Informs NRC of Change in Completion Date for Regulatory Commitment Made in USEC Ltr Re Certificate Amend Request & Ncsas/Ncses.Specifics of Commitment Changes, Listed
ML20198L323
Person / Time
Site: Portsmouth Gaseous Diffusion Plant
Issue date: 12/28/1998
From: Toelle S
UNITED STATES ENRICHMENT CORP. (USEC)
To: Paperiello C
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM), NRC OFFICE OF NUCLEAR MATERIAL SAFETY & SAFEGUARDS (NMSS)
References
GDP-98-0289, GDP-98-289, NUDOCS 9901040157
Download: ML20198L323 (4)


Text

.-.

CSEC

. A Global Energy Company j

December 28,1998 GDP 98-0289 Dr. Carl J. Paperiello 1

Director, Office of Nuclear Material Safety and Safeguards Attention: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Portsmouth Gaseous Diffusion Plant (PORTS)

Docket No 70-7002 Notification of Change in Regulatory Commitment - Certificate Amendment Request -

Deletion of Seal Exhaust Pump Overflows in Buildings X-330 and X-333

Dear Dr. Paperiello:

The purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of a change in the completion date for a regulatory commitment. This commitment was made in USEC letter GDP 98-0127 dated July 1,1998 (Reference 1), and it is related tc the certificate amendment request and the revision of NCSAs/NCSEs. The specifics of the commionent changes are provided below.

Original Commitment Letter GDP 98-0127, Enclosure 1, Response (2) stated:

The applicable NCSAs/NCSEs governing the Area I, Il and III seal exhaust system will be revised to reflect the limiting oil quantity noted in Item (1) above and as stated in GDP 98-0027 (Reference 3). Those revisions will be prepared and approved by December 31,1998.

f Revised Commitment Tlie commitment has been revised to read as follows:

\\

\\\\,D b

/

The applicable NCSAs/NCSEs governing the Area I, II and 111 seal exhaust system T

will be revised to reflect the limiting oil quantity noted in Item (1) above and as stated in GDP 98-0027 (Reference 3). Those revisions will be prepared and approved by January 1 1998.

990104C157 981228 PDR ADOCK 07007002 3*

C PDR 6903 Rockledge Drive, Bethesda, MD 20<.17-1818 Telephone 301-564-3200 Fax 301-564-3201 http://www.usec.com Offices in Livermore. CA Paducah, KY Portsmouth, OH Washington, DC

,a 1

1 Dr. Carl J.,Paperiello December 28,1998 l

GDP 98-0289, Page 2 Justification for Revised Commitment Revision of the NCSA described by the original commitment identified additional changes to the Safety Analysis Report (SAR) requirement for alumina loading of chemical traps. This requirement is not directly related to the seal exhaust overflows, but is part of the seal exhaust station operation.

' The NCSA cannot be completed until these changes are made to the SAR. The Request for Application Change has been initiated to make the changes to the SAR, but will take additional time to complete.

Should you have any questions related to this subject, please contact Mark Smith at (301) 564-3244.

Commitments contained in this submittal are identified in Enclosure 1 to this letter.

Sincerely, 0-W YSee

, Steven A. Toelle Nuclear Regulatory Assurance and Policy Manager E

Enclosure:

Commitments Contained in This Submittal

. cci Mr. Robert C. Pierson, NRC HQ NRC Region III Office NRC Resident Inspector-PORTS 1

NRC Resid nt Inspector-PGDP js L

l c

i I

i l

. Dr. Carl J. Paperiello December'28,1998 GDP 98-0289, Page 3 i

REFERENCES 1)

Letter from Steven A. Toelle (USEC) to Dr. Malcolm R. Knapp (NRC), " Response to Request for Additional Information - Certificate Amendment Request-Deletion of Seal Exhaust Pump Overflows in Buildings X-330 and X-333," USEC Letter GDP 98-0127, dated July 1,1998.

1 i

l l

i l

4 d

~.

n i-

,,3.

p.

I GDP 98-0289 Page1of1 Commitments Contained in This Submittal The following commitment is revised from that contained in Reference 1 as described in the cover letter of this submittal:

1.

The applicable NCSAs/NCSEs governing the Area I, II and III seal exhaust system will be revised to reflect the limiting oil quantity noted in Item (1) above and as stated in GDP 98-0027 (Reference 3). Those revisions will be prepared and approved by January 15,1998.