Notice of Nonconformance from Insp on 970210-0513. Nonconformance Noted:Vendor Failed to Verify Adequacy of Anfb Critical Power Correlation & Adequacy of Application to Atrium 10ML20199F117 |
Person / Time |
---|
Issue date: |
10/27/1997 |
---|
From: |
NRC (Affiliation Not Assigned) |
---|
To: |
|
---|
Shared Package |
---|
ML20199F104 |
List: |
---|
References |
---|
REF-QA-99900081 NUDOCS 9711240115 |
Download: ML20199F117 (6) |
|
|
---|
Category:NOTICE OF DEVIATION/NONCONFORMANCE FROM A REGULATORY
MONTHYEARML20212L2771999-10-0404 October 1999 Notice of Nonconformance from Insp on 990816-20. Nonconformance Noted:Inspectors Identified Listed Six Open NCRs Initiated in 1998 & Did Not Include Timely Resolution & Disposition to Completion ML20211N6361999-09-0808 September 1999 Notice of Nonconformance from Insp on 990630-0701. Nonconformance Noted:Licensee Had Not Performed Suitable Qualification Testing of Representative Sample or Performed Analysis to Demonstrate Environ Qualification ML20199L6431999-01-22022 January 1999 Notice of Nonconformance from Insp on 991014-15 & 28-29. Nonconformance Noted:Repair & Replacement Svcs Failed to Perform Adequate Insps at Subcontractor Source to Ensure Conformance with Procurement Documents ML20198A8051998-12-14014 December 1998 Notice of Nonconformance from Insp on 980921-25 & 1116-17. Nonconformance Noted:Inspectors Identified on 980923,that Submerged Arc Welding Flux,Ordered by Purchase Agreement E64876,accepted at Receipt Inspection Dispite Listed Info ML20154Q8581998-10-21021 October 1998 Notice of Nonconformance from Insp on 980908-1002. Nonconformance Noted:Valcor Failed to Prescribe Written Guidance within Procedures & Drawings to Control Application of Dry Film Graphite Lubricant to V70900-65-11 Series ML20236V3601998-07-29029 July 1998 Notice of Nonconformance from Insp on 980615-17. Nonconformance Noted:Westinghouse Had Not Adequately Completed Design Reviews for Serviceability of Remaining Ice Basket Sheet Metal Screws ML20236P4961998-07-13013 July 1998 Notice of Nonconformance from Insp on 980421-23. Nonconformance Noted:By Sept 1997,licensee Had Not Taken Adequate Corrective Actions Re Adequacy of Relaxation of Sizing Equation Criteria for ac-powered Motor Actuators ML20236L1971998-07-0808 July 1998 Notice of Nonconformance from Insp on 980520-22. Nonconformance Noted:Contractually Imposed Requirements of ASME Boiler & Pressure Vessel Code in Nov & Dec of 1996 Did Not Meet ASME Requirements of QW-409.1 ML20248M2591998-06-10010 June 1998 Notice of Nonconformance from Insp on 980114-16 & 0302-06. Nonconformance Noted:In September 1997,licensee Failed to Promptly Identify & Correct Significant Quality Problems W/Certain Program Controls & Process of Vendor ML20197B8011998-03-0404 March 1998 Notice of Deviation from Insp Rept on 980126-28.Deviation Noted:Licensee Did Not Revise Emergency Plan Implementing Procedures & No Rev Were Presented to Reactor Safety Committee for Review & Approval by 970701 ML20199E2561998-01-28028 January 1998 Notice of Nonconformance from Insp on 971117-21. Nonconformance Noted:Insp Team Found That for Listed AP600 Calculations Westinghouse Failed to Perform Adequate Design Review to Establish Acceptability of AP600 Design Analyses ML20008C2531998-01-26026 January 1998 Notice of Nonconformance from Insp on 971117-19 for Westlectric Castings,Inc.Nonconformance/Deviation Noted: Authority & Duties of All Westlectric QA Dept Personnel Not Accurately Delineated in Westlectric QA Manual,Rev K ML20198J5161998-01-0202 January 1998 Notice of Nonconformance from Insp on 971027-31. Nonconformance Noted:Inspectors Identified on 971029 That Five Meter Long Load Thermocouple Was Not Being Inserted from Front End of Furnace During Thermal Treatment SG Tube ML20203E0091997-12-10010 December 1997 Notice of Nonconformance from Insp on 971002-03. Nonconformance Noted:Epd Does Not Include Appropriate Quality Standards in QCP-187 Critical Characteristic Requirement Charts Re Matl Verification Category ML20199F3711997-11-19019 November 1997 Notice of Nonconformance from Insp on 970826-29 & 1030 for Astro Nuclear Dynamics,Inc.Nonconformance Noted:President Was Not Trained for Task of Assuring That Quality of Items