[1 % UNITED STATES g ,g NUCLEAR REGULATORY COMMISSION o '* WASHINGTON. D.C. 20%M001
%....,/ February 12, 1998 DOCKET NO: 70-754 LICENSEE: General Electric Co. (GE Val)
Pleasanton, California
SUBJECT:
SAFETY EVALUATION REPORT: APPLICATION DATED JUNE 4,1997 - UPDATE ORGANIZATIONAL CHANGES AND RESUMES, CORRECT TYPOGRAPHICAL ERRORS BACKGROUND in correspondence dated June 4,1997, General Electric Co. - Vallecitos Nuclear Centor (GE-Val) requeted its license be amended to correct typographical errors in environmental action levels, update corporate organizational changes, and update the licensing organization chart and personnel resumes.
DISCUSSION The organizational changes are necessary because of the retirement of the previous licensing project officer and a basic reorganization within the licensing staff at the Center, in addition, GE-Val now has become the cognizant o ganization for the Morria !Ilinois, spent fuel storage facility. Accordingly the Irradiation Processing Operations is new anamed as Vallecitos and Morris Operations (V&MO). In addition, new resumes have been added fo, the new licensing project manager and associated lictnsing organization personnel changes. These organization and management changes were discussed in the RIV Inspection Report 70-754/97-01 dated April 16,1997, which also verified that the new personnel met the qualifications specified in the license application.
In the area of typographlca; errors, GE-Val has corrected the units from pCi/gm tc pCi/gm fer Cs-137 in the stream bottom and for gross alpha and gross beta vegetation action levels. The environmental action levels were discussed in the RIV Inspection Report 70-754/96-02 dated December 2,1999. The updated paragrapn 1.5.11 indicates the closing, but rot ,
decommissicning, of Building 300 (Building 300 is licensed by the State of Califomia).
Organizational component descriptions were rearranged and renumbered. The licensee added a reference to the Region IV Walnut Creek Field Office. The ventilation air throughput has been updated from " max.18,500 cim' to " nominal 27,000 cfm." Units were added to discharge levels of liquid water waste (excluding seqitary waste) for gross alpha and gross beta-gamma (uCl/ml).
ENVIRONMENTAL REVIEW Based on the information subtr.itted by GE-VAL, these changes are considered administrative and organizatiotialin nature. The staff has determined that !5e proposed changes do not adversely affect the public health and safety or the environme 't and are categorically excluded from the requirements to perform a site-specific environmental assessment. Therefore, in 9802250006 980212 PDR ADOCK 07000754 C PDfi l
i
\
- 2 accordance with 10 CFR 51.22(c)(11) neither an environmeldal assessment nor an environmental impact statement is warranted for.this action.
CONCLUSION 4
~ The staff concludes that GE-Val's request to amend their iisanse to include the administrative
. changes meets regulatory requirements and constitutes no impact upon the health and safety
! of the pubne t.nd the common defense and security, t
.' - The Region IV Principal Inspector has no objection to the proposed actions.