|
---|
Category:CORRESPONDENCE-LETTERS
MONTHYEARIR 05000412/19990071999-10-21021 October 1999 Refers to Special Team Insp 50-412/99-07 Conducted from 990720-29 & Forwards Nov.Two Violations Identified.First Violation Involved Failure to Implement C/A to Prevent Biofouling of Service Water System ML20217M1591999-10-19019 October 1999 Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates L-99-143, Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct1999-10-11011 October 1999 Informs That Subsequent Review of Approval Ltrs & SE for Relief Requests 1TYP-2-B5.40-1 (Rev 0),BV1-RV-AUG (Rev 1), BV2-RV-AUG (Rev 1),BV3-IWA-1 (Rev 1) & BV3-IWA-2 (Rev 1) Identified Erroneous Statements Which Dl Wishes to Correct L-99-152, Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections1999-10-11011 October 1999 Submits Relief Request BV3-N-533-1,rev 0,requesting Use of ASME Approved Code Case N-553-1, Alternative Requirements for VT-2 Visual Examination of Class 1,2 & 3 Insulated Pressure Retaining Bolted Connections ML20217C6741999-10-0808 October 1999 Forwards RAI Re Licensee 970128 Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions, . Response Requested within 60 Days of Receipt of Ltr L-99-151, Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program1999-10-0707 October 1999 Responds to NRC Re Violations Noted in Insp Rept 50-412/99-07.Corrective Actions:Condition Repts Were Written for Listed Issues So That Repts Could Be Addressed Using BVPS Corrective Action Program ML20217E0301999-10-0707 October 1999 Forwards Insp Repts 50-334/99-06 & 50-412/99-06 on 990809-13 & 990823-27.Violation Noted Involving Failure to Correctly Translate Design Change Re Pertinent Operating Logs & Plant Equipment Labeling ML20212M2661999-09-30030 September 1999 Forwards Order Approving Transfer of Licenses for Beaver Valley from Dlc to Pennsylvania Power Co & Approving Conforming Amends in Response to 990505 Application ML20212K8071999-09-30030 September 1999 Informs That on 990916,NRC Staff Completed mid-cycle Plant Performance Review (PPR) of Facility.Staff Conducted Reviews of All Operating NPPs to Integrate Performance Info & to Plan for Insp Activities at Facility ML20216J9621999-09-30030 September 1999 Forwards Insp Repts 50-334/99-05 & 50-412/99-05 on 990725-0904.Two Violations Noted & Being Treated as Ncvs.One Violation Re Failure to Follow Operation Manual Procedure Associated with Configuration Control Identified L-99-149, Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion1999-09-28028 September 1999 Informs NRC That Items Identified in 990629 Response to GL 98-01 Have Been Completed.Attached Table Submitted with Has Been Updated to Reflect Completion L-99-148, Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 9908171999-09-24024 September 1999 Notifies NRC of License Withdrawal of M Linch,License SOP-11478 IAW 10CFR50.74.M Linch Resigned from Employment at Bvps,Effective 990817 ML20212G0601999-09-23023 September 1999 Forwards Answer of Duquesne Light Co to Petition to Waive Time Limits & Suppl Comments of Local 29, Intl Brotherhood of Electrical Workers.Copies of Answer Have Been Served to Parties & Petitioner by e-mail or Facsimile ML20212C5521999-09-21021 September 1999 Forwards for Filing,Answer to Firstenergy Nuclear Operating Co & Pennsylvania Power Co in Opposition to Petition to Waive Time Limits & Suppl Comments of Local 29 Intl Brotherhood of Electrical Workers L-99-144, Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-031999-09-20020 September 1999 Forwards NRC Form 536 Which Addresses Util Proposed Operator Licensing Exam Schedule,In Response to Administrative Ltr 99-03 ML20212B3291999-09-16016 September 1999 Forwards for Filing,Petition to Waive Time Limits in 10CFR2.1305 & Supplemental Comments of Local 29,Intl Brotherhood of Electrical Workers Re Beaver Valley Power Station,Units 1 & 2 L-99-134, Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC1999-09-15015 September 1999 Provides Addl Info to Support 990617 LAR 127,proposing Mods to Heatup,Cooldown & Overpressure Protection Curves.Info Is Provided to Formally Docket Info Discussed During 990820 Telcon with NRC ML20211Q3431999-09-0808 September 1999 Informs That During 990903 Telcon Between L Briggs & T Kuhar,Arrangements Were Made for NRC to Inspect Licensed Operator Requalification Program at Plant,Unit 1.Insp Planned for Wk of 991115 ML20211Q5601999-09-0707 September 1999 Forwards Insp Rept 50-412/99-07 on 990720-29.Three Apparent Violations Noted & Being Considered for Escalated Ea. Violations Involve Failure to Implement C/As to Prevent bio- Fouling of Svc Water Sys L-99-138, Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d)1999-09-0303 September 1999 Forwards Rev 37 to Issue 4 for BVPS Physical Security Plan (PSP) (Base Plan,Safeguards Contingency Plan & Training & Qualification Plan).Changes to Plan Are Listed.Encls Withheld Per 10CFR2.790(d) L-99-136, Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls1999-09-0202 September 1999 Forwards Data Point Library (Dpl) Changes,Iaw Provisions of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6, Administrative Implementation Requirements. Ten Listed Dpls Have Specific Setpoint Values Removed,Per Unit 2 Dpls L-99-098, Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods1999-09-0202 September 1999 Forwards Proposed Changes to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Change Would Reduce Operations QA Program Description Commitments by Limiting Required Onsite Safety Committee Reviews of Mods L-99-137, Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 31999-08-31031 August 1999 Forwards Issue 3,rev 3 to Bvps,Unit 1 Inservice Testing Program for Pumps & Valves. Encl 1 Provides Summary of IST Program Changes Which Have Been Incorporated Into Issue 3, Rev 3 L-99-022, Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl1999-08-31031 August 1999 Forwards Issue 2,Rev 1 to Bvps,Unit 2 Inservice Testing (IST) Program for Pumps & Valves. Summary of Changes,Encl L-99-012, Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2,operations QA Program Description,Per 