m NOV 121995 Docket No. 50-29 LICENSEE:

Yankee Atomic Electric Company FACILITY:

Yankee Nuclear Power Station

SUBJECT:

TRIP REPORT: MANAGEMENT REVIEW MEETING Two members of the NRC staff met with the project staff, plant personnel and senior management for the Yankee Nuclear Power Station (Yankee) on October 29 and 30, 1985. The trip was made to allow the NRC managers for Yankee in the proposed NRR organization to become familiar with the Yankee Atomic Electric Company organization and operations.

engineering improvements (both NRC mandated and plant betterments) goin Discussions held on October 29 covered the Yankee organization, on

, meetings with members of the Yankee staff, and tours of the computer and environmental monitoring facilities. An informal round-table discussion was held with senior management from the Yankee organization.

General issues identified at this management discussion included timely completion of Systematic Evaluation Program cpen issues, consideration of licensing actions by accounting for plant unique characteristics, and completion of amendments for the current refueling outage.

A tour of the Yankee plant site was conducted October 30.

Following the tour, the NRC staff met with members of the plant management to discuss current operational and licensing concerns. Additionally, the impact of the SEP process and reviews on future licensing actions was discussed.

Cr W & M D7 James W. Clifford, Project Manager Operating Reactors Branch No. 5 Division of Licensing DISTRIBUTION Docket File NRC POR Local PDR ORBf 5 Reading -

JZwolinski CJamerson JClifford t112 0511140310gonoo29 goj OELD EJordan PDR ADOCK PDR 6

BGrimes P

'l ACRS(10)

I NRC Participants J

I Q

DL:yBj#

DL:0RB#5 DL:0RB#5 CJamersoF JClifford:tm JZwolinski l

ll/q/85' 6/1//85 ll / o /85 l

7.-

  • p ree UNITED STATES 8

~

7 g

NUCLEAR REGULATORY COMMISSION D

l WASHINGTON, D. C. 20.>55

% 4,,,+

November 12, 1985 Docket No. 50-29 LICENSEE: Yankee Atomic Electric Company FACILITY: Yankee Nuclear Power Station

SUBJECT:

-TRIP REPORT: MANAGEMENT REVIEW MEETING Two members of the NRC staff met with the project staff, plant personnel and senior management for the Yankee Nuclear Power Station (Yankee) on October 29 and 30, 1985. The trip was made to allow the NRC managers for Yankee in the proposed NRR organization to become familiar with the Yankee Atomic Electric Company. organization and operations.

Discussions held on October 29 covered the Yankee organization, on engineering improvements (both NRC mandated and plant betterments) going

, meetings with members of the Yankee staff, and tours of the computer and environmental monitoring facilities. An informal round-table discussion was held with senior management from the Yankee organization. General issues identified at this management discussion included timely completion of Systematic Evaluation Program open issues, consideration of licensing actions by accounting for plant unique characteristics, and completion of amendments fcr the current refueling outage.

A tour of the Yankee plant site was conducted October 30. Following the tour, the NRC staff met with members of the plant management'to discuss current operational and licensing concerns. Additionally, the impact of the SEP process and reviews on future licensing actions was discussed.

.hmWlO James W. Cli ford, Project Manager Operating Reactors Branch No. 5 Division of Licensing

Yankee Atomic Electric Company Yankee Nuclear Power Station cc:

Mr. James E. Tribble, President Yankee Atomic Electric Company 1671 Worcester Road Framingham, Massachusetts 01701 Thomas Dignan Esquire Ropes and Gray 225 Franklin Street Boston, Massachusetts 02110 Mr. N. N. St. Laurent Plant Superintendent Yankee Atomic Electric Company Star Route Rowe, Massachusetts 01367 Chainnan Board of Selectmen Town of Rowe Rowe, Massachusetts 01367 Resident Inspector Yankee Nuclear Power Station c/o U.S. NRC Post Office Box 28 Monroe Bridge, Massachusetts 01350 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, Pennsylvania 19406 Pobert M. Hallisey, Director P5diation Control Program Massachusetts Department of Public Health 150 Tremont Street, 7th Floor Boston, Massachusetts 02111 George Papanic, Jr.

Senior Project Engineer - Licensing Yankee Atomic Electric Company 1671 Worcester Road Framingham, Massachusetts 01701