Forwards Rev 16 to Erp ERP-230, OSC Activation. Procedure Revised with Effective of 981007 & Not Submitted within 30 Days as Required by 10CFR50,App E.Computer Generated Rept Index Identifying Latest Revs of Erps for PBAPS Also Encl
ML20199D371
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 01/07/1999
From: Geoffrey Edwards
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20199D375 List:
References
NUDOCS 9901200082
Download: ML20199D371 (1)


Text

-..,.

. - ~,--.. ~. - _. - - - -

. - _.~,. -. - - _..-_. ~ -

etitlan cupport Deptrim2nt

_i_

10CFR50, Appendix E

=

PECO NUCLEAR geco s,, c,,

965 chesterbrook Bouievara A Unit of PECO Energy Wayne PA 19087-5091 January 7,1998 j

l Docket Nos. 50-277 l

50-278 License Nos. DPR-44 DPR-56 U.S. Nuclear Regulatory Commission l

Attn: Document Control Desk Washington, DC 20555

Subject:

Peach Bottom Atomic Power Station, Units 2 and 3 Emergency Response Procedure Revisions

Dear Sir / Madam:

By letter dated December 11,1998, PECO Energy submitted revised emergency response l

implementing procedures for Peach Bottom Atomic Power Station (PBAPS), Units 2 and 3. In our letter, we indicated that a nLmber of the procedures were not submitted within 30 days of their revision as required by 10CFR50, Appendix E, due to an administrative oversight. As a result of an investigation into this incident, we identified one (1) additional procedure that we l

failed to submit within 30 days of its revision.

l l

Accordingly, the following enclosed Emergency Response Procedure (ERP) for PBAPS, Units 2 and 3, was revised with an effective date of October 7,1998, and was not submitted within 30 l

days as required by 10CFR50, Appendix E. This letter provides the required notification of the revision to the above procedure. We apologize for any inconvenience this may have caused.

ERP-230, Rev.16 " Operations Support Center (OSC) Activation."

l Also enclosed, is a copy of a computer generated report index identifying the latest revisions of j

ine ERPs for PBAPS.

i If you have any questions or require additional information, please do not hesitate to contact us.

I Very1

yours, 4

\\.

\\

arrett D. Edwards

' Director - Licensing

%q O{

Enclosures I

cc:

H. J. Miller, Administrator, Region I, USNRC (w/ enclosures,2 copies)

A. C. McMurtray, USNRC Senior Resident inspector, PBAPS (w/ enclosures) 4

~

9901200082 990107 PDR ADOCK 05000277 Y