MONTHYEARML23339A0042023-12-0404 December 2023 Email Submitting Form 897 ML21287A4512021-10-15015 October 2021 Email for NuScale Topical Report Quality Assurance Program Description Topical Report -A Version Verification ML21154A1322021-05-26026 May 2021 Final Safety Evaluation Transmittal Email ML21053A2662021-02-22022 February 2021 SMR DC Docs - FW: NuScale EPZ Review Path Forward ML20203M1872020-07-14014 July 2020 Control Room Staffing Topical Report - NRC Staff'S Documentation of the Results of the Completeness Review ML20190A2352020-07-0808 July 2020 SMR DC Docs - Approved Version of NuScale Topical Report, Rod Ejection Accident Methodology, TR-0716-50350, Revision 1 ML20141L6102020-05-20020 May 2020 SMR DC Docs - NuScale Topical Report - Approved Version of NuScale Applicability of Areva Method for the Evaluation of Fuel Assembly Structural Response to Externally Applied Forces, TR-07116-50351, Revision 1 ML20090A8642020-03-30030 March 2020 SMR DC Docs - NuScale Topical Report - Approved Version of TR-0516-49417, Evaluation Methodology for the Stability of the NuScale Power Module, Revision 1 ML19331A7302019-11-27027 November 2019 SMR DC Docs - FW: Ibr Flow Chart ML19331A7382019-11-27027 November 2019 SMR DC Docs - FW: Chapter 18 (Di IP) Related (non-prop) ML19331A7262019-11-26026 November 2019 SMR DC Docs - (External_Sender) Ibr Flow Chart ML19329E7132019-11-25025 November 2019 SMR DC Docs - FW: Chapter 18 (Di IP) Related ML19323F6982019-11-19019 November 2019 DCA Technical Specification Confirmatory Items - Email Commitments ML19329E7022019-11-0606 November 2019 SMR DC Docs - (External_Sender) Chapter 18 (Di IP) Related ML19309D7862019-10-31031 October 2019 Reconciliation - NRR Response to Acrs' September 20 2019 Letter on NuScale Stability Analysis Topical Report ML19309E0172019-10-31031 October 2019 Reconciliation - NRR Response to Acrs'S September 24 2019 Letter on NuScale External Forces Topical Report ML19309F8612019-10-31031 October 2019 Reconciliation - NRR Response to Acrs'S September 25, 2019 Letter on the Focus Area Review Approach ML19276D2812019-10-0303 October 2019 SMR DC RAI - Request for Additional Information No. 526 Erai No. 9719 ML19235A1092019-08-23023 August 2019 SMR DC RAI - Request for Additional Information No. 525 Erai No. 9705 (19.02) ML19206B0772019-07-25025 July 2019 SMR DC Docs - FW: FW: NuScale Chapter 5 Section 5.2.3 - Changes to Information on Check Valves ML19171A0092019-06-20020 June 2019 SMR DC RAI - Request for Additional Information No. 524 Erai No. 9691 (3.9.4) ML19157A0352019-06-0606 June 2019 SMR DC RAI - Request for Additional Information No. 523 Erai No. 9682 (12.3-12.4, 9.3.2) ML19150A3172019-05-30030 May 2019 SMR DC RAI - Request for Additional Information No. 522 Erai No. 9681 (14) ML19151A0272019-05-30030 May 2019 SMR DC RAI - Request for Additional Information No. 522 Erai No. 9681 (14) ML19099A1272019-04-0909 April 2019 SMR DC Docs - FW: NuScale Comments Chapter 5 SER W/Ois ML19098A2362019-04-0808 April 2019 SMR DC Docs - FW: NuScale Comments Chapter 5 SER W/Ois ML19089A0112019-03-29029 March 2019 SMR DC Docs - NuScale Topical Report - Approved Version of Subchannel Analysis Methodology, TR-0915-17564, Revision 2 ML19081A2722019-03-22022 March 2019 SMR DC RAI - Request for Additional Information No. 521 Erai No. 9672 (19) ML19079A3632019-03-20020 March 2019 SMR DC RAI - Request for Additional Information No. 520 Erai No. 9642 (16) ML19077A2852019-03-18018 March 2019 SMR DC RAI - Request for Additional Information No. 519 Erai No. 9656 (12.03) ML19063D4042019-03-0404 March 2019 SMR DC RAI - Request for Additional Information No. 518 Erai No. 9659 (19) ML19062A0012019-03-0303 March 2019 SMR DC RAI - Request for Additional Information No. 518 Erai No. 9659 (19) ML19057A4382019-02-26026 February 2019 SMR DC Docs - March 5, 2019, Public/Closed Meeting on NuScale EPZ Sizing Methodology Topical Report_Nrc Staff Talking Points (Public) ML19056A5062019-02-25025 February 2019 SMR DC RAI - FW: Request for Additional Information No. 365 RAI No. 9309 (3.8.4) Rev 1 (to Remove Prop from Previous Subject Line) ML19046A0672019-02-15015 February 2019 SMR DC RAI - Request for Additional Information No. 517 Erai No. 9657 (12.03) ML19032A1202019-02-0101 February 2019 SMR DC RAI - Request for Additional Information No. 516 Erai No. 9647 (15.0.6) ML19016A2692019-01-16016 January 2019 SMR DC RAI - Request for Additional Information No. 515 Erai No. 9607 (12.02) Revision 1 ML19015A2782019-01-15015 January 2019 SMR DC RAI - Request for Additional Information No. 366 RAI No. 9292 (12.3) ML19015A2742019-01-15015 January 2019 SMR DC RAI - Request for Additional Information No. 486 Erai No. 9296 (12.3) ML19014A0882019-01-14014 January 2019 SMR DC RAI - Request for Additional Information No. 515 Erai No. 9607 (12.02) ML19014A0842019-01-14014 January 2019 SMR DC RAI - FW: Request for Additional Information No. 371 RAI No. 9373 (15.06.06) ML19003A1772019-01-0303 January 2019 SMR DC Docs - Approved Version of NuScale Topical Report TR-0616-48793, Nuclear Analysis Codes and Methods Qualification, Revision 1 ML19003A4612019-01-0303 January 2019 SMR DC Docs - Approved Version of Topical Report TR-0116-21012, NuScale Power Critical Heat Flux Corrections, Revision 1 ML18352B0812018-12-18018 December 2018 SMR DC RAI - Request for Additional Information No. 513 Erai No. 9643 (4.04) ML18352B0852018-12-18018 December 2018 SMR DC RAI - Request for Additional Information No. 514 Erai No. 9645 (4.04) ML18341A3452018-12-0707 December 2018 SMR DC RAI - NuScale Request for Additional Information -eRAI No. 9631, Section 6.2.6 - Cancelled ML18333A0212018-11-29029 November 2018 SMR DC RAI - Request for Additional Information No. 512 Erai No. 9634 (16) ML18324A8142018-11-20020 November 2018 SMR DC RAI - Request for Additional Information No. 511 Erai No. 9613 (12.02) ML18312A2492018-11-0808 November 2018 SMR DC Docs - FW: NuScale FSAR Draft Changes in Section 2.4.4 ML18309A2642018-11-0505 November 2018 SMR DC RAI - Request for Additional Information No. 510 Erai No. 9631 (6.2.6) 2023-12-04
[Table view] |
Text
From: Tesfaye, Getachew To: Osborn, Jim Cc: Bradford, Anna; Dudek, Michael; Cowdrey, Christian; Green, Brian; Scheetz, Maurin; Bavol, Bruce; Melton, Mike; English, Liz; Bryan, Marty
Subject:
Completeness Review for "NuScale Control Room Staffing Plan" Topical Report Rev. 0 Date: Tuesday, July 14, 2020 6:54:00 PM
- Jim, As I informed you on Friday July 10, 2020, we have completed the completeness review of the "NuScale Control Room Staffing Plan" Licensing Topical Report (LTR) Rev. 0 (TR-0420-69456) submitted to the NRC on June 11, 2020. Based on our evaluation, we have determined that the LTR provides sufficient technical information for the NRC staff to conduct a detailed technical review. If the NRC staff needs additional information to complete its review, we will issue formal requests for additional information (RAIs).
At this time, we are unable to commit to a 12-month review and approval timeframe you requested due to the potential policy issue involving the elimination of the Shift Technical Advisor (STA) position. If the proposed elimination of STA position does not involve policy issues, then we would plan to issue the advanced safety evaluation report to ACRS by February 15, 2021, and to brief ACRS by March 31, 2021. We would expect NuScale to issue the Approved version by May 31, 2021. If the proposed elimination of the STA position does involve policy issues, we expect as much as 6 months to be added to the review time.
If the proposed elimination of STA position does not involve policy issues, then the NRC staff estimates that conducting a detailed safety review of this LTR will require approximately 500 staff-hours, including project management time. This estimate is based on RAIs with a 30-day NuScale response time, with the initiation of a NuScale RAI review timeline that starts upon draft RAI receipt. The estimate also assumes three meetings between the NRC staff and the NuScale staff to discuss the LTR review, an audit that is currently planned for the week of August 24, 2020, and presentations to the ACRS. This estimate is based on the NRC staffs cursory review for sufficiency and completeness. The level of effort could change once the NRC staff delves into matters of technical and/or policy merit during the detailed safety review of the LTR. Similarly, the schedule could change if additional rounds of RAIs are needed, or if the ACRS declines to review the LTR.
If you have any question regarding this matter, please do not hesitate to contact me.
Best regards, Getachew Tesfaye Senior Project Manger NRC/NRR/DNRL/NRLB Tel. (301) 415-8013