| Site: | Washington Public Power Supply System |
| Issue date: | 12/21/1973 |
| From: | Stello V US ATOMIC ENERGY COMMISSION (AEC) |
| To: | Moore V US ATOMIC ENERGY COMMISSION (AEC) |
| References | |
| CON-WNP-0933, CON-WNP-933 NUDOCS 8605280438 | |
| Download: ML20198F206 (2) | |
Text
._
o kchet le DEC 21 1973 Docket fio. 50-460 Voss A. fhore, Assistant Director for LWR's Group 2. L RESPONSE 70 STAfsDARD REVIEW ASSIGNMENT - fiUCLEAR PROJECT tt3.1, REVIEW OF PSAR CilAPTERS 13 & 14 Applicant: Washington Public Power Supply System Licensing Stage: CP Branch & Project fianager Requesting Assistance: LWR 2-3. T. Cox Technical Review Branch Involved: L:03B Requested Cf.mpletion Date: 12/20/73 Review Statui: Q1 co:aplete The attached report contains an infomation request and position state-ment relative to our review of the subject SAR for transmittal to the applicant in accordance with the review schedule.
O*iniSignutyi Yleto. Sgeg3, Victor Stello, Jr., Assistant Director for Reactor Safety Directorate of Licensing
Enclosure:
As stated CC:
S. Ilanauer J. Hendrie A. Giambusso W. Mcdonald A. Schwencer T. Cox R. W. !!ouston C. R. Van Niel S. Varga DISTRIBUTION:
Docket 8605280438 731221 L Rdg.
PDR ADOCK 05000460 OSB Rdg.
A PDR Elva Leins g,
L:058 -
L:0SB/
.L:A@Rk CRVandieMic RWHouston VStello#
12'/20/73 12
_,,/_ /73 12/a//73 w misin su-om
.= can
'.='*******a
WPPSS Nuclear Project No. 1 Docket No. 50-460 13.0 Conduct of Operations 13.1 It appears from Figure 13.2-1 of your PSAR that no licensed operator candidates will be scheduled to complete the examination eligibility requirements to obtain their R0 license prior to fuel loading.
It is expected that your technical specifications will require a shift crew of not less than three licensed operators (including not less than one SRO) plus additional unlicensed personnel. Your training program should be sLcuctured so that sufficient licensed personnel will be available when the technical specifications are issued at the commence-ment of fuel loading.
13.2 Regulatory Guide 1.17, dated June 1973, identifies the regulatory position on protection against industrial sabotage which includes provisions for consideration and implementation during the design phase.
Indicate your position relative to conforming to the applicable Regulatory position, particularly Section C.3., and ANSI N18.17, Section 5.
In addition, provide a description of how you plan to implement these or equivalent provisions.
.