Application for Amend to License NPF-49,by Incorporating Attached Proposed Rev Into TS 3/4.2.2, Heat Flux Hot Channel Factor-FQ(Z), 6.9.1.6.a & 6.9.1.6.b, Colr
ML20199L063
Person / Time
Site: Millstone Dominion icon.png
Issue date: 01/18/1999
From: Bowling M
NORTHEAST NUCLEAR ENERGY CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20199L067 List:
References
NUDOCS 9901270117
Download: ML20199L063 (5)


Text

- - . . - . . ~ . - - .. -. - -.- - - - . - - ..- --. - - _ - - - - .

gbg Rope Ferry Rd. (Route 156), Tcterford, CT 06385 j Nuclear Energy ~ >

mu. tone Nudear Power Stadon i

' * ~

Northeast Nudear Energy company P.o. Box 128 Waterford, CI 06385-0128 i

  • V *.

(860) 447-1791 q Fax (860) 444-4277 The Northeast Utdmes System  ;

I

JAN l 81999  !

7 Docket No. 50-423 l B17609 j i

Re:10CFR50.90 U' . S. Nuclear Regulatory Commission l

' Attention: Document Control Desk j

. Washington, DC 20555 1 Millstone Nuclear Power Station, Unit No. 3  !

Proposed Revision to Technical Specification l Heat Flux Hot Channel Factor-Fo(Z) and Core Operatina Limit Report (COLR) Modifications (TSCR 3-27-98) .,

Pursuant to 10CFR50.90, Northeast Nuclear Energy Company (NNECO) hereby L . proposes to amend Operating License NPF-49 by incorporating the attached proposed i

' revision into Millstone Unit No.- 3 Technical Specifications 3/4.2.2 " Heat Flux Hot  !

Channel Factor-Fo(Z)" and 6.9.1.6.a and 6.9.l.6.b " Core Operating Limit Report" .

(COLR).

Description of Proposed Revision i

- This proposed Technical Specification (TS) change affects sections 3/4.2.2 and related

BASES, in addition to the COLR as presented in section 6.9.1.6. This change is comprised of'several unrelated issues which have been grouped together for L convenience since they modify similar sections of the TS's. The change to TS 3/4.2.2 ,

modifies this TS to be in accordance with NRC approved Westinghouse methodologies for the Heat Flux Hot Channel Factor-Fo(Z). This change represents the only technical _ '

change to' the TS's conveyed by this letter. The balance of the changes affect TS \

section 6.9.1.6 and are administrative in nature. These administrative changes are not c related to 'each other, nor are they related to the Heat Flux Hot Channel Factor change.

l a

, . 4 ."\ 1 --

990127011'T 990118 PDR ADOCK 0S000423.

PDR2 ;

p

,. 0S3422 5 MIT.1245.

!.  : L 1 - - . , . .,.n n , , , ,, , , , - - . -

- . . . -. . . - - _ - - =. _ - . - ._. - - - - - -

U.S. Nuclear Regulatory Commission B17609\Page 2 Furthermore it is noted that this submittal satisfies a NNECO License Condition to ,

incorporatp. into TS 6.9.1.6 references to the shutdown margin analysis methods which l

have been reviewed and approved by the NRC [1].

Markuo of Proposed Revision A copy of the marked up Technical Specificat'on pages is contained in Attachment 1.

The markup reflects the currently issued version of the Technical Specifications.

Pending Technical Specification revisions or Technical Specification revisions issued subsequent to this submittal are not reflected in the enclosed markup. ,

Retvoe of Proposed Revision  !

I 1

i A copy of the retyped Technical Specification pages are contained in Attachment 2. l The retyped pages reflect the currently issued version of the Technical Specification.

Pending Technical Specification revisions or Technical Specification revisions issued subsequent to this submittal are not reflected in the enclosed retype. The enclosed '

retype should be checked for continuity with Technical Specifications prior to issuance.

Backaround. Safety Summarv. Sianificant Hazards Consideration and Environmental Considerations Background, Safety Summary, Significant Hazards Consideration and Environmental Considerations that support this proposed revision are contained in Attachments l 3 and 4.

Plant Operations Review Committee and Nuclear Safety Assessment Board Review Plant Operations Review Committee and Nuclear Safety Assessment Board have  ;

reviewed this proposed License Amendment change and concur with the conclusions I presented in the rationale for the proposed change relative to safety.

i State Notification  !

in accordance with 10CFR50.91(b), we are providing the state of Connecticut with a copy of this proposed amendment to ensure their awareness of this request.

I I i j {1] Letter from James W. Anderson U.S. Nuclear Regulatory Commission, to {

Martin L. Bowling, Jr., NNECO " Issuance of Amendment-Millstone Nuclear Power Station, Unit No. 3 (TAC NO. M98699)" dated October 21,1998.

l S

U.S. Nuclear R:gulatory Commission B17609\Pcg3 3

, 8 Schedule Reauest for NRC Acoroval NNECO requests NRC review and approval of this proposed revision, and that the license amendment be effective upon issuance. There are no regulatory commitments contained within this letter.

If the NRC Staff should have any questions or comments regarding this submittal, please contact Mr. David Dodson at (860) 447-1791 extension 2346.

Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY Me4 Martin L. Bowling, Jr. /

Recovery Officer-Technical Services Subscribed and sworn to before me this /f4 day of6&W#f 1999 e~

L pFt4f.6668$gg Date Commission Expires:e_ m EU PUBLIC: .

___ ....,w.ppgpuvt:qibt@W@g Attachments: 1) Marked Up Pages

2) Rehped Pages 1
3) Background and Safety Summary
4) Significant Hazards Consideration and Environmental Considerations cc: H. J. Miller, Region I Administrator J. W. Anderson, NRC Project Manager, Millstone Unit No. 3 A.C. Cerne, Senior Resident Inspector, Millstone Unit No. 3 '

E.V. Imbro, Director, ICAVP inspections 1

Director '

Bureau of Air Management Monitoring and Radiation Division Department of environmental Protection l 79 Elm Street l Hartford, CT 06106-5127 IMM:im i

(

l l

1 i Docket No. 50-423 i

, ., B17609 l

,, z.

l~

l r

i l i i

!. Attachment 1 l.

i Millstone Nuclear Power Station, Unit No. 3 l

. Proposed Revision to Technical Specification l Heat Flux Hot Channel Factor and

j. Core Operating Limit Report (COLR) Modifications (TSCR 3-27-98) l l

Marked Up Pages i

l 1

i

[ i a

i l

l l

]

January 1999 l-l l.

i U.S. Nucle:r R gulatory Commission

, B17609\ Attachment 1\Page 1 MARKUP OF PROPOSED REVISION l

)

Refer to the attached markup of the proposed revision to the Technical Specifications.

The attached markup reflects the currently issued version of the Technical Specifications listed below. Pending Technical Specification revisions issued I subsequent to this submittal are not reflected in the enclosed markup.

1 l

,