ML20199L382
| ML20199L382 | |
| Person / Time | |
|---|---|
| Site: | Clinton |
| Issue date: | 01/20/1999 |
| From: | Hopkins J Office of Nuclear Reactor Regulation |
| To: | |
| Shared Package | |
| ML20199L384 | List: |
| References | |
| NPF-62-A-119 NUDOCS 9901270215 | |
| Download: ML20199L382 (2) | |
Text
_. -
,p y p
t UNITED STATES s
j NUCLEAR REGULATORY COMMISSION 2
WASMINGToN, D.C. 30665 4001
\\...../
ILLINOIS POWER COMPANY DOCKET NO. 50-461 CLINTON POWER STATION. UNIT 1 AMENDMENT TO FACILIT( OPERATING LICENSE Amendment No.119 License No. NPF-62 1.
The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by lilinois Power Company (the licensee), dated August 24,1998, as supplemented November 20,1998, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter l-B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
2.
Accordingly, by Amendment No.119, the license is amended to authorize revision of the Updated Safety Analysis Report (USAR) as set forth in the application for amendment by lilinois Power dated August 24,1998, as supplemented by letter dated November 20, 1998. Illinois Power shall update the USAR to reflect the revised description authorized by this amendment in accordance with 10 CFR 50.71(e).
l 9901270215 990120 PDR ADOCK 05000461 P
PDR l
l l
1
- o 1
< 3.
This license amendment is effective as of its date of issuance and shall be implemented within 45 days of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION
/
o J
Jon B. Hopkins, Senior Proj ct Manager Project Directorate 111-2 Division of Reactor Projects Ill/IV Office of Nuclear Reactor Regulation i
Date of issuance: January 20, 1999
.v,
-