Northern States Power Company Prairie !sland Nuclear G;nerating Plant 1717 Wakonado Dr. East Welch, Minnesota $500C January 23,1998 U S Nuclear Regulatory Commission Attn: Document Cr ntrol Desk Washington, DC 20555 PRAIRIE ISLAND NUCLEAR GENERATING PLANT Docket Nos. 50 282 License Nos. DPR-42 50-306 DPR-60 Updated Reply to Notice of Violation (Inspection Report 97015)

Failure to Declare Rod Deviation Monitor Inoperable as Required by Procedure Your letter of September 19,1997, which transmitted Inspection Report No. 97015, required a response to a Notice of Violation. Our response to the notice was submitted October 20,1997. In that response we made a commitment to revise the rod position verification surveillance procedures to include the required actions identified in existing Temporary Memorandums for determining individual rod position indicator and rod position deviation monitor operability. We also committed that input from users of the procedures would be factored into the revisions and that the revisions would be completed by December 31,1997.

The completion of the committed procedure revisions took longer than originally anticipated. A December 31,1997 due date for an associated Error Reduction Task Force corrective acti vvas identified and that due date was extended prior to December 31,1997. However, becauso the NRC commitment from the October 20, 1997 response had not been entered into the Prairie Island commitment tracking system, the individual responsible for completion of the procedure revisions was not

[j aware that a commitment had been made to the NRC to revise the procedures by

'2 December 31,1997, and the NRC was not informed of the delay in completion of the procedure revisions prior to tne committed date.

jgol l.I.[.lb. ll.ilh..b.

90o1290178 900123 ADOCK0500g2 POR

.e USNRC NORTHERN STATES POWER COMPANY January 23,1998 Pago 2 It was identified on January 5,1998 that the commitment to complete the procedure revisions by December 31,1997 had not been met. The procedure revisions were subsequently approved on January 6,1998. The procedures were not utilized during the period between December 11,1997 and when the procedure revisions were approved on January 6,1998. If 1: 9ad been necessary to utilize the procedures during that period of time, the requir6. Aanges were in place in the form of Temporary Memorandums.

Changes to the commitment tracking process which would ensure that all NRC commitments are entered into the tracking system in a more timely manner are being implemented, in this letter we have reported a change to the completion date for one Nuclear Regulatory Commission comnntment, from December 31,1997 to January 6,1998.

Please contact Gene Eckholt (012-369-1121) if you have any questions related to this

letter, Joal P Sorensen Plant Manager Prairie Island Nuclear Generating Plant c: Regional Administrator Region 111, NRC Senior Resident inspector, NRC NRR Project Manager, NRC J E Silberg 1