Forwards Insp Rept 99901022/85-01 on 850612-14 & Notice of Nonconformance
ML20198F405
Person / Time
Issue date: 11/13/1985
From: Zech G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To: Hatch A
HATCH, INC.
Shared Package
ML20198F409 List:
References
REF-QA-99901022 NUDOCS 8511140344
Download: ML20198F405 (2)


Text

.

/

UNITED STATES 8.

NUCLEAR REGULATORY COMMISSION o

WASHINGTON, D. C. 20555

(

November 13, 1985 Docket No. 99901022/85-01 p-Hatch Incorporated ATTN: Mr. A. E. Hatch President 1206 Myrtle Avenue e

El Paso, Texas 79901 Gent % men:

This refers to the inspection condu[tEd by K.',R. Naidu and J. C. Harper of this E

12-14, 1985, of your facility at El Paso, Texas and to the office on June discussions of our findihgs with you and your Qualii.y Control Manager at the i$

conclusion of the inspection.

The purpose of this inspection was to determine the adequacy of the implemen-

=

Areas tation of your quality assurance program with emphasis on welding.

3 examined during the inspection and our findings are discussed in the enclosed g

Within these areas, the inspection consisted of an examination of report.

procedures and representative records, interviews with personnel, and observations by the inspector.

=EE During the inspection it was found that ths implementation of your QA program failed to meet certain NRC requirements. Our inspectors identified two 7

nonconformances; one relates to inadequacies in yow welding activities and the 1-other involves a failure to establish a procedure for crimping of electrical E

connections ~. The specific findings and references to the pertinent requirements at are identified in the enclosures to this:1etter.

y N

E Please provide us within 30 days from the date of this letter a written statement containing:

(1) a description of steps that have been or will be taken to correct these items; (2) a description of steps that have been er

~

will be taken to prevent recurrence; and (3) the dates your corrective actions and ' preventive measures were or will be completed. Consideration may be given to extending your response time for good cause shown.

In accordance with 10 CFR 2.790 of the Commission's regulations, a copy of this letter and the enclosed inspection report will be placed in the NRC's Public Document Room.

4

\\

t 0511140344 851113 PDR GA999 ErfVHATCH d

99901022 PDR h

l

. November 13, 1985 Hatch Incorporated Should you have any questions concerning this inspection, we v.ill be pleased to discuss them with you.

Sincerely, ORIGtNAL $1GNED BY:

GARY G. ZECH Gary G. Zech, Chief Vendor Program Branch Division of Quality Assurance, Vendor, and Technical Training Center Programs Office of Inspection and Enforcement

Enclosures:

1.

Appendix A - Notice of flonconformance 2.

Appendix B - Inspection Report No. 9991022/85-1 Distribution:

p :lE:09 VPB rdg DQAVT rdg RVollmer JCollins JStone EMerschoff KNaidu JHarper

~

  • e previous concurrence.

(~