10CFR50.54(a)(3)(ii),including Description of Proposed Change,Reason for Change & Basis for Concluding Revised Program Satisfy 10CFR50,App B L-99-037, Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change1999-08-30030 August 1999 Forwards Proposed Change to Bvps,Units 1 & 2 Operations QA Program Description,Iaw 10CFR50.54(a)(3)(ii).Attachment 1 Further Describes Proposed Change & Identifies Reason for Change L-99-132, Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 21999-08-26026 August 1999 Forwards fitness-for-duty Program Six Month Rept for 990101-990630 for Bvps,Units 1 & 2 05000412/LER-1999-007, Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info1999-08-19019 August 1999 Forwards LER 99-007-00, Forced Shutdown Due to Inoperable EDG, Per 10CFR50.73(a)(2)(i).Rept Is Delayed Due to Util Needing Addl Three Days to Address Event Issues on Reportability & Provide Addl Safety Implications Info ML20211A5111999-08-18018 August 1999 Forwards Insp Repts 50-334/99-04 & 50-412/99-04 on 990613- 990724.One Violation Noted & Treated as Non-Cited Violation Involved Failure to Maintain Containment Equipment Hatch Closed During Fuel Movement L-99-127, Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel1999-08-17017 August 1999 Provides Response to NRC Ltr Requesting Review & Comment of NRC Reactor Vessel Structural Integrity Database by 990901.Inconsistencies Noted in Way Data Characterizes Condition of Reactor Vessel L-99-124, Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached1999-07-30030 July 1999 Requests Withdrawal of Editorial Changes That Do Not Pertain to Transfer of Operating Authority or Plant Ownership That Are Proposed in LARs 269 & 144.Revised mark-up License Pages Reflecting Changes,Attached L-99-121, Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements1999-07-28028 July 1999 Submits Data Point Library (Dpl) Changes,Iaw Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,rev 1,Section 3.6, Administrative Implementation Reqiurements L-99-118, Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 20011999-07-25025 July 1999 Forwards Response to NRC AL 99-02,request for Info Re Estimate of Number of New Licensing Actions Expected to Be Submitted in Fy 2000 & 2001 L-99-120, Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations1999-07-22022 July 1999 Forwards Annual Rept of Facility Changes,Tests & Experiments for BVPS Unit 1,IAW 10CFR50.59.Rept Provides Brief Description of Each Facility & Procedure Change & Summary of Safety Evaluations L-99-119, Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 9901221999-07-20020 July 1999 Forwards Rev 17 to UFSAR for Beaver Power Station,Unit 1. Submittal Reflects Changes to Facility & Procedures as Described in UFSAR That Were Completed During Annual Reporting Period Endinig 990122 L-99-113, Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by1999-07-15015 July 1999 Forwards Final,Typed TS Pages for LARs 262 & 135,previously Submitted with Editorial Changes Identified by L-99-111, Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes1999-07-15015 July 1999 Forwards Revised Final Typed Pages for LARs 109 & 115, Previously Submitted by 990615 & 28 Ltrs.Revised Pages Replace Those Previously Provided for LARs 109 & 115.With Summary of Editorial Changes L-99-112, Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl1999-07-14014 July 1999 Responds to NRC Questions Made During 990518 Meeting with Util Re LARs 220 & 88,for Bvps,Units 1 & 2.Copy of Ltr DLC-99-743,which Is non-proprietary Version of DLC-96-310 & Westinghouse Technical Bulletin ESBU-TB-96-07-R0 Also Encl L-99-110, Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.61999-07-14014 July 1999 Forwards Changes to ERDS for Unit 1,IAW Requirements of 10CFR50,App E,Section VI.3.a & NUREG-1394,Rev 1,Section 3.6 ML20209G5701999-07-12012 July 1999 Discusses Closure of TACs MA0525 & MA0526 Re Response to RAI Concerning GL 92-0,Rev 1,Suppl 1, Rv Structural Integrity. Info in Rvid Revised & Released as Ver 2 as Result of Review of Response ML20207H6621999-07-0808 July 1999 Forwards RAI Re Util 981112 Response to IPEEE Evaluations for Plant,Units 1 & 2.RAI Was Discussed During 990628 Telcon in Order to Ensure Clear Consistent Understanding by All Parties of Info Needed L-99-105, Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves1999-07-0808 July 1999 Forwards Response to NRC 990420 RAI Re Previous Responses to GL 95-07, Pressure Locking & Thermal Binding of SR Power-Operated Gate Valves ML20209D8191999-07-0707 July 1999 Forwards Insp Repts 50-334/99-03 & 50-412/99-03 on 990502- 0612.No Violations Noted.Program for Maintaining Occupational Exposures as Low as Reasonably Achievable (ALARA) & for Training Personnel,Generally Effective L-99-109, Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-62301999-07-0707 July 1999 Forwards Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999, IAW ASME Boiler & Pressure Vessel Code,Section Xi,Article IWA-6230 L-99-108, Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC1999-07-0707 July 1999 Requests Withdrawal of Change Proposed for TS Bases Page B 3/4 2-2 from LARs 1A-262 & 2A-135,originally Submitted by Licensee to NRC L-99-104, Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl1999-06-29029 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness at Nuclear Power Plants. Disclosure Rept Encl L-99-093, Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.51999-06-25025 June 1999 Provides Response to RAI on Proposed Change to Operations QA Program Description.Attachment 2 Provides Revised Markup for Proposed Changes to Affected UFSAR Section 17.2.5 L-99-102, Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl1999-06-22022 June 1999 Forwards Typed,Final TS Pages for LARs 259 & 131.Summary of Description of Plant Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages,Encl L-99-101, Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal1999-06-22022 June 1999 Submits Response to NRC Oral RAI Concerning Qualifications for Senior Nuclear Executive Ref in 10CFR50.80 Submittal L-99-062, Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages1999-06-17017 June 1999 Forwards Final TS Pages for LARs 262 & 135,including Summary Description of Plants Editorial Changes Incorporated in Addition to Those Addressed in Previously Provided marked-up Pages 1999-09-08