Sold Through Brokage Program Conformed to Documents ML20212C8271997-10-28028 October 1997 Notice of Nonconformance from Insp on 970602-05 & 1002. Nonconformance Noted:Licensee Certified Matl Test Rept for Matl Supplied to Centerior Energy Did Not Include Complete Heat Treatment Certification ML20199F1171997-10-27027 October 1997 Notice of Nonconformance from Insp on 970210-0513. Nonconformance Noted:Vendor Failed to Verify Adequacy of Anfb Critical Power Correlation & Adequacy of Application to Atrium 10 ML20211F0311997-09-26026 September 1997 Notice of Nonconformance from Insp on 970819-21. Nonconformance Noted:Nus Did Not Adequately Document Corrective Actions Taken in Response to Identified Occurrences of Inadequate Soldering on Modules Mfg ML20210R8021997-08-29029 August 1997 Notice of Nonconformance from Insp on 970714-18. Nonconformance Noted:Two Lead Auditor Candidates Were Credited Max of Points for 5 Yrs of Work Experience Towards Lead Auditor Qualification W/O Any Objective Evidence ML20151M1211997-08-0606 August 1997 Notice of Nonconformance from Insp on 970616-19. Nonconformance Noted:Licensee Did Not Prescrive Instructions or Procedures to Ensure That Epoxy Not Applied on Insulated Lead Wires of safety-related Pressure Switches ML20149J3161997-07-23023 July 1997 Notice of Nonconformance from Insp on 970514.Nonconformance Noted:On 961108,maint Personnel at Licensee Discovered That Control Wires on Terminals 12 & 13 of Power Shield Trip Unit Were Reversed on Breaker S/N 51817A-107073 ML20149H9671997-07-22022 July 1997 Notice of Nonconformance from Insp on 970304-07,0428 & 0502. Nonconformance Noted:Facility Did Not Document & Disposition Four Test Failures of SCE Batteries IAW 10CFR50,App B Quality Assurance Program in July 1996 ML20148K0901997-05-20020 May 1997 Notice of Nonconformance from Insp on 970310-14. Nonconformance Noted:Ge Did Not Adequately Inform Licensee Design Organizations Implementing Average Power Range monitor-rod Block monitor-TS Mod ML20138J9001997-05-0202 May 1997 Notice of Nonconformance from Insp on 970417.Nonconformance Noted:Appropriate QA Oversight of Design Activities Performed by Initec Not Provided ML20138E3281997-04-29029 April 1997 Notice of Nonconformance from Insp on 970121-24. Nonconformances Noted:Dubose Certified Matl Test Rept for Matl Supplied to San Onofre Did Not Ref or Include Mill Heat Analysis as Identified Attachment ML20141E6211997-03-28028 March 1997 Notice of Nonconformance from Insp on 961118-20 & 970106-09. Nonconformance Noted:Lucent Failed to Ensure That Design Bases Requirements Were Translated Into Instructions for C&D Battery Cell Mfg,Charging & Conditioning Process Controls ML20135E4531997-03-0404 March 1997 Notice of Nonconformance from Insp on 961112-14 & 970128-30. Nonconformance/Deviation Noted:Failure to Ref or Include Mill Heat Analysis as Identified Attachment & Failure to Ref Mill Heat Analysis or Certification for Heat Treatment ML20134K4101997-02-10010 February 1997 Notice of Nonconformance from Insp on 961202-06. Deviation Noted:E&W Did Not Verify Adequacy of Design Pressure Ratings of Four Air Conditioner Units & Commercial Grade Dedication Plans Did Not Address Verification ML17161A0111996-12-17017 December 1996 Notice of Nonconformance from Insp on 960916-18 & 1007-09. Nonconformance Noted:Assembly Line & Mfg Personnel in Several Areas at Facility Unaware of Procedures & Instructions to Control Activities Being Performed ML20135E6121996-12-0404 December 1996 Notice of Nonconformance from Insp on 960909-12 & 1028-31. Nonconformance/Deviation Noted:Facility Failed to Consider Licensee Findings Re commercial-grade Dedication Activities of Subvendor ABB-Electro Mechanics ML20129J7141996-11-0404 November 1996 Notice of Nonconformance from Insp on 960909-12. Nonconformance/Deviation Noted:Document 900181,Rev 10,dtd 931208,specifies That Documented Test Results Approved by Engineering &/Or Qa.Substitution of Engineering Not Allowed ML20147C6541996-10-29029 October 1996 Notice of Nonconformance from Insp on 960923-26. Nonconformance/Deviation Noted:Unqualified Source Matl Approved Vendor List,Ref in Procedure 17375,Rev N/C Not Developed & Not Available for Use ML20128Q8121996-10-16016 October 1996 