Submits Daily Highlight.Licensee Commenced Venting Preparatory to Inerting on 841212 & by 841213,oxygen Concentration in Drywell Less than 1%
ML20197J215
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 12/17/1984
From: Rajender Auluck
Office of Nuclear Reactor Regulation
To: Case E, Harold Denton, Edison G
Office of Nuclear Reactor Regulation
References
CON-WNP-0779, CON-WNP-779 NUDOCS 8412260369
Download: ML20197J215 (1)


Text

sc11 M Docket No.: 50-397 f1EMORANDUM FOR: H. Denton, NRR E. G. Case, NRR G. Edison, TOSB, NRR D. Eisenhut, DL F. Miraglia, DL T. Novak, DL H. Thompson, DHFS R. Vollmer, DE R. Bernero, DSI T. Speis, DST B. Snyder, TMIPO, NRR G. Holahan, ORA 8 D. Crutchfield, DL THRU: A. Schwencer, Branch Chief Licensing Branch No. 2 Division of Licensing FROM: R. Auluck, Project Manager Licensing Branch No. 2 Division of Licensing

SUBJECT:

DAILY HIGHLIGHT WNP-2 PLANT STATUS _ COMMERCIAL OPERATION (WNP-2)

On December 13, 1984, the Washington Public Power Supply System declared WNP-2 ready to begin commercial operation. The licensee commenced venting preparatory to inerting on December 12, 1984 and by late evening on December 13, 1984, the oxygen concentration in the drywell was less than 15.

g R. Auluck, Project Manager

" "9 "

8412260369 go b97

  • Division of Licensing e ADOCK O q C

L8#2 Reading EHylton RAuluck AD/L Technical Assistant (S. Black)

DL Director's Technical Assistant (J. Lyons)

L42%p LBF2/DL RAufuck:dh ASchwencer 12/ f 84 f 12/7/84