[Table view] Category:OUTGOING CORRESPONDENCE
MONTHYEARIR 05000412/19990071999-10-21021 October 1999 Refers to Special Team Insp 50-412/99-07 Conducted from 990720-29 & Forwards Nov.Two Violations Identified.First Violation Involved Failure to Implement C/A to Prevent Biofouling of Service Water System ML20217M1591999-10-19019 October 1999 Forwards NRC Rept Number 17, Requal Tracking Rept from Operator Licensing Tracking Sys.Rept Was Used by NRC to Schedule Requalification Exam for Operators & Record Requal Pass Dates ML20217C6741999-10-0808 October 1999 Forwards RAI Re Licensee 970128 Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident Conditions, . Response Requested within 60 Days of Receipt of Ltr ML20217E0301999-10-0707 October 1999 Forwards Insp Repts 50-334/99-06 & 50-412/99-06 on 990809-13 & 990823-27.Violation Noted Involving Failure to Correctly Translate Design Change Re Pertinent Operating Logs & Plant Equipment Labeling ML20212K8071999-09-30030 September 1999 Informs That on 990916,NRC Staff Completed mid-cycle Plant Performance Review (PPR) of Facility.Staff Conducted Reviews of All Operating NPPs to Integrate Performance Info & to Plan for Insp Activities at Facility ML20216J9621999-09-30030 September 1999 Forwards Insp Repts 50-334/99-05 & 50-412/99-05 on 990725-0904.Two Violations Noted & Being Treated as Ncvs.One Violation Re Failure to Follow Operation Manual Procedure Associated with Configuration Control Identified ML20212M2661999-09-30030 September 1999 Forwards Order Approving Transfer of Licenses for Beaver Valley from Dlc to Pennsylvania Power Co & Approving Conforming Amends in Response to 990505 Application ML20211Q3431999-09-0808 September 1999 Informs That During 990903 Telcon Between L Briggs & T Kuhar,Arrangements Were Made for NRC to Inspect Licensed Operator Requalification Program at Plant,Unit 1.Insp Planned for Wk of 991115 ML20211Q5601999-09-0707 September 1999 Forwards Insp Rept 50-412/99-07 on 990720-29.Three Apparent Violations Noted & Being Considered for Escalated Ea. Violations Involve Failure to Implement C/As to Prevent bio- Fouling of Svc Water Sys ML20211A5111999-08-18018 August 1999 Forwards Insp Repts 50-334/99-04 & 50-412/99-04 on 990613- 990724.One Violation Noted & Treated as Non-Cited Violation Involved Failure to Maintain Containment Equipment Hatch Closed During Fuel Movement ML20209G5701999-07-12012 July 1999 Discusses Closure of TACs MA0525 & MA0526 Re Response to RAI Concerning GL 92-0,Rev 1,Suppl 1, Rv Structural Integrity. Info in Rvid Revised & Released as Ver 2 as Result of Review of Response ML20207H6621999-07-0808 July 1999 Forwards RAI Re Util 981112 Response to IPEEE Evaluations for Plant,Units 1 & 2.RAI Was Discussed During 990628 Telcon in Order to Ensure Clear Consistent Understanding by All Parties of Info Needed ML20209D8191999-07-0707 July 1999 Forwards Insp Repts 50-334/99-03 & 50-412/99-03 on 990502- 0612.No Violations Noted.Program for Maintaining Occupational Exposures as Low as Reasonably Achievable (ALARA) & for Training Personnel,Generally Effective ML20207G2611999-06-0707 June 1999 Informs That NRR Has Reorganized,Effective 990328.Forwards Organizational Chart IR 05000412/19980091999-05-26026 May 1999 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-412/98-09 ML20195C4461999-05-21021 May 1999 Forwards Insp Repts 50-334/99-02 & 50-412/99-02 on 990321-0501.No Violations Were Identified.Licensee Conduct of Activities at Beaver Valley Power Station Characterized by Safe Conduct of Activities During Refueling Outage ML20206P1241999-05-14014 May 1999 Refers to Proposed Changes Submitted by Dl on 990316 to BVPS QA Program Described in BVPS-2 Ufsar,Chapter 17.2.Forwards RAI Re Proposed QA Program Changes ML20206N3161999-05-0606 May 1999 Responds to Ltr to NRC on Continued Events Re Transfer of Generation Assets Between Dl & Firstenergy.Info Will Be Considered as NRC Monitor Pending License Transfer Application of Bvps,Units 1 & 2 & Pnpp ML20206H7931999-04-30030 April 1999 Ack Receipt of 990426 Request for Enforcement Discretion & 990427 Withdrawal of Request for Enforcement Discretion. Resolution Documented.Enforcement Discretion Not Necessary ML20206B2751999-04-22022 April 1999 Forwards Insp Repts 50-334/99-01 & 50-412/99-01 on 990207- 0320.One Violation of NRC Requirements Identified & Being Treated as non-cited Violation Consistent with App C of Enforcement Policy ML20206A8381999-04-20020 April 1999 Forwards Reactor Operator Initial Exam Rept 50-412/99-301 on 990322-25.All Three Reactor Operator Applicants Passed. Initial Written Exam Submittal Was Determined Not to Meet NRC Guidelines in Certain Instances ML20205R9071999-04-20020 April 1999 Forwards Second Request for Addl Info Re Response to GL 95-07, Pressure-Locking & Thermal-Binding of Safety-Related Power-Operated Gate Valves, for Beaver Valley Power Station,Units 1 & 2 ML20205Q8311999-04-14014 April 1999 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-334/98-11 & 50-412/98-11 Issued on 990225.Actions Will Be Examined During Future Insp of Licensed Program ML20205L0341999-04-0909 April 1999 Forwards SER Accepting Util 971209 & 980729 Submittal of Second 10-year Interval ISI Program Plan & Associated Relief Requests for Beaver Valley Power Station,Unit 2.TER Also Encl ML20205P2431999-04-0909 April 1999 Discusses 990225 PPR & Forwards Plant Issues Matrix & Insp Plan.Ltr Provided to Minimize Resource Impact on Staff & to Allow for Scheduling Conflicts & Personnel Availability to Be Resolved in Advance of Inspector Arrival ML20205K0901999-04-0505 April 1999 Informs of Individual Exam Result on Initial Retake Exam Conducted on 990322-25 at Licensee Facility.Three Individuals Were Administered Exam & All Three Passed. Forwards Encl Re Exam.Without Encl ML20205R1791999-03-30030 March 1999 Responds to Issue Re Generic Implication of part-length Control Rod Drive