Notice of Nonconformance from Insp on 960715-18. Nonconformance Noted:Licensee Did Not Establish,Review or Approve Procedures to Control & Ensure Repeatable Results Re Development of safety-related EC Data Screen Techniques ML20128G7861996-09-25025 September 1996 Notice of Nonconformance from Insp on 960709-12. Nonconformance Noted:Licensee Did Not Establish Procedures to Control & Ensure Repeatable Results Re Development of SR EC Computer Data Screening Techniques ML20129A9911996-09-10010 September 1996 Notice of Nonconformance from Insp on 960506-10. Nonconformance Noted:Ge Failed to Recalculate or Reconfirm Applicability of Generically Determined SLMCPR to New Fuel Bundle Designs 1999-09-08
[Table view]Some use of "" in your query was not closed by a matching "". Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000027/19992011999-10-0606 October 1999 Insp Rept 50-027/99-201 on 990817-20.No Violations Noted. Major Areas Inspected:Organizational Structure & Functions Programs ML20212L2831999-10-0404 October 1999 Insp Rept 99901341/99-201 on 990816-20.Non Compliance Noted. Major Areas Inspected:Tva Central Labs & Field Testing Svcs Activities for Calibration of Measuring & Test Equipment & Activities Re Metallurgical Testing & Matl Failure Analysis ML20212L2771999-10-0404 October 1999 Notice of Nonconformance from Insp on 990816-20. Nonconformance Noted:Inspectors Identified Listed Six Open NCRs Initiated in 1998 & Did Not Include Timely Resolution & Disposition to Completion IR 05000146/19992021999-10-0404 October 1999 Insp Rept 50-146/99-202 on 990830-0902.No Violations Noted. Major Areas Inspected:Onsite Review of Selected Aspects of Organizational Structure & Functions Program,Emergency Preparedness,Fire Protection Program & Facility Inspections IR 05000188/19992011999-09-24024 September 1999 Insp Rept 50-188/99-201 on 990830-0902.No Violations Noted. Major Areas Inspected:Review of Selected Aspects of Operations Program,Organizational Structure & Functions Program,Design Control Program & Review & Audit Program ML20212A8531999-09-13013 September 1999 Notice of Violation from Insp on 990712-30.Violation Noted: from 980324-990730,TS SR 3.5.1.4 & 3.5.2.5 Failed to Require Each ECCS Pump to Develop Pump Differential Pressure Greater than or Equal to ECCS Total Flow Resistance ML20211N6361999-09-0808 September 1999 Notice of Nonconformance from Insp on 990630-0701. Nonconformance Noted:Licensee Had Not Performed Suitable Qualification Testing of Representative Sample or Performed Analysis to Demonstrate Environ Qualification ML20211N6411999-09-0808 September 1999 Insp Rept 99900401-201 on 990330-0701.Noncompliance Noted. Major Areas Inspected:Quality Assurance Program IR 05000228/19992011999-09-0202 September 1999 Insp Rept 50-228/99-201 on 990816-19.No Violations Noted. Major Areas Inspected:Routine,Announced Insp Was on-site Review of Selected Aspects of Licensee Class II non-power Reactor Operation IR 05000116/19992011999-09-0101 September 1999 Insp Rept 50-116/99-201 on 990810-12.No Violations Noted. Major Areas Inspected:Organizational Structure & Functions, Operations,Design Control,Review & Audit,Environ Protection, Radiation Protection Operator Requalification & Maint IR 05000160/19992031999-08-30030 August 1999 Insp Rept 50-160/99-203 on 990119-21.No Violations Noted. Major Areas Inspected:Organization & Staffing & Proposed Decommissioning Activities ML20211A7841999-08-19019 August 1999 Notice of Violation from Insp on 990802-04.Violation Noted: Rept Not Submitted for Balance of 1997 & CY98 ML20211H0891999-08-19019 August 1999 Notice of Violation from Insp on 990628-0811.Violation Noted:Periodic Assessment Conducted for Period of November 1996 Through May 1998 Did Not Adequately Evaluate Maint Activities as Listed IR 05000057/19992011999-08-19019 August 1999 Insp Rept 50-057/99-201 on 990802-04.Violations Noted. Major Areas Inspected:Review of Selected Aspects of Organizational Structure & Functions Program,Radiation Protection Program & Surveillance Program ML20217H8791999-08-16016 August 1999 NRC Operator Licensing Exam Rept 50-002/OL-99-01 (Including Completed & Graded Tests) for Tests Administered on 990719- 21.Exam Administered to One RO & One Sro.Ro