ML20203N875

From kanterella
Jump to navigation Jump to search
Forwards Proposed Rev 8 to QA Program Topical Rept for Review & Approval.Changes Reduce Commitments Contained in Previously Accepted QA Program Description.W/O Encl.Fee Paid
ML20203N875
Person / Time
Site: Millstone, Haddam Neck, 05000000
Issue date: 04/29/1986
From: Opeka J
NORTHEAST UTILITIES, NORTHEAST UTILITIES SERVICE CO.
To: Murley T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
B12023, NUDOCS 8605060171
Download: ML20203N875 (2)


Text

NORTHEAST UTILITIES o.m.,.i On.c... som.n si,

. B.,nn. cono.ci,coi N EsI N a5a P.O. BOX 270 s-e n=<***** * " "

HARTFORD CONNECTICUT 06141-0270 J $,%,CC,$~',

t203) 66s-5000 k

. L April 29,1986 Docket Nos. 50-213 50-245 30-336 50-423 B12023 Dr. Thomas Murley Regional Administrator Region i U. S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, PA 19406 Gentlenen:

Haddam Neck Plant Millstone Nuclear Power Station, Unit Nos.1,2 and 3 Reporting of Changes to the Quality Assurance Program Proposed Revision 8 to the Northeast Utilities Quality Assurance Program Topical Report in accordance w;th 10CFR50.54(a)(3), transmitted herewith are three (3) copies of proposed Revision 8 of the Northeast Utilities Quality Assurance Frogram (NUQAP) Topical Report (Attachment il) submitted for your review and approval. Proposed changes to the Topical Report are indicated by a vertical line in the right-hand margin of the text. The reason and basis for each change are detailed in Attachrnent I which is arranged in a sequence which comcides with the Topical Report sections.

The changes included in proposed Revision 8 of the NUQAP Topical Report do reduce commitments contained in our previously accepted quality assurance program description and are submitted for your approval prior to implementation. This proposed revision of the NUQAP Topical Report, although reducing previously accepted commitments, continues to satisfy the criteria of 10CFR30 Appendix B.

Please note that the draf t NUQAP Topical Report is shown as Revision 8 without a date. This draf t will be issued as Revision 8 and dated the same as the effective date of approval when we receive it, or sixty (60) days following this submittal as prescribed in 50.54(a)(3)(iv).

Please be advised that this submittal is in addition to the annual submittal of quality assurance program changes required by 10CFR$0.54(a)(3).

Northeast Utilities will be submitting additional quality assurance program changes during June of this year.

p\\

8605060171 860429 DR ADOCK 05000213

\\\\

p PDR fC YU/rcK 5 'WO 00

=

..- Pursuant to the requirements of 10CFR170.12(c), enclosed with this submittal is the application fee of $150.00.

Very truly yours, NORTHEAST UTILITIES SERVICE COMPANY 5 0%$t-J. F. OpWa V

Senior Vice President cc:

U. S. NRC Document Control Desk (15 copies)

NRC Region IV Vendor Program Branch (1 copy)

NRC Senior Resident inspector - Millstone Station (1 copy)

NRC Senior Resident Inspector - Haddam Neck (1 co NRC Resident inspector - Millstone Station (I copy) py)