Mechanism Housing Leak at Praire Island, Unit 2 & Beaver Valley Power Station,Units 1 & 2 ML20205C0301999-03-26026 March 1999 Informs That Util Responses to GL 97-04, Assurance of Sufficient Net Positive Suction Head for Emergency Core Cooling & Containment Heat Removal Pumps Acceptable ML20204D7371999-03-16016 March 1999 Advises That RW Lindsey Authorized to Administer Initial Written Exams to Sh Cencic,Tf Lardin & Ta Pittas on 990322. Region I Operator Licensing Staff Will Administer Operating Tests ML20207E0201999-02-25025 February 1999 Forwards Insp Repts 50-334/98-11 & 50-412/98-11 on 981227- 990206 & Forwards Notice of Violations Re Uncontrolled Reduction of Main Condenser Vacuum ML20203D0691999-02-10010 February 1999 Forwards SE Accepting Approval of Proposed Revs to Plant QA Program Description in Chapter 17.2 of Updated Fsar,Per Util 981224 Submittal ML20206U3011999-02-0505 February 1999 Forwards Insp Repts 50-334/98-09 & 50-412/98-09 on 981116-1217 & Nov.Violation Identified Re Inadequate Design Control in Unit 2 Dc Voltage Drop Calculation ML20203A0811999-02-0404 February 1999 Forwards Request for Addl Info Re Review of Beaver Valley Power Station,Unit 1 License Amend to Allow one-time Extension of Steam Generator Insp Interval ML20199E6681999-01-14014 January 1999 Forwards RAI Re Licensee Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs, for Plant,Units 1 & 2 ML20199F1961999-01-13013 January 1999 Forwards Insp Repts 50-334/98-10 & 50-412/98-10 on 981115-1226.No Violations Noted.Informs That Overall Fire Protection Program Functioning Well ML20199F5101998-12-29029 December 1998 Discusses Third 10-year Interval ISI Program Plan & Associated Relief Requests for BVPS-1 Submitted by Dlc on 970917 & 980618.Informs That NRC Has Adopted Ineel Recommendations in TER INEEL-98-00893.Forwards SE & TER ML20198K5911998-12-24024 December 1998 Forwards Emergency Response Data Sys Implementation Documents Which Include Data Point Library Updates for Fermi (Number 268),Peach Bottom (Number 269) & Beaver Valley (Number 270).Without Encls ML20198K8251998-12-21021 December 1998 Forwards SER Granting Licensee 980611,as Suppl 981015 Pump Relief Request PRR-5 for Third 10-year IST Interval for Beaver Valley Power Station,Unit 1 Pursuant 10CFR50.55(a)(f)(6)(i) ML20198B1301998-12-0909 December 1998 Advises of Planned Insp Effort Resulting from Beaver Valley Power Station mid-year Insp Resource Planning Meeting Held on 981110.Historical Listing of Plant Issues & Details of Insp Plan for Next 6 Months Encl ML20198A1301998-12-0909 December 1998 Forwards SE Re USI A-46 Program Implentation for Plant Unit 1.Staff Concludes Program Implementation Met Purpose & Intent of Criteria in Generic Implementation Procedure 2 & Suppl SER 2 for Resolution of USI A-46 ML20196J2761998-12-0404 December 1998 Forwards Corrected Pages 17 & 18 of NRC Integrated Insp Repts 50-334/98-06 & 50-412/98-06 for Exercise of Enforcement Discretion ML20196H3051998-12-0202 December 1998 Forwards Insp Repts 50-334/98-06 & 50-412/98-06 on 981004-1114.No Violations Noted.Conduct of Activities at Beaver Valley Power Station Facilities Characterized by Safe Plant Operations ML20196H2781998-12-0202 December 1998 Forwards Insp Repts 50-334/98-08 & 50-412/98-08 on 981026- 30.No Violations Noted.Plant Operations Witnessed by Team Were Conducted in Safe & Controlled Manner ML20196G9921998-12-0101 December 1998 Forwards Ltrs from Fk Koob, to JW Pack & CF Wynne Re Plant Deficiencies Assessed During 981006 Exercise Against Hancock County,Wv & Beaver County,Pa,Respectively ML20196D4371998-11-25025 November 1998 Discusses Concerns Re Announced Asset Transfer Between Firstenergy Corp & Duquesne Light Co ML20196A7101998-11-24024 November 1998 Forwards Notice of Withdrawal of Amend to License NPF-73. Proposed Change Would Have Extended on one-time Only Basis, Surveillance Interval for TSs 4.8.1.1.1.b & 4.8.1.2 Until First Entry Into Mode 4 Following Seventh Refueling Outage ML20195K3331998-11-18018 November 1998 Informs That Effective 981214,DS Collins Will Become Project Manager for Beaver Valley Power Station,Units 1 & 2 IR 05000334/19980041998-11-13013 November 1998 Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Repts 50-334/98-04 & 50-412/98-04 Issued on 980915.C/As Will Be Examined During Future Insp of Licensed Program ML20195J2941998-11-12012 November 1998 Forwards Safety Evaluation Re First & Second 10-year Interval Inservice Insp Request for Relief ML20155K4041998-11-0505 November 1998 Forwards Insp Repts 50-334/98-07 & 50-412/98-07 on 981006- 07.No Violations Noted.Overall Performance of Emergency Response Organization Was Good 1999-09-08
[Table view] |
See also: IR 05000334/1997008
Text
,
.
.
.
February 18, 1998
EA No.: 98 045
Mr. J. E. Cross
President
Generation Group
. Duquesne Light Company i
Post Office Box 4 j
Shippingport, Pennsylvania 15077
J8 JECT: NRC INTEGRATED INSPECTION REPORT 50 334/97 08,50 412/97 08
NOTICE OF VIOLATION l
Dear Mr. Cross: l
!
The NRC has received your response dated January 9,1998, to NRC inspection report !
Nos. 50 334/97 08and 50 412/97 08. Concerning violation A, thank you for informing us I
of the corrective ** d preventive actions documented in your letter. These actions will be ;
examined during a future inspection of your licensed program. :
,
in your response you requested that the NRC withdraw violation B contained in the report j
-(item 50 334/97 08-05). After careful review of your submittel, we have concluded that l
_ your rationale and basis is inadequate to support withdrawing the violation for the ;
following reasons: ;
(1) Your response stated, in part, that, *the method used for calibration of the Victoreen
(vendor) RMS follows vendor recommendations for performing periodic electronic
and radiation calibrations..." As indicated in Section R2.1 of our inspection report, t
t. the vendor instruction manual specifications for operating voltage specified an
'
operating voltage range between 500 and 1400 volts. Contrary to this _
.
specification, your organization established the operating voltage for the RM 1LW- !