Failed Written Portion of Exams IR 05000274/19992011999-08-16016 August 1999 Insp Rept 50-274/99-201 on 990713-16.No Violations Noted. Major Areas Inspected:Organizational Structure & Functions, Experiments,Operations,Fuel Handling,Safeguards,Procedures, Operator Requalification,Review & Audit & Surveillance IR 05000264/19992011999-08-10010 August 1999 Insp Rept 50-264/99-201 on 990712-15.No Violations Noted. Major Areas Inspected:Operations Program,Organizational Structure & Functions Program,Design Control Program,Review & Audit Program & Radiation Protection Program ML20210L7211999-08-0505 August 1999 Insp Rept 99900403/99-201 on 990720.No Violations or Deviations/Noncompliance Noted.Major Areas Inspected: Documentation Re Fabrication of Reactor Pressure Vessel Surveillance Specimens & Surveillance Capsules IR 05000097/19992011999-08-0404 August 1999 Insp Repts 50-097/99-201 & 50-157/99-201 on 990426-30.No Violations Noted.Major Areas Inspected:Onsite Review of Selected Aspects of Operations Program,Organizational Structure & Review & Audit Program IR 05000020/19992011999-07-30030 July 1999 Insp Rept 50-020/99-201 on 990628-0701.No Violations Noted. Major Areas Inspected:Announced Insp Included Onsite Review Selected Aspects of Design Change Functions Program, Radiation Protection Program ML20210J7151999-07-30030 July 1999 Notice of Violation from 990416 Discussion.Violation Noted: from 990128-0406,Quality Consultants & Inspections,Inc Used Iridium-192 in Missouri,Non-Agreement State Without Specific License Issued by NRC & Without Filing Form 241 with NRC ML20210C3781999-07-20020 July 1999 Notice of Violation from Insp on 990318.Violations Noted: on 980224,individual Attempted to Enter Protected Area of Plant with Firearm.Search Equipment Operator Failed to Failed to Secure Item & Prevent Access ML20210D0991999-07-16016 July 1999 Notice of Violation from Insp on 990608.Violation Noted: Between 990109 & 0410,Weldtek Testing Labs,Used Iridium 192 on Army Depot in Anniston,Alabama,Area of Exclusive Federal Jurisdiction within as Without Filing NRC Form 241 IR 05000128/19992011999-07-0909 July 1999 Insp Rept 50-128/99-201 on 990608-10.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp,Verification of C/A Previously Committed to by Licensee IR 05000186/19992011999-07-0101 July 1999 Insp Rept 50-186/99-201 on 990607-11.Violations Noted.Major Areas Inspected:Operations Program,Organizational Structure & Functions Program,Design Control Program,Review & Audit Program,Fuel Handling Program & Experimental Program IR 05000070/19992011999-07-0101 July 1999 Insp Repts 50-070/99-201,50-073/99-201 & 50-183/99-201 on 990607-10.No Violations Noted.Major Areas Inspected: Operation Program,Organizational Structure & Functions Program ML20196K0261999-06-28028 June 1999 Notice of Violation from Insp on 990616.Violation Noted: Individual Operating Moisture/Density Gauge Containing Licensed Matl in Vicinity of Fond-Du-Lac,WI,did Not Possess Whole Body Radiation Nonitoring Divice ML20196D4851999-06-21021 June 1999 Partially Deleted Notice of Violation from Insp on 990204. Violation Noted.Ed Mccormic,Individual Licensed Operator, Violated 10CFR50.53(j) by Use of Illegal Drug (Marijuana) as Evidence by Confirmed Positive Test for Urine on 981222 IR 05000166/19992011999-06-14014 June 1999 Insp Rept 50-166/99-201 on 990517-20.No Violations Noted. Major Areas Inspected:Organizational Structure & Functions, Operations,Review & Audit Program,Rp Program,Operator Requalification Program,Surveillance Program & Experiments IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000113/19992011999-06-0909 June 1999 Insp Rept 50-113/99-201 on 990504-07.No Violations Noted. Major Areas Inspected:Review of Selected Conditions & Records Since Last Insp,Verification of C/A Previously Committed to by Licensee & Discussions with Personnel IR 05000123/19992011999-06-0909 June 1999 Insp Rept 50-123/99-201 on 990517-20.No Violations Noted. Major Areas Inspected:Review of Selected Aspects of Operations Program,Organizational Structure & Functions Program,Design & Control Program & Review & Audit Program ML20207G8511999-06-0707 June 1999 Notice of Violation from Investigation Rept A4-1998-042 on 990127.Violation