December 15, 1998 Mr. Garrett D. Edwards Director-Licensing, MC 62A-1 PECO Energy Company Nuclear Group Headquarters Correspondence Control Desk P.O. Box No.195 Wayne, PA 19087-0195
SUBJECT:
PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 - WITHDRAWAL OF A REQUEST FOR EXEMPTION FROM CERTAIN REQUIREMENTS OF 10 CFR PART 50,~ APPENDIX R, SECTION lil.G, " FIRE PROTECTION OF SAFE SHUTDOWN CAPABILITY"(TAC NOS. M98907 AND M98908)
Dear Mr. Edwards:
PECO Energy Company (the licensee), in its application dated May 22,1997, requested an exemption from certain provisions of 10 CFR Part 50, Appendix R, Section Ill.G, " Fire Protection of Safe Shutdown Capability." Specifically, the licensee requested exemption from the automatic fire suppression requirements stipulated by Section Ill.G.2.c for thirteen (13) fire areas located in the Peach Bottom Atomic Power Station (PBAPS), Units 2 and 3, Turbine Building and Control structure. In addition, the licensee requested affirmation of exemptions, previously granted in March 1985, for one (1) fire area in the Control Structure and two (2) fire areas in the Reactor Buildings.
Subsequently, by letter dated December 11,1998, the licensee withdrew the exemption request. Accordingly, the Commission has closed the associated TAC Nos. M98907 and M98908.
Sincerely, original signed by:
f8 22 Oo8[ M y77 Mohan C. Thadani, Senior Project Manager g
F PDR Project Directorate 1-2 Division of Reactor Projects -l/ll Office of Nuclear Reactor Regulation Docket Nos. 50-277 and 50-278 cc: See next page DISTRIBUTION Docket File OGC MBoyle PUBLIC ACRS
_PDI 2 Reading CAnderson, RGN-l lfO JZwolinski GHill(2)
RCapra GShear pgp r;n p' pr;""~" [??>((
1 MThadani MBoyle Ki E a '-
"b
MO'Brien(2)
_A/
[M n
OFFICE Pdb Pkhh PDI-2/D NAME bhadani:rb MO'Ekri_en RCapra "*
DATE 1%/ M98 h/h8 12./l8 /9 8 OFFICIAL RECORD COPY DOCUMENT NAME: PB98907.WDR 2100.21
...s-.~_.
psk m r o
+1 UNITED STATES sj j
NUCLEAR REGULATORY COMMISSION t
WASHINGTON, D.C. 20555-0001 g..... /
t December 15, 1998 Mr. Garrett D. Edwards Director-Licensing, MC 62A-1 PECO Energy Company Nuclear Group Headquarters Correspondence Control Desk P.O. Box No.195 Wayne, PA 19087-0195
SUBJECT:
PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 - WITHDRAWAL OF A REQUEST FOR EXEMPTION FROM CERTAIN REQUIREMENTS OF 10 CFR PART 50, APPENDIX R SECTION lli.G," FIRE PROTECTION OF SAFE SHUTDOWN CAPABILITY"(TAC NOS. M98907 AND M98908)
Dear Mr. Edwards:
)
PECO Energy Company (the licensee), in its application dated May 22,1997, requested an l
exemption from certain provisions of 10 CFR Part 50, Appendix R, Section Ill.G," Fire Protection of Safe Shutdown Capability " Specifically, the licensee requested exemption from the automatic fire suppression requirements stipulated by Section Ill.G.2.c for thirteen (13) fire areas located in the Peach Bottom Atomic Power Station (PBAPS), Units 2 and 3, Turbine i
Building and Control structure. In addition, the licensee requested affirmation of exemptions, previously granted in March 1985, for one (1) fire area in the Control Structure and two (2) fire areas in the Reactor Buildings.
Subsequently, by letter dated December 11,1998, the licensee withdrew the exemption request. Accordingly, the Commission has closed the associated TAC Nos. M98907 and M98908.
Sincerely, Mohan C. Thadani, Senior Project Manager Project Directorate 1-2 Division of Reactor Projects -l/11 Office of Nuclear Reactor Regulation Docket Nos. 50-277 and 50-278 cc: See next page
i t
l Mr. Garrett D. Edwards Peach Bottom Atomic Power Station, PECO Energy Company Units 2 and 3 i
cc:
l l
i J. W. Durtiam, Sr., Esquire Chief-Division of Nuclear Safety Sr. V.P. & General Counsel PA Dept. of PECO Energy Company Environmental Resources 2301 Market Street, S26-1 P.O. Box 8469 Philadelphia, PA 19101 Harrisburg, PA 17105-8469 PECO Energy Company ATTN: Mr. J. Doering, Vice President Board of Supervisors 1
Peach Bottom Atomic Power Station Peach Bottom Township 4
1848 Lay Road R.D.#1 Delta, PA 17314 Delta, PA 17314 i
j-PECO Energy Company Public Service Commission of Maryland i
ATTN: Regulatory Engineer, A4-5S Engineering Division
{
Peach Bottom Atomic Power Station Chief Engineer i
1848 Lay Road 6 St. Paul Centre Delta, PA 17314 Baltimore, MD 21202-6806 Resident inspector Mr. Richard McLean U.S. Nuclear Regulatory Commission Power Plant and Environmental Peach Bottom Atomic Power Station Review Division P.O. Box 399 Department of Natural Resources Delta, PA 17314 B-3, Tawes State Office Building Annapolis, MD 21401 Regional Administrator, Region i U.S. Nuclear Regulatory Commission Dr. Judith Johnsrud 475 Allendale Road National Energy Committee King of Prussia, PA 19406 Sierra Club 433 Orlando Avenue Mr. Roland Fletcher State College, PA 16803 Department of Environment 201 West Preston Street Manager-Financial Control & Co-Owner Baltimore, MD 21201 Affairs Pub!ic Service Electric and Gas A. F. Kirby, lil Company Extemal Operations - Nucleer P.O. Box 236 Delmarva Power & Light Company Hancocks Bridge, NJ 08038-0236 P.O. Box 231 Wilmington, DE 19899 Manager-Peach Bottom Licensing PECO Energy Company PECO Energy Company Nuclear Group Headquarters Plant Manager Correspondence Control Desk Peach Bottom Atomic Power Station P.O. Box No.195 1848 Lay Road Wayne, PA 19087-0195 Delta, PA 17314
._.