104 (Unit 1 liquid waste effluent: Victoreen detector type 843 30) at 450 volts. ;
(2)- Your response stated that ANSI N42.18 neither directs nor implies that the -
operating high voltage be set on a plateau. We disagree. Such a position is ,
contrary to well established industry practices and fundamentals for radiation
detection instrument calibration. The commonly accepted industry guidance ANSI .
N42.18, Section 5.4.7.5 specifies the expected condition that operating voltage be !
'
established such that a 15% variation in opeisting voltage not cause more than a
5% variation in detection capability. Your own calibration records (Attachments 1
and 2) clearly demonstrate that the esteblishment of operating voltage at 450 and
650 volts for the RM 1LW 104 and the RM 1RM 215A monitors, respectively,
permits a 15% variation in operating voltage to affect detection capability
- significantly, i.e., well beyond'a 5% variation.
_. ,
m==a m mPDR m Il ll Il Ill.Il II M V, .
e .
>
>
'0FFICIAl. RECORD COPY IE:01
__emee-m+m
' _mww+p-
i
!
l
i,
I
.
,
Mr. J. E. Cross 2 1
j
t
(3) Your ratior. ale to establish a different method does not 3ppear well conceived. You
stated that, "the primary disadvantages of using the detectorplateau method for ;
- determining the photomultiplier tube operating high voltage is that the sensitivity of ;
each detector willbe different and the same detector inay have a different
~
'
j sensitivity after each calibration. This would result in recalculating detector
sensitivity after each calibration which could directly affect monitor alarm setpoints
i andinputs to telease calculations. " These f actors, v.hich you cite as ;
j ' disadvantages,' provide the bas:s of why it is imperative to effectively establish
operating voltage r d determine individual detector sensitivity. Variations due to
aging and environmental conditions are expected over the operating life of the i
detector and other Instrument components. Accordingly, the principal purpose of
'
secondary calibration is to validate the detector efficiency obtained during primary
calibration. Section 1.1.1 of your ODCM, describes the setpoint determination
4 method for Unit 1 effluent RMS. The ODCM requires that detector efficiency
- (cpml Cilml) be used to calculate alarm and high high alarm setpoints. However,
. by your methodology, detector efficiency would not be maintained in a acceptable
l range with any variation in operating high voltage.
l
'
From our review, it is evident that your calibration methodology did not establish the
! operating voltago for these instruments in conformance with commonly accepted industry
i standards; and you provided no new information in support of the recognition or
l acceptability of any other calibration technique. This finding continues to constitute a
failure to establish inadequate procedures for calibration of radiation monitoring systems.
- Accordingly, we find no basis to withdraw the violation, as originally cited. You are
i
required to respond to the violation, within 30 days of the date of this letter, in accordance
,
with instructions previously provided. in your ret ponse, please confirm that 1RM 215A
5
and RM 1LW 104 are in conformance with the detector efficiencies listed in vour ODCM,
! Table 1.1 la.
4
Sincerely,
! Original Signed by:
i Charles W. Hehl, Director
Division of Reactor Projects
Docket Nos. 50 334;50 412
i
- _ . _ _ _ _ _ _ . _ _ - _ . _ _ _ . , _ _ . _ . _ . - . _ . _ _ ~ ~ . . _ . ~ _ _ _ . _ _ _ . . . _ _ _ . _ _ . _ _ . _ , _ _ _ . _ . , _ . . _ _ _ . . . _ _ . _ . _ _ ,
- - . - . . ... - .-. -_ . . - . . - . - . - ..- -.-._.-.- .. - --_ . -. .
. . ;
i
i
i k
,
Mr. J. E. Cross 3 l
l
~
cc w/ encl: ;
~ Sushil C. Jain, Vice President, Nuclear Services i
R. LeGrand, Division Vice President, Nuclear Operations Group & Plant Manager j
- W. Kline, Manager, Nuclear Engineering Department l
B. Tulte, General Manager, Nuclear Operations Unit i
M. Perger, Acting Manager, Quality Services Unit !
J. Arias, Director, Safety & Licensing Department i
J. MacDonald, Manager, System and Performance Engineering l
t
cc w\cy of Licensee's Response:
M. Clancy, Mayor !
.
Commonwealth of Pennsylvania ,
State of Ohio
State of West Virginia
i
i
>
l
,
t
t
.
t
F
L
b
4
>
& e v---%--- -~ - ,
r ^,mm-r- +-y+-'a -
= **'-g ery e afv x-
_ . _ _ . . _ _. . . _ . __ ___. _ . _ _ _ . . _ _ _ . .
i
Mr. J. E. Cross 4
'
DJaidbutlort w/cy of Licensee Response:
Region 1 Docket Room (with concurrences) ,
'
'
PUBLIC '
Nuclear Safety information Center (NSIC)
NRC Resident inspector
H. Miller, RA/W. Axelson, DRA
N. Perry, DRP
D. Haverhamp, DRP
'
A. Linde, DRP i
J. Stolz, PDI 2, NRR :
D. Brinkman, PM, PDl 2, NRR !
J. Lieberman, OE
T. Walker, ORA
B. McCabe, OEDO
R. Correia, NRR
F. Talbot, NRR
DOCDESK
inspection Program Branch, NRR (IPAS)
,
.
DOCUMENT NAME: G:\ BRANCH 7\BV9708. REP
T) resolve e copy of this document. Indicate in the box: *C" = Copy without ettschment/ enclosure 'E' = Copy with attachment / enclosure *8fa = No
00PY 4 ,
OFFICE Rl/DRP 1 R 1fML I Rl/ORyJd l Rl/ $P , I I I
E NPerry #M /
'
J@lle'~ DHolodf/ - CHsW # #
DATE Mtit/.9Br/n/rr 02/ I /98 02/ G /98 02/ /f'/98 02/ /98
0FFICIAL RECORD COPY
. .- - . - --_ -- - - - .. __
1
l .
'
"
ATTACHMENT I
'
l DUQUESNE LIGHT COMPANY RTL # A9.655J
Beaver VP.!Iey Power Station HP Form 4.5.11.1
,
12/1994
'
i
COUNTER CAllBRATION RECORD-Plateau Plot Data
'
i ,
I SOURCE DATA INSTRUMENT DATA COUNTING DATA !