Noted:After 980528,ES Feemster,Initiated Reactor Simulator Training Attendance Record Indicating Attendance at 980528 Training Session Not Attended IR 05000243/19992011999-06-0707 June 1999 Insp Rept 50-243/99-201 on 990510-13.No Violations Noted. Major Areas Inspected:Onsite Review of Selected Aspects of Organizational Structure,Review & Audit Program,Radiation Protection Program,Safeguards Program & Security Program ML20195J4851999-06-0303 June 1999 NRC Operator Licensing Exam Rept 50-128/OL-99-01 (Including Completed & Graded Tests) for Tests Administered on 990405- 06.Exam Results:Both Candidates Failed Written Portion of Exams IR 05000607/19992011999-06-0303 June 1999 Insp Rept 50-607/99-201 on 990330-0401.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000002/19992011999-05-27027 May 1999 Insp Rept 50-002/99-201 on 990503-06.No Violations Noted. Major Areas Inspected:Organizational Structure & Functions, Operations,Design Control,Review & Audit,Operator Requalification,Maint,Surveillance & Procedures ML20195K1151999-05-25025 May 1999 NRC Operator Licensing Initial Exam Rept 50-156/OL-99-01 (Including Completed & Graded Tests) for Tests Administered on 990517-20 ML20207F1521999-05-25025 May 1999 Notice of Violation from Investigation Rept 1-94-021 on 940506-960329.Violation Noted:Between 740831-910407,licensee Made Changes to Facility Described in Safety Analysis Rept for Refueling Core Offloads Without Performing Evaluation IR 05000288/19990011999-05-24024 May 1999 NRC Operator Licensing Exam Rept 50-288/99-01 (Including Completed & Graded Tests) for Tests Administered on 990503-06 IR 05000182/19992011999-05-0606 May 1999 Insp Rept 50-182/99-201 on 990412-15.No Violations Noted. Major Areas Inspected:Operations,Organizational Structure & Functions,Design Control,Review & Audit,Radiation Protection & Environ Protection Programs IR 05000062/19992011999-05-0606 May 1999 Insp Rept 50-062/99-201 on 990414-16.No Violations Noted. Major Areas Inspected:Radiation Protection & Transportation ML20206M8571999-05-0606 May 1999 Insp Rept 99901339/99-201 on 990405-06.No Violations or Deviations Noted.Major Areas Inspected:Procedures & Representative Records,Interviewed Personnel & Observed Activities IR 05000005/19992011999-04-22022 April 1999 Insp Rept 50-005/99-201 on 990322-26.No Violations Noted. Major Areas Inspected:Selected Aspects of Operations Program,Physical Security Program,Radiation Protection Program & Operator Requalification Program ML20205R3271999-04-21021 April 1999 Insp Rept 99900003/99-201 on 990322-25.Violations Noted. Major Areas Inspected:Activities Related to Manufacture & Testing of Nuclear Fuel & Related Components ML20205R3171999-04-21021 April 1999 Notice of Violation from Insp on 990322-25.Violation Noted: Lab Analyst Failed to Perform Over 20 Required Weekly Calibrations of Leco Hydrogen Analyzer During Period of Apr 1996 - Mar 1999 IR 05000193/19992011999-04-0707 April 1999 Insp Rept 50-193/99-201 on 990322-26.No Violations Noted. Major Areas Inspected:Licensee Programs Re Operations,Health Physics & Security IR 05000131/19992011999-04-0707 April 1999 Insp Rept 50-131/99-201 on 990315-17.No Violations Noted. Major Areas Inspected:Organization,Operations & Maint IR 05000326/19992011999-03-25025 March 1999 Insp Rept 50-326/99-201 on 990223-25.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000146/19992011999-03-22022 March 1999 Insp Rept 50-146/99-201 on 990216-18.No Violations Noted. Major Areas Inspected:Plant Status,Including Dismantlement Activities,Odcm & Calibr of Effluent Radiation Monitoring Sys & Flow Rate Monitors 1999-09-08
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
o l
4 NOTICE OF NONCONFORMANCE Siemens Power Corporation Docket No.: 99900081 Nuclear Division.
Pichland, Washington l
On February 10 through May 13,1997, the staff of the U.S. Nuclear Regulatory Commission (NRC) performed an inspection of activities conducted by the Siemens Power
-l Corporation - Nuclear Division (SPC), at the company's facilities in Richland, Washington.
j The results of that inspection found that SPC failed to perfonn certain activities in accordance with applicable NRC requirements, as detailed in this notice of nonconforma're.
