Notifies of 1986 Indian Point 2 full-participation Exercise on 860604 (Insp Rept 50-247/86-13).Team Assignments, Schedule,Exercise Event & Time Line,Open Items,Objective Lists & Synopsis of State & County Matl Encl.W/O Encl
ML20198H938
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 05/16/1986
From: Amato C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Bellamy R, Van Neil R, Vito D
NRC, NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
NUDOCS 8605300607
Download: ML20198H938 (4)


See also: IR 05000247/1986013

Text

__ . _ - - _ __

_

-

_.._ _ _ _ _ __. . _ _ _ . _

I

.

,

!

! ,

Docket No. 50-247

t

i

MEMORANDUM FOR: Distribution

2 THRU: Terry L. Harpster, Chief, Emergency Preparedness Section '

Emergency Preparedness and Radiological Protection Branch

Division of Radiation Safety and Safeguards

FROM: Charles G. Amato, Regional Team Leader, EPS, EP&RPB, DRSS

,

SUBJECT: 1986 INDIAN POI: i-2 FULL PARTICIPATION EXERCISE j

j

! The exercise will be held on June 4 beginning at 6:10 A.M. and ending about 12 l

1 hours later. Our inspection number is 50-247/86-13.

2

i We will stay at the Thayer Hotel, West Point, New York. Reservations have  !

,

been made for Monday through Thursday morning. The hotel cannot accommodate

j anyone after noon Thursday. Please call 914-446-4731 to guarantee your

i reservation no later than Friday, May 23, 1986. (Those staying beyond

i Thursday are to make their own arrangements). The rate is $49 per day; there

! is no State tax. Three R/As have been reserved for Region I team members.

Travel request forms have been completed for team members.

]

! Familiarize yourself with IE Inspection Procedure 82301; Indian Point-2

! Emergency Plans and Inspection Procedures which relate to your assignment; the .

l openitemsandobjectives(listofeachattached);andthescenario.

i

There may be intense public awareness. NRC and FEMA will hold a public

i meeting beginning at 10:00 A.M. Friday, June 6 in Building 1 of the

Westchester County Airport to discuss the exercise.

!

] Attached are the team assignments and schedule, exercise event and time line,

) open items, objective lists, and a synopsis of the New York State /four county

! RERP. Additional material may be forwarded at a later date, if needed, and ,

j may be hand written. -

1

'

If you have questions, comments, suggestions or problems, call me at FTS

488-1394 or 215-337-5394. ,

l

!

Wh.

Charles G. Amato

&

Regional Team Leader

l

!

1

I

0FFICIAL RECORD COPY

]

p 5000h47

. m a gg

.

Distribution 2

Attachments:

1. Team Assignments and Schedule

2. Exercise Event and Time Line

3. Open Items and Objectives List

4. Synopsis of Off-site Plan

Distribution:

R. Bellamy, RI

R. Van Neil, HQ

D. Vito, RI

P. Gaul, RI

P. Koltay, SRI, IP3

E. Podolak, HQ

L. Rossback, SRI, IP2

J. Hawxhurst, RI

J. Jamison, PNL

'.

k

to 78

5//4/86 5/l@6

0FFICIAL RECORD COPY

_ _ . . ._ _ . - _.

! ,

.

.

Enclosure I

Team Schedule and Assignments

!

A. Schedule

i

l Monday, June 2 Team members arrive at hotel

i

j Tuesday, June 3 0800-1030 Accesstrainingandbadging ,

!

1100 Controller-observer briefing

' 1500 NRC team meeting

Wednesday, June 4 0610 Exercise begins

1745 Exercise ends

,

1815 Initial NRC team debriefing 2

2

Thursday, June 5 0830 NRCteamdebriefingcontinueg

1

1100 Consolidated Edison critique

l

1330 NRC exit meeting

j 1330 FEMA / State / County meeting

Friday, June 6 1000 NRC/ FEMA public meeting

,

fSimulatorbuildingconferenceroom

!

E0F conference room

.

C

,

4

'

l

!

!

I

i

l

4

3

0FFICIAL RECORD COPY

l

_. . - _ _ _ - .-

1

4

.

.

.

Enclosure II

B. Team Assignments

! 1. Control Room Gary Weale, PNL

2. Technical Support Center Larry Rossback, SRI, IP2

t

3. OSC/ accountability Darrell Fisher, PNL

4. E0F Ed Podolak, HQ

5. EOF Charles Amato, RI I

6. On-site team John Davis

,

{

7. Off-site team Joseph Stephen

8. JNC Davo Vito

9. RAC Observer Jim Hawxhurst

.i

fTeam Leader / Floating Observer until E0F activation ordered

,! Senior Inspector / Floating Observer. Will observe JNC after activation

i

a

1

1