Isotope: Ba-133 Type: ( M-LW-10d/ Counted By:_
Radiation Type: Gamma Sorial No.: N/A Badge #: 4.L Zr Dkte: I 25 V 7
- Accountability Probe Type
- 843-30 Count Time: /u.
Number: 442 Serial No.: 200 Plateau Determination
Plateau Check
<
1
Grosa cpm Not cpm % CHANGE i
Voltage Bkg opm
'
400 360 97390 97030 XXXXXXXX
'
450 380 220290 225910 132.8
500 380 267606 26,7226 18.3 i
j 550 480 418584 418104 56.5
600 560 422228 421668 0.9
. 650 500 424530 424030 0.6
,
4
e
4
~$ ~
h
a
_
Operating Voltage: __
-
N . ,.. e. . ,. Duni ....; no ..,e.
a,
. - .- - .-- - _-- - . .
_ _. . _ _ _ . . _ _ . _ . _ . _ . - _ _ _ . . . _ _ _ _ . . _ _ _ _ _ _ - . _ . . . . ._ ___.._ ._ ._
, ,*
-
,
. .
t
4
,
DUQUESNE LIGHT COMPANY. RTL # A9.65SJ
1
Beaver Valley Power Station HP Form 4.5.11.2
, l 12/1994
.
COUNTER CAUBRATION RECORD-Plateau Plot Grash ,
)
SOURCE DATA INSTRUMENT DATA COUNTING DATA
l- .. A
4 Isotope: Ba-133 Type: g M-LW-10J Counted By: VW/
, Radiation Type: Gamma Serial No.: N/A Badge #: A#i L @ ate:4 .Ef 't 7
Accountability Probe Type: 843-30 Count Time: / m,J
Number: 442 Serial No.: 200 Gross epm
'
det cpm
I
-
,50
- 0
, p.
-
400
i
350
!-
i
300
f 7
11
aa 250
J
-
200
/
i
4 .
150
,
,
.100 u
50 _
.
- 400 450 500 550 600 650
VOLTAGE
Reviewed By: Badge #: h Date: /23/0 7
.
, ,,m- , - - - - - --m. -
,----m - ..- ....n- w wr. nm, .
r-
_ - _ _ _ _ _ _ _ _ _ _
.
.,'
! ATTACHMENT 2
DUQUESNE LIGHT COMPANY RTL # A9.655J
Beaver Valley Power Station HP Form 4.5.11.1
12/1994
Q.OUNTER CAllBRATION RECORD-Plateau Plot Data
SOURCE DATA' INSTRUMENT DATA COUNTING DATA
Isotope: Cs-137 Type: RM-215A Counted By: A.C_a3(el1:
Radiation Type: Beta Serial No.: ' '
_... Badge #: 2iGL Date: eu-^ .
Accountability Probe Typ6: 843-20A Count Time: / r.d
Number: -
166 Serial No.: N/A Plateau Determination
/ Plateau Check
Voltage Skg epm Gross cpm Net cpm % CHANGE
550 0 114 114 )O000000(
600 0 4304 4304 3675.4
_
650 20 20058 20038 365.6
700 20 35944 35924 79.3
750 20 44846 44826 24.8
800 40 46310 46270 3.2
850 00 47254 47174 2.0
900 220 48516 48296 2.4
Operating Voltage:
'
Reviewed By: N Badge #: /d#f \ Date: C 7[f&
.
-
. .
. -. .- . _ - . . _._ . - . .. . - __ _-
,.e ' ,
'
DUQUESNE LIGHT COMPANY RTL # A9.655J
Beaver Valley Power Station HP Form 4.5.11.2
12/1994
COUNTER CAUBRATION RECORD-Plateau Plot Graoh
SOURCE DATA' INSTRUMENT DATJ COUNTING DATA
isotope: Cs-137 Type: RM-215A Counted By: d , (1, k I (1
Radiation Type: Beta Serial No.: N/A Badge #: 1I6 B Date: ' tu % *
Accountability Probe Type: -843-20A Count Time: le
Number: 166 Serial No.: N/A Gross cpm
/ et
N epm
60
50
H
40
--
2u
$! t
3
D
'
20 ,
10
,
0 -
550 600 650 700 750 800 850 900
VOLTAGE
Reviewed By: Badge #: [29 \ Date: 0 Y 94
.-
4
.e ,' e **
- Be er V.fley Power St. tion
$nippingport. P A 15077 0004
RONALD L LeGR AND (412) 39NE22
2."Se*,."l"'.'*."n'a'ei.niu.n.., Januay 9. WM **"*
L-98-003
U. S. Nuclear Regulatory Commission
Attention: Document Control Desk
Washington, DC 20555-0001
Subject: Beaver Valley Power Station, Unit No. I and No. 2
BV-1 Docket No. 50-334, License No. DPR-66
HV-2 Docket No. 50-412, License No. NPF-73
Integrated Inspection Report 50-334/97-08 and 50-412/97-08
Reply to Notice of Violation
In response to NRC correspondence dated Novemoer 26,1997, and in accordance
with 10 CFR 2.201, the attached reply addresses the Notice of Violation transmitted with
the subject inspection report. An extension of the due date of the response until
January 9,1998, was requested of the NRC staff on December 24,1997.
Duquesne Light has performed a detailed review of the circumstances surrounding
alleged Violation B. Based on the details provided in the attached response to this
violation, Duquesne Light respectfully requests that this violation be withdrawn.
If there are any questions concerning this response, please contact Mr. J. Arias at
(412) 393-5203.
Sincerely,
{ .,a//,/,' w/ ,ofi
,{~
i
Ronald L. LeGrand !
Attachment
c: Mr. D. S. Brinkman, Sr. Project Manager
Mr. P. W. Eselgroth, Chief, Reactor Projects Branch No. 7, Region I l
Mr. D. M. Kern, Sr. Resident Inspector j
AhMMihn:NRG Region 1 Administrator y
,h G m_
I
[. ,wd h,_
. _
,
_ b) .
.
,g, ".
.
.