A.
Criterio !!!, "DcJign Control," of Appendix B to Title 10, Part 50, of the bde of Dderal Regulations (10 CFR Part 50), requires that design control measures shall provide for verifying or checking the =d~;a y of design, and shall be applied to i
reactor physics, stress, thennai, hydrauls, and accident analyses.
Section 4, " Design Control," of SPC's Quality Assurance (QA) Program topical
+
report, EMF-1, " Quality Assurance Pregam for Nuclear Fuels and Services,"
Revision 28, dated Febmary 10,1995, requires that design verirmation activities shall be perfonned in accordance with sub-tier QA and Engineering procedures. (The NRC approved EMF-1 on January 16,1996, as meeting the reqeirements of Appendix B to 10 CFR Part 50.)
SPC adopted the NRC approved methodology to detennine the safety limit and operating limit minimum critical power ratios (SLMCPR and OLMCPR) for boiling-water reactor (BWR) licensees. Specifically, the methodology, now the property of SPC, was developed by Advanced Nuclear Fuels Corporation (ANF), as documented y
,in ANF 1125(P)(A), "ANFB Critical Power Conclation," Supplements 1 and 2 dated April 4,1990. As stated in the conditions of approval in the NRC's safety evaluation (SER) for ANF 1125(P)(A), this NRC-approved and SPC adopted methodology limited the local peaking factor to F:. s; 1.3, and did not permit a flow-dependent bias.
Contrary to the above, the following examples demonstrate SPC's failure to comply j
with established methodologies and, therefore, constitute Nonconformance 99900081/97-01-01.
(1) - IIn the following instances, SPC failed to verify the adequacy of the ANFB i
" critical power correlation and the adequacy of its application to the '
+
' ATRIUM *-10 fuel assemblies designed for the Pennsylvania Power and Light.
Company, Susquehanna Unit 2 Cycle 9 relot,d:
[
JM71agvgg t.
m m
i
- (a)
The appikation of the ANFB correlation to the ATRIUM *-10 fuel assemblies for Susquehanna Unit 2
- Cycle 9 showed that the local p-=Hng factor (F,) was t
greater than 1.3, which placed it outside the NRC-approved range for the ANFB correlation of less than i
1.3.
l (b)
As used to determine the SLMCPR and OLMCPR for the ATRIUM"-10 fuel assemblies for Susquehanna Unit 2 Cycle 9, the ANFB corr 1=' ion included a l
nonconservative flow bias and, therefore, was outside the l
NRC approved SPC methodology, i
(2)
SPC failed to develop a adequate number of test points, rnd failed to test an adequate range of conditions to justify the uncertainty values for the additive constants" used in determining the SLMCPR for the ATRIUM"-9 fuel design.
This implies that SPC should have used larger uncertainty values in the.
SLMCPR determination,, in order to reflect the full operability range of the -
ATRIUM" 9 fuel design. In addition, because the results of the ANFB correlation are used as inputs to the safety limit taethodology, this has immediate implications regarding the SLMCPR and OLMCPR of the following plants with ATRIUM"-9 fuel:
Commonwer'th Edison Company Quad Cities Unit 2 Cycle 15 Dresden Unit 3 Cycle 15 12Salle County Unit 2 Cycle 8 Washington Public Power Supply System Washington Nuclear Unit 2 Cycle 13 B.
Criterion III, " Design Control," of Appendix B to 10 CFR Prat 50, requires that design control measures shall provide for verifying or checking the adequacy of design, and shall be applied to reactor physics, stress, thermal, hydraulic, and acc!: lent analyses.
Section 4, " Design Control," of SPC's Quality Assurance (QA) Program topical report, EMF-1,
- Quality Assurance Program for Nuclear Faels and Services,"
Revision 28, dated Febnsary 10,'1995, requires that design verification activities shall be performed in accordance with sub-tier QA and Engineering procedures. (The NRC approved EMF-1 on_ January 16,1996, as meeting the requirements of Appendix B to 10 CFR Pan 50.)
2 r
4.-
, -.., -.- -,,--~.-.,w.,
,n-.,...,r w-,
~,,-r-.-y.-4
.w,
-wm.,,,,w,,w.r-.
