ML20199E105

From kanterella
Jump to navigation Jump to search
Summary of 981119 Meeting with Util to Discuss Pge Preliminary Plans for Final Site Radiation Surveys at Trojan Nuclear Plant.List of Attendees Encl
ML20199E105
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 01/13/1999
From: Thonus L
NRC (Affiliation Not Assigned)
To:
NRC (Affiliation Not Assigned)
References
NUDOCS 9901200315
Download: ML20199E105 (4)


Text

. _ _ . . _ _ _ _ __ _. . _ _ _ . _ _ . . ._ ___ _ - _ - . _

7 January 13, 1999 LICENSEE: Portland General Electric Company FACILITY: Trojan Nuclear Plant

SUBJECT:

SUMMARY

OF MEETING HELD ON NOVEMBER 19,1998 BETWEEN THE NRC AND PORTLAND GENERAL ELECTRIC REGARDING LICENSEE PLANS FOR FINAL SITE SURVEYS AT TROJAN On November 19,1998, members of the NRC staff met with representatives from Portland General Electric (PGE) to discuss PGE's preliminary plans for final site radiation surveys at the Trojan Nuclear Plant. A list of the NRC and PGE attendees is included as Enclosure 1.

Since PGE has not yet submitted any docketed correspondence on final site surveys, the meeting was informational in nature. PGE representatives described their preliminary plans for the final site radiation surveys for the Trojan site (slides are included as Enclosure 2).

The NRC staff provided the licensee with an updated reference which replaces NUREG 5512. The NRC staff informed the PGE staff that the survey plan needed to be submitted as part of the license termination plan (as required by 10 CFR 50.82) and that the NRC staff could not perform a meri agful review without the remainder of the license termination plan.

ORIGINAL SIGNED BY:

Lee H. Thonus, Project Manager Non-Power Reactors and Decommissioning Project Directorate Division of Reactor Program Management Office of Nuclear Reactor Regulation Docket No. 50-344

Enclosures:

1. List of Attendees

)

1

2. PGE slides I cc w/ enclosures:

See next page i DISTRIBUTION: (Enclosure 2 in PDND r/f)

E-Mall and Docket File 50-344 HARD COPY SCollins/RZimmerman (SJC1/RPZ) RBurrows (Docket File 50-344 i BBoger (BAB2) RDudley PUBLIC DMatthews (DBM) MFairtile SWeiss 1 l

TMartin (SLM3) TFredrichs PDND r/f I

THiltz (TGH) PHarris LThonus WHuffman ,

TKenyon Region til 'g I D

AMarkley qy JMinns JHickey (T7-F27)

Pray , O '5 DScaletti MMasnik MWebb -

DWheeler EHylton PDND:PM g PD :LA PDND:(A)S LThonus E- o MMasnik H S ss 1/0/99 1/ /99 1/l]/99 1/g/99 OFFICIAL RECORD COPY DOCUMENT NAME: G:\SECY\MTG_NOTC\MTGSUM.LT 9901200315 990113 DR ADOCK 050003 4 ,_ , - . c, ot_ . _ - . _ -

3 pn CEcoq l

  • y k UNITED STATES j* j NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 2066M001

/ January 13, 1999 l

l LICENSEE: Portland General Electric Company FACILITY: Trojan Nuclear Plant I

l

SUBJECT:

SUMMARY

OF MEETING HELD ON NOVEMBER 19,1998 BETWEEN THE NRC AND PORTLAND GENERAL ELECTRIC REGARDING LICENSEE PLANS FOR FINAL SITE SURVEYS AT TROJAN l

On November 19,1998, members of the NRC staff met with representatives from Portland General Electric (PGE) to discuss PGE's preliminary plans for final site radiation surveys at the Trojan Nuclear Plant. A list of the NRC and PGE attendees is included as l Enclosure 1. l Since PGE has not yet submitted any docketed correspondence on final site surveys, the meeting was informational in nature. PGE representatives described their preliminary plans for the final site radiation surveys for the Trojan site (slides are included as Enclosure 2).

The NRC staff provided the licensee with an updated reference which replaces NUREG 5512. The NRC staff informed the PGE staff that the survey plan needed to be j submitted as part of the license termination plan (as required by 10 CFR 50.82) and that the NRC staff could not perform a meaningful review without the remainder of the license termination plan.

%// M Lee H. Thonus, Project Manager Non-Power Reactors and Decommissioning Project Directorate Division of Reactor Program Management Office of Nuclear Reactor Regulation Docket No. 50-344 l

Enclosures:

1. List of Attendees
2. PGE slides cc w/ enclosures:

! See next page 1

4 L

l l

..._._-..___.________.___..._.____.m..__ . . . _ . _ . _ _ _ . .

9 Mr. Stephen M. Quennoz . Trojan Nuclear Plant Portland General Electric Company Docket No. 50-344 cc:

Chairman of the Board of County I Commissioners Columbia County St. Helens, OR 97501 Mr. David Stewart-Smith '

Oregon Department of Energy i 625 Marion Street, N.E. ,

Salem, OR 97310  !

Regional Administrator, Region IV U.S. Nuclear Regulatory Commission Harris Tower and Pavilion ]

611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 Mr. H. Ray Pate Manager Licensing, Compliance and Commitment Management Portland General Electric Company Trojan Nuclear Plant 71760 Columbia River Highway I Rainier, OR 97048 l l Mr. Lloyd K. Marbet I

! 19142 S.E. Bakers Ferry Road l- Boring, OR 97009 i Mr. Jerry Wilson l

!- Do it Yourself Committee r- 570 N.E. 53rd

!' Hillsboro, OR 97124 l Mr. Eugene Rosofie

! Northwest Environmental Advocates 302 Haseltine Building 133 S.W. 2nd Avenue Portland, 'OR - 97204

).

i l

r 9

ENCLOSURE 1 ATTENDEES Trojan Final Site Survey Meeting November 19,1998 Portland General Electric Jerry Cooper Lanny Dusek Gina Huey Tom Meek NRC Ann Hodgdon, OGC Tim Johnson, NMSS/DWM-John Minns, NRR/PDND Pat Santiago, NMSS/DWM Lee Thonus, NRR, PDMD