DUQUESNE LIGHT COMPANY
Neclear Power Division
Beaver Valley Power Station, Unit Nos. I and 2
Reniv to Notice of Violation
Integrated Inspection Report 50-334/97-08 and 50-412/97-08
Letter Dated November 26,1997
VIOLATION A (Severity Level IV, Supplement IV)
Description of Violation (50-334/97 08-04)
Unit 1 Technical Specification (TS) 6.8.1.a requires that, " Written procedures shall be
established, implemented, and maintained covering...the applicable procedures
recommended in Appendix "A" of Regulatory Guide 1.33, Revision 2, February 1978,"
which includes radiation protection procedures. This requirement is partially
implemented by the site Health Physics Manual, which requires in Chapter 1, Part II,
Section E.2.g, that individuals shall comply with the provisions of their radiological work
permit (RWP) and any supplementary posted material for work in the radiologically
controlled area (RCA). Alllicensee RWPs require the user to review the radiological
conditions of their work area by reviewing the posted area survey maps.
Contrary to the above, workers were fotr during the period of October 6-8,1997, in the
radiologically controlled areas (prima;y auxiliary and containment buildings), who had
not reviewed their survey maps prior to entry and were unaware of the radiological
conditions in their work and travel areas in the RCA.
Reason for the Violation
The primary cause of the violation is that management did not develop and communicate
adequate standards to ensure compliance. A review of site procedures determined that
there was a lack of specific guidance to be provided to workers regarding requirements
for knowledge of radiological conditions in low dose rate travel areas. A secondary cause
was that workers were complacent or had a lack of concern about their dose and the dose
rates in low dose rate areas. This is partially attributed to the lack of adequate standards.
l
_
i
_ - - _ - . - . .- -.--. . - . - - - - - - - -- . - - -
', .
+
m,.. m
j/ Reply to Notice of Violation
.
NRC Integrated Inspection 50-334/97-08 and 50-412/97-08
Page 2
l l
l Corrective Actions Taken and the Results Achieved
l
'
The following were immediate corrective actions, some of which are interim and will be
'
discontinued when other corrective actions are completed that will provide a similar level
of compliance. These actions ensured workers were aware of the radiological conditions
[ in their work and travel areas.
- Developed and issued a Standard of the Week for two consecutive weeks that
. included the expectation that workers are responsible to be knowledgeable of the
,
radiological conditions of their work and travel areas. ,
-* Instituted interim direct verbal worker briefings at strategic Radiologically Controlled
'
Area (RCA) entry points. These briefings informed workers of the radiological
conditions in their work and travel areas and included the location of any applicable
ALARA low dose waiting areas.
'
- Com.aunicated details of the deficiency and the revised interim controls to station
L managers and requested they achieve compliance from all individuals under their
cognizance.
- Added a supplement to radiation worker training that included management
expectations that workers are responsible to be knowledgeable of the radiological
'
conditions in their work and travel paths.
.
The following corrective actions were taken in addition to the immediate corrective
actions listed above:
- Revised the responsibilitu for Health Physics updating of posted survey maps to
ensure more timely and efficient updating.
- Upgraded and simp}ified the posted survey maps at the entrances to RCAs to make
them easier for the worker to read and understand.
- . Issued a letter to Health Physics personnel describing the c'orrective actions taken and
.
those planned to be taken to address the deficiency.
- ' Issued a letter from the Plant Manager to station radiation workers reinforcing
management expectations of worker responsibilities with regard to their knowledge of
radiological conditions in their work and travel areas.
l
l.
'
. .
3
.. _ .. -_ _ _ __ _ _ _ .- _ _ ._... . . _ . ._ . ._ _ _ . .
'
.
, ; .
- ,
- Reply to Notice of Violation
NRC Integrated Inspection 50-334/97-08 and 50-412/97-08
- Page 3
- Corrective Actions to Prevent Further Violations ;
- The following additional corrective actions will be implemented:
- Incorporate additional management expectations for worker knowledge of radiological
! conditions in their work and travel areas into radiation worker training. This will be -
- completed by January 31,1998.
.
- Revise Health Physics Manual (HPM) procedures to describe the methods to be
followed to ensure timely posting and updating of survey maps. The HPM will also
be revised to describe the requirements for the workers to familiarize themselves with ;
the radiological conditions in their work and travel areas. These will be completed by
February 28,1998.
Provide workers retuming for the next refueling outage (2R07), that are not required
) *
to receive radiation worker requalification training, information about management
,
--
expectations regarding worker knowledge of radiological conditions in their work and
'
travel areas. This will be completed by the start date for 2R07.
- Conduct e.n effectiveness review of the corrective actions throughout the first half of
1998, inclusive of 2R07 completion. This will be completed by June 30,1998.
Date When Full Comoliance Was Achieved
. ..
J
With the institution of the direct verbal worker briefimgs at strategic RCA enny points,
full compliance was achieved.
,
<
d
-
I
'
- I ~=-- - . . - . - . , ., ., n,7 y, ,, , _,. ._ , _ _
-- .. - - - -. ---- ---------
i_
- d.
q
,' Reply to Notice of Violation
I
l
-NRC Integrated Inspection 50-334/97-08 and 50-412/97-08
, Page 4
4
i
'
VIOLATION B (Severity Level IV, Supplement IV)
i
Descriotion of Violation (50-334/97-08-05)
>
Unit' l Technical Specification (TS) 6,8.'t.a requires that, " Written procedures be
- established, implemented and maintained covering...the applicable procedures ,
recommended in Appendix "A" of Regulatory Guide 1.33, Revision 2, February 1978,"
which includes procedures for radiation monitoring system (RMS) operation.
Contrary to the above, the licensee failed to establish adequate RMS calibration
- instructions in regard to determining RMS operating high voltage. Specifically, operating l
high voltage was not established on a plateau for RM-lRM-215A (Unit 1 Containment
'
,
Particulate) and RM-ILW-104 (Unit 1 Liquid Waste Effluent). This was contrary to ;
vendor manual "Victorcen Installation, Operation, and Maintenance, lastruction Manual
Beta Scintillation Detectors Models 843-20,843-20A, and 843-20B" and "Victorcen
! Instructional Manual Gamma Scintillation Detector Model 843-30" respectively; and was ,
contrary to RMS calibration standards and industry guidance documents.