.s QAP4 requires that Research and Technology (R&T) shall be responsible for j
supporting the design process by developing and maintaining computer codes and methodologies. QAP-4 also states that design verification is the process of reviewing, confirming, or substantiating (validating) the design by one or more methods to l
provide assurance that the design meets specifad requirements.
i Contrary to the above, the following examples demonstrate SPC's failure to comply with established procedures and/or methodologies and, therefore, constitute l
Nonconformance 99900081/97 01-02.
j (1)
For thermal hydrau.ic (T/H) analysis, SPC used a variety of system codes, such as ANF RELAP and S RELAP. SPC derived these codes from other codes developed by the NRC and the U.S. Depanment of Energy (DOE).
SFC modified the codes after adopting them for in house use and but failed to adequately verify, develop or maintain the modifed codes.
In panicular, SPC failed to (a) perform verif% tion activities for codes that are purchased from outside sources for use by SPC, (b) document testing and verification of the code, (c) perform adequate code validation, and in many instances, perform independent validation.
'(2)
Software development record (SDR) 10315 documents a change to the COTRANSA code, which is used to perform plant specific anticipated operational occurrence (AOO) analyses. After implementing this change, SPC did perform the required verification and validation (V&V); however one of the cases used in the V&V of this case was not technically adequate. SPC -
subsequently identified and corrected an input error, and reanalyzed the case with satisfactory results. However, SPC failed to record this input error or its effect on the analysis.
(3)
SDR 10610 documents several small discrepancies in the results obtained using the UNIX and Cray versions of the FLEX code, which could lead to a reduction in the calculated peak cladding temperature (PCT). SPC stated that these discrepancies were caused by differences in the floating point precision of the two computer systems. However, SPC failed to confirm and record in SDR-106-10 its. fmdings concerning this assumed causal factor.
(4)
As reponed in ANF-91-048(P)(A), published in 1993, comparison between the RELAX and FLEX codes and their respective primary documentation (XN-
.NF 98019(P)(A) published in 1982) verified that (a) the code solution
. procedure had been modified (b) important T/H models had been changed substantially, and (c) a number of new input options had been added.
Nevenheless, the reported verification of these changes corr.isted of a single
. systems calculation. No comparisons with experimental data were included, 3
= = -
~. -
e 4
nor were there any test casse to show that models unaffected by the modification gave the same results as the previous versions of the code.
Therefore, SPC apparently implemented modifications to the RELAX and FLEX codes without adequate verifier. ion of changes.
C.
Criterion !!!, " Design Control " of Appendix B to 10 CFR Part 50, requires that design control measures shall provide for verifying or checking the adequacy of j
design and shall be applied to reactor physics, stress, thermal, hydraulic, and accident analyses.
- 10 CFR 50.46(a)(3)(i) states that a sigel%
.c change or error is one which results in a calculated PCT which differs by more u, n 50'F from the temperature calculated for the limiting transient using the last acceptable model.
i Contrary to the, above, SDR-1241, whl;h addresses changes in TOODEE2, usug95 code, documented a change in PCT of 63'F, resulting from a change in RELAPS code boundary conditions. Even though the change in PCT was more than 50'F, SPC failed to consider it a significant change and provide sufficient information to NRC licensees so that licensees could report the nature of the ciange to the NRC as required by 10 CFR 50.46. This constitutes Nonconformance 99900081/97-01-03.
D.
Criterion 111, " Design Control," of Appendix B to 10 CFR Part 50, requires that design control incasures shall include provisions to ensure that appropriate quality
- standa.-ds are specified and included in design documents and that deviations from such standards are controlled.
Criterion V, " Instructions, Procedures, and Drawings," of Appendix B to 10 CFR Part 50, requires that activities affecting quality shall be prescribed by and accomplished in accordance with documented instructions, procedures, or drawings.
Section 4, " Design Control," of SPC's Quality Assurance (QA) Program topical report, EMF 1, "Qu:.lity Assurance Program for Nuclear Fuels emi Services,"
Revision 28, dated Februry 10,1995, requires thet design verification activities shall be perfonned in accordance with sub-tier QA and Engineering procedures. (The NRC approved EMF 1 on January 16,1996, as meeting the requirements of Appendix B to '9 CFR Part 50,)
QAP-4 requires that R&T shall support the design process by developing and maintaining computer codes and methodologies. In addition, QAP-4 states that errors sre to be reported according to the requirements of EMF-P00,066, QAP-13, " Control of Nonconformances " Revision 0, dated August 22,1996, and that corrective actions and their disposition are to be performed according to the requirements in EMF-P00,067, QAP 14, " Corrective Action," Revision 0, dated August 22,1996.
F 4
g.
p,
.---.-.w--
,wn.,
,rn r~
~
Contrary to the above, the following e.tamples demonstrate SFC's failure to established adequate procedures and/or methodologies and, therefore, constitute Nunconformance 99900081/97-01-04.
