three-foot space between tables).
3. Acceptable arrangements should be made by the facility if the applicants are to have i lunch, coffee or other refresnments. These arrangements shall comply wlth item 1 above and must be reviewed by the examiner and/or proctor.
4. The facility licensee provides pads of 81/2 by 11 inch lined paper in unopened packages for each applicant's use in completing the examination. The examiner distributes these pads to the applicants as needed.
5. Applicants may bring pens, pencils, calculators or slide rules into the examination room.

Only black ink or dark pencils should be used for writing answers to questions.

6. No wall charts, models, and/or other training materials can be present in the l examination room. No other equipment or reference material will be allowed unless provided by the examiner.
7. The fac;lity staff is provided with a copy of the written examination and answer key after j the last candidate has handed in his written examination. The facility staff will then have five (5) working days to provide formal written comments with supporting documentation regarding written examination questions and answers to the Chief Examiner.

PROCEDURES FOR THE ADMINISTRATION OF WRITTEN EXAMINATIONS

1. Verify candidate identity.
2. Pass out examinations and all handouts. Remind applicants not to review examination untilinstructed to do so.

READ THE FOLLOWING INSTRUCTIONS VERBATIM:

1. Cheating on the examination means an automatic denial of your application and could result in more severe penalties.
2. After the examination has been completed, you must sign the statement on the cover sheet indicating that the work is your own and yw have not received or given assistance in completing the examination. This must be done after you complete the examination.

ENCLOSURE 2

- - - - -r ,g-www --,v--+g, '

READ THE FOLLOWING INSTRUCTIONS:

1. Restroom trips are to be limited and only one applicant at a time may leave. You must avoid all contact with anyone outside the examination room to avoid even the appearance or possibility o'i cheating.
2. Use black ink or dark pencil only to facilitate legible reproductions.
3. Print your name in the blank provided in the upper right-hand corner of the examination cover sheet and each answer sheet.
4. Mark your answers on the answer sheet provided. USE ONLY THE PAPER PROVIDED AND DO NOT WRITE ON THE BACK SIDE OF THE PAGE.
5. Before you turn in your examination, consecutively number each answer sheet.
6. The point value for each question is indicated in [ brackets] after the question.
7. If the intent of a question is unclecr, ask questions of the examiner only.  ;
8. When turning in your examination, assemble the completed examination with examination questions, examination aids and answer sheets, in addition, turn in all scrap paper,  !
9. Ensure all information you wish to have evaluated as part of your answer is on your answer sheet. Scrap paper will be dispose; 'f immediately following the examination.
10. To pass the examination, you must achieve a grade of 70 percent or greater in each category.
11. There is a time limit of three (3) hours for completion of the examination.-
12. When you have completed and turned in your examination, leave the examination area (DEFINE THE AREA). If you are observed in this area while the examination is stillin progress, your license may be denied or revoked.

ENCLOSURE 2

-. . . _ - .- . . _ . . - - - . - . . - . - - - . - _ . . - . . ~ - . - . . _ . _

L ., ,.

I l

4 FACILITY REVIEW OF WRITTEN EXAMINATIONS

1. At the option of the Director, Non-Power Reactors and Decommissioning Project Directorate, the facility may review the written examination up to two weeks prior to its administration. This review may take place at the facility or an NRC office. The Chief Examiner wil! coordinate the details of the review with the facility. An NRC examiner will always be present durirsg the review. The examination or written notes will NOT be retained by the facility.

Whenever this option of examination review is utilized, the facility reviewers will sign the following statement prior to being allowed access to the examination.

a. Pre-Examination Security Agreement I acknowledge that I have acquired specialized knowledge concerning the examination scheduied for at as of the date of my signature below. I agree that I will not knowingly divulge any information concerning this examination to any unauthorizeri persons. I understand that I am not to participate in any instruction involving those applicants scheduled to be administered the above examination from this date until after the examination has been administered. I turther understand that violation of the conditions of this agreement may result in the examinations being cancelled and/or enforcement action against myself or the facility licensee by whom I am employed or represent.

l Signature /Date l In addition, the facility staff reviewers will sign the following statement after the written examination has been administered.

l

b. Post-Examination Security Agreement I __ did not, to the best of my knowledge, divulge any information concerning the examinations administered during the week of ,

j at or any l instruction to those applicants who were administered the examination from the date I entered into this security agreement until the completion of examination administration.

Signature /Date 2

5 ENCLOSURE 4 I

e i

_~ - ._. = - . _ _ _ _ = _ _ _ _ , , . . . - - .

t

2. Regardless of whether the above examination review option is exercised, immediately following the administration of the written examination, the facility staff is provided a marked-up copy of the examination and the answer key. The copy of the written examination includes pen and ink changes made to questions during the examination administration.

If the facility did not review the examination prior to its administration, they will have five (5) working days from the day of the written examination to submit formal comments. If the facility reviewed the examination prior to its administration, any additional comments must be given to an examiner prior to his/her leaving the facility. These comments will be addressed to the Chief Examiner by the Reactor Supervisor. Comments not submitted within the required time frame will be considered for inclusion in the grading process on a case-by-case basis. This may cause delays in grading the examinations.

3. The fc!!owing format should be used for submittal of specific comments:
a. Listing of NRC question, answer and reference
b. Facility comment / recommendation
c. Reference (to support facility comment)

NOTES: 1. No change to the examination will be made without submittal of a reference to support the facility comment. Any supporting documentation that was not previously supplied, should be provided.

2. Corr,ments made without a concise facility recommendation wi;l not be addressed.

3 A two-hour post examination review may be held at the discretion of the Chief Examiner, if this review is held, the facility staff should be informed that only written comments that are properly supported will be considered in the grading of the examination.

ENCLOSURE 4