Text
-
DISTRIBUTION Docket File WM-64 PDR/DCS DBangart, RIV WM-64/TT0/86/04/18/1 T01sen
_1 HRose RBrich APR 21 av6 PGarcia EHawkins LLW Branch, WMLU URF0 r/f URc0:TTO Docket No. WM-64 040WM64701E John G. Themelis, Project Manager Uranium Mill Tailings Project Office U.S. Department of Energy Albuquerque Operations Office P.O. Box 5400 Albuquerque, New Mexicc 87115
Dear Mr. Themelis:
In accordance with your requests, we have reviewed the " Remedial Action Inspection Plan" for the Lakeview, Oregon, UMTRA Project. Our connents and questions are enclosed.
If you have any questions, please contact Tom Olsen at FTS 776-2813 or i
me.
l l
Sincerely, ll5ll 7
Edward F. Hawkins, Chief l
Licensing Branch 1 k
Uranium Recovery Field Office Region IV f
Enclosure:
As stated cc:
J. G. Oldham, M-K F. R. Miera, DOE, OR 8605120030 860422 PDR WASTE PDR WM-64 0FC : URF0
- URF NAME : T01sen/lv
- EHawkins DATE :86/04/18
1 o
/
Questions and comments on RAIP - Lakeview, Oregon, UMTRA Project Page 4, section 6.3.3 - Radon Barrier This section discusses the types of tests to be performed during placement of the radon barrier material; however, the frequency of the tests is not quantified, nor are the testing methods specified.
The statement that tests will be performed "as frequently as is required" is unacceptable. A statement that delineates the types of tests and quantifies the frequency should be added to this section.