(1)
SPC failed to establish an acceptable verification and validation (V&V) procedure for code development and modification. SPC also failed to establish an adequate code design verification method, in tu icular, SPC failed to clearly define minor changes or errors, and it did nci establish an adequate code assessment process that included assessment of code changes against apr griate phenomenological tests, separate effects tests, and/or integral system tests.
(2)
EMF-608, " Computer Code Control Requirements - Engineering,"
(EMF-608), Revision 12, dated December 27,1995, and Revision 13, issued during the inspection on February 7,1997, failed to address notification concerning code errors and evaluation of the effects of such errors on the end-user. Revkion 14 to EMF-608, issued on March 12, 1997, also did not adequately address these issues.
(3)
SPC failed to provide adequate instructions to its analysts for use in selecting the appropriate entrainment fraction to establish the time of reflood for LOCA analyses. SPC then changed the process for determining the time of reflood, establishing not only a relative entrainment fraction, but also an " absolute" criterion dt.;ived on the bases of the mass velocity of entrained liquid, as documented in SPC memorandum, " Response Packages for Issues from NRC Inspection Week 1," dated March 14, 1997.
Howevn the rellood mass velocity is subject to significant oscillations, spikes, and other unsteady behavior (that is, it is not a smooth monotonically increasing function of time). Consequently, SPC failed to establish criteria rqnrding the steadiness of the entrainment mass velocity and the minimum ra% ion over which the mass velocity exceeds the " absolute" value used to 4mtms.e the onset of reflood.
E.
Criterion II, " Quality Assurance Program," of Appendix B to 10 CFR Part 50, requires that the QA program shall provide for indoctrination and training of personnel performing activities affecting quality as necessary to ensure that they achieve and maintain suitable proficiency.
Sectior 18, " Training," of QA topical report EMF-1, Revision 28 requires the respective supervisor / manager be responsible for defining, implementing, and documenting appropriate training to ensure that employees achieve and maintain the proficiency needed to carry out their assignments.
5
To funher define the applicable procedures, SPC developed EMF-P00,071, QAP-18,
" Training," Revision 0, dated August 22,1996. In panicular, that procedure requires that the applicable tranager snall use assessment of education and experience to determine the specific type (s) and extent of tra'.dng necessary to corcpetently perform a specific job. Highty technical jobs (for ext mple, it' Engineering) may require extensive education and prior experience befc o an ir divi 6al is qualified to perform the related responsibilities without oversight or w,, stance.
Contrary to the above, SPC's current training program fails to provide the necessary assessment of education and experience. SPC failed to establish the method or procedure for determining the knowledge and skills needed to perform the tasks associated with the functions of a specific engineering-related job or job category, as required by EMF-1560, " Nuclear Engineering and Product Mechanical Enginering Training and Proficiency Assessment Guideline," Revision 1. In addition, SPC failed to establish a method or procedure for evaluating the effectiveness of the training program. This constitutes Nonconformance 99900081/97-01-05.
Pinse provide a written statement or explanation to the U.S. Nuclear Regulatory Cuanission, A'ITN: Document Control Desk, Washington, D.C. 20555, with a copy to the Chief, Quality Assurance, Vendor Inspection, and Maintenance Branch, Division of Reactor Controls and Human Factors, Office of Nuclear Reactor Regulation, within 30 days of the date of the letter transmitting this notice of nonconformance. This reply should be clearly marked as a " Reply to a Notice of Nonconformance," and should include for each nonconfonnance (1) the reason for the nonconformance, or if contested, the basis for disputing the nonconformance, (2) the conective steps that have been taken and the results achieved, (3) the corrective steps that will be taken to avoid funher noncompliances, and (4) the date when your corrective action will be completed. When good cause is shown, consideration will be given to extending the response time.
Because your response will be placed in the NRC Public Document Room (PDR), to the extent possible, it should not include any personal privacy, proprietary, or safeguards information so that it can be placed in the PDR without redaction. If personal privacy or proprietary information is necessary to provide an acceptable response, then please provide a bracketed copy of your response that identifies the information that should be protected and a redacted copy of your response that deletes such information. If you request withholding of such material, you mM11 specifically identify the portions of your response that you seek to have withheld and provide in detail the basis for your claim of withholding (e.g., explain why the disclosure of information will create an unwarranted invasion of personal privacy or provide the infonnation required by 10 CFR 2.790(b) to support a request for withholding confidential commercial or financial information). If safeguards information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21.
Dated a3 Rockville, Maryland thisMPday of October,1997 6
l l
_