4
Discussion of the Allened Violation
Duquesne Light Company (DLC) has evaluated the alleged violation and the related
'
discussion in NRC Inspection Report 50-334/97-08 & 50-412/97-08 and does not concur
with the violation. The method used for calibration of the Victoreen (vendor) Radiation
Monitoring System (RMS) follows vendor recommendations for performing periodic
electronic and radiation calibrations of the monitors, and utilizes approved site specific
Maintenance Surveillance Procedures and Health Physics Manual procedures. These
procedures use a calibration method described in the vendor's system manual which was
provided with the purchase of the Beaver Valley Power Station (BVPS) Unit 1 Radiation
- Monitoring System (RMS). The site calibration procedures have incorporated vendor . '
improvements in the method for maintaining source geometry during calibration of the
units since the initial issue of vendor's system manual. DLC has obtained written
confirmation from the vendor that use of the calibration method provided with the system
manual including the use of the standard geometry fixture is correct.
With regard to the specific vendor manuals cited in the _ violation (Victoreen Installation, ,
Operation, and Maintenance, Instruction Manual Beta Scintillation Detectors Models
- 843-20, 843-20A, and 843-20B and Victorcen Instructional Manual Camma Scintillation
Detector Model 843-30), DLC has obtained written confirmation trc.n the vendor that the
- manuals are intended for general use, where detector is typically used for detection of a -
single isotope.1This is not the case for a process radiation monitor, where the detection
. _ . _ . _ _ _ _ - . _ __ _ . _ _. _ _ ____ _ _._ _ .
s
3 R.
4
[ Reply to Notice of Violation
NRC Integrated Inspection '0-334/97-08 and 50-412/97-08
-Page5
.
'
and measurement ofisotopes with characteristic decay energies from 80 Kev to 3 Mev '
.
are required. This is the detecticn range for the BVPS Unit 1 RMS.
.
The violation refers to "RMS calibration standards," which apparently refers to the
inspection report reference to ANSI N42.18. DLC has reviewed this document and
concludes that this standard neither directs nor implies that the operating high voltage be -
set on a plateau. Specifically, DLC has concluded that ANSI N42.18, Section 5.4.7.5,
" Power Requirements" under Standards of Performance, is intended to address the effects
l
- on instrument accuracy ofline voltage and frequency variations; not operating high
i. voltage variations. Also, this section appears to be directly related to a previous section
- in the standard under Specification of Performance,5.3.2.4.2, Power Variations, which a
addresses line voltage.
l The violation also refers to " industry guidance documents," which apparently refers to
l the discussion of EPRI TR-102644 in the inspection report. DLC perfonned a search of
i applicable regulations and NRC guidance documents and could not locate any NRC
endorsement of this document. Likewise, DLC has not endorsed this document in its
RMS calibration pro:,edures.
! In addition, an independent third party evaluation of the alleged violation was performed
at the request of DLC. This evaluation assessed the calibration methodology used at
'
BVPS and concluded that the specific count rate method of calibration is acceptable and
,
that setting the voltage on a plateau for scintillation detectors using photomultiplier tubes
,
is unnecessary,
in conclusion, RMS calibrations are performed in accordance with vendor
recommendations and technical documentation, and applicable regulations using
approved site specific procedures. Based on the above discussion, DLC respectfully
,
requests that the violation be withdrawn.
Discussion of Radiation Monitor System Calibration Method
~ DLC performed a detailed review of the methods used for calibrating the BVPS radiation
.
monitoring systems in an effort to ensure that the current practice used at BVPS is
! correct. The following discussion summarizes this review is being provided as additicaal
information.
The process and effluent RMS is calibrated to measure the concentration of radioactive
'
isotopes over a wide energy range (80 Kev to 3 Mev). Calibration methods developed .
and recommended by the vendor and used at BVPS standardizes the response of the RMS
E . scintillation detectors in a manner that provides traceability to the original detection
geometry primary isotopic calibration. The method used, as described by the vendor, is
_
called the " Specific Count Rate Method"(SCRM). The vendor acknowledges that there
,
-
s--,, .,. --- , * .- -- , ,*
.. ..
f
,
3
, 3 ".
>
/ '
Reply to Notice of Violation ,
' NRC Integrated Inspection 50-334/97 08 and 50-412/97 08
Page 6
'
are two additional methods that can be employed to establish a phot'omultiplier tube
(PMT) operating point for scintillation detectors, " Detector Plateau Method" and
" Specific Pulse Height Method."- However, the vendor did not and does not recommend
the use of either of these methods for the calibration of the BVPS Unit 1 RMS.
The SCRM recommended by the vendor requires setting the low discriminator to a
standardized value ' The detector is then placed in a specific geometry and exposed to a
reference transfer source traceable to the primary calibration. The PMT high voltage is
then varied until a specific count rate is produced from the detector. Additional sources
of different energies are then used to verify the energy response linearity and the source
strength linearity of the detector. This method is similar to the " Detector Plateau .
>
'
Method," but with the added feature of using a specific count rate to select the operating
high voltage and eliminating the ambiguity associated with selecting an operating high
voltage from a plateau. The primary benefit of using the SCRM is that all detectors in the
same geometry will have the same gain, or sensitivity and "as-found" and "as-left"
analysis may be performed as part of the calibration, to demonstrate the detector was
operating properly since the last calibration.
The primary disadvantages of using the " Detector Plateau Method" for determining the
PMT operating high voltage is that the sensitivity of each detector will be different and ,
the same detector may have a different sensitivity after each calibration. This would
result in recalculating detector sensitivity after each calibration which could directly
- affect monitor alarm setpoints and inputs to release calculations. Setting the operating
- high voltage on a plateau would minimize count rate changes due to voltage drift or PMT
'
gain changes above or below the selected operating high voltage. However, for a non-
,
monenergetic application (gross activity detection), such as that desired in a nuclear
power plant, selection of an operating high voltage based on a plateau would not ensure
the low energy response of the system.
As noted in the inspection report, a small change in operating high voltage could result in
j a significant change in output count rate. However, in consultation with the vendor, any
l such changes would be readily apparent in the nominal monitor readings. Also, as noted
-
in the inspection repon, performance of the BVPS Unit 1 RMS with respect to high
- voltage based on "as-found" and "as-left" data indicate that the high voltage power
supplies are highly stable and that typically there is little if any high voltage drift.
'
In summary, during factory primary calibrations, the vendor did not and does not attempt
to find a plateau and does not select PMTs to obtain specific response characteristics.
,
. Because of the variables involved in calibrating scintillation detectors to operate over a
_.
. wide energy range, selection of an operating high voltage using the " Specific Count Rate
.
.
Method" permits not utilizing generation and use of plateau data.
[1
l
. - . . . - - - - - - - -- - - -