Letter Sequence Approval |
---|
|
|
MONTHYEARML20197H3941986-11-14014 November 1986 Submits Conclusions Re Review of Concerns Noted in to DG Eisenhut Re Response Time Testing of Turbine Stop Valve Closure,Reactor Scram & end-of-cycle Recirculation Pump Trip Functions at Facility Project stage: Approval 1986-11-14
[Table View] |
|
---|
Category:INTERNAL OR EXTERNAL MEMORANDUM
MONTHYEARML20217M5311999-10-25025 October 1999 Notification of 991103 Meeting with Util in Rockville,Md to Discuss Licensee Analytical Approach in Design of Pipe Supports at Plant ML20217C9051999-10-12012 October 1999 Forwards SER Input Approving License Request for Amend to Plant,Units 1 & 2.Licensee Proposal to Modify Definition of Core Alteration in Section 1.0 of TS & Update Sections 3/4.1,3.4.3 & 3/4.9 to Reflect Proposed Definition Change ML20211K8611999-09-0101 September 1999 Informs That There Has Been Some Confusion Re Recently Issued ODCM Generic Section Rev Which Needs to Be Clarified. Clarifications Are Listed ML20210P1361999-08-0404 August 1999 Notification of 990817 Meeting with Util in Rockville, Maryland to Discuss Status of Licensing Actions Submitted by Comm Ed & Plan for Proposed Licensing Workshop ML20237E3131998-08-26026 August 1998 Forwards for Public Release,Info Re NRC SMM Held on 980714-15.Summary of January 1998 NRC SMM & Watch List Removal Evaluation Factors Also Encl ML20237D9721998-08-11011 August 1998 Notification of Cancelled Licensee Meeting W/Util on 980903 to Discuss Effectiveness of Performance Improvement Initiatives & Progress Toward LaSalle Unit 1 Restart ML20237D9751998-08-11011 August 1998 Notification of Cancelled Licensee Meeting W/Util to Discuss Effectiveness of Performance Improvement Initiatives & Progress Toward LaSalle Unit 1 Restart ML20237D9821998-08-11011 August 1998 Notification of Licensee Meeting W/Util on 980915 to Discuss Status of LaSalle Unit 1 & Performance Improvement & Restart Plans for LaSalle Unit 2 ML20216H6971998-03-17017 March 1998 Notification of 980326 Meeting W/Commonwealth Edison Co in Lisle,Il to Discuss Comed Request to Consolidate near-site Emergency Operations Facility Into Single Central EOF ML20198N7961998-01-13013 January 1998 Confirms Rev to Time of NRC Oversight Panel Meeting for LaSalle County Station.Meeting Will Be Conducted on 980126 in Lisle,Il to Discuss Status & Effectiveness of Restart Plan Plant Performance Improvement Actions ML20197A8901997-12-16016 December 1997 Forwards Plant Restart Action Plan,For Review & Approval. Restart Action Plan Status Will Be Updated on as Required Basis ML20217D4261997-09-30030 September 1997 Informs of Scheduled Visits W/Nuclear Services at Gpu on Nov 14th & Visit at Commonwealth Edison on Dec 3rd & Would Like to Receive Any Info Available.Supporting Documentation Encl ML20211D6721997-09-15015 September 1997 Provides NRR Concurrence to Remove Big Rock Point from SALP Program,To Extend Current Point Beach SALP Cycle from 15 to 19 Months & to Extend Current LaSalle County Station SALP Cycle to Approx Six Months Following Restart of Either Unit ML20211D7661997-09-0303 September 1997 Informs of Intent & Rationale for Extending Current LaSalle County Station SALP Cycle to Approx Six Months Following Restart of Either Unit ML20217D5461997-04-18018 April 1997 Forwards Partially Withheld Background Briefing Package in Preparation for 970425 Meeting Between Comed & Commission IA-97-178, Forwards Partially Withheld Background Briefing Package in Preparation for 970425 Meeting Between Comed & Commission1997-04-18018 April 1997 Forwards Partially Withheld Background Briefing Package in Preparation for 970425 Meeting Between Comed & Commission ML20147J2391997-04-0909 April 1997 Notification of Meeting on 970416 W/Util in Rockville,Md to Discuss Overall Response & Present Addl Details Re Performance Indicators Used to Monitor Performance Stations ML20136C1031997-03-0606 March 1997 Forwards Correspondence Transmitted Via Internet to J Zwolinski from P Blanch During 970102-31.Requests Correspondence Be Placed in PDR ML20138J7671997-02-0505 February 1997 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licenseing Exam on 970409. Ltr W/Copy to Chief,Operator Licensing Branch Must Be Submitted to Listed Address in Order to Register Personnel ML20149M6901997-01-19019 January 1997 Notification of 970128 Meeting W/Commonwealth Edison Co to Discuss Licensee Proposed Program for Use of Mixed Oxide Fuel ML20134E8811996-12-27027 December 1996 Submits Dates Requested Re Plants ML20134E9141996-12-18018 December 1996 Discusses Highlights of Independent Self Assessment Exit Meeting ML20134E9071996-12-17017 December 1996 Submits Draft Highlights on Licensee Independent Self Assessment Exit Meeting & Decision to Extend Outages ML20134E8261996-12-16016 December 1996 Forwards Highlights from Exit Meeting for LaSalle Independent Safety Assessment ML20134E8401996-12-16016 December 1996 Discusses Highlights from LaSalle Independent Safety Assessment Exit Mtg ML20134E8581996-12-16016 December 1996 Forwards Highlights from Exit Meeting for LaSalle Independent Safety Assessment ML20210N4271996-12-0202 December 1996 Informs About Drop in Meeting on 961203 for Update on Industry Restructuring & Deregulation,Unicom Strategic Planning & Mixed Oxide Fuel ML20217D5421996-11-27027 November 1996 Forwards Partially Withheld Background Briefing Package in Preparation for 961203 Meeting Between Comed,Nuclear Strategic Services & Chairman Jackson ML20129J4781996-11-0404 November 1996 Summarizes 961030 Operating Reactors Events Briefing 96-14 Re Notification of Senior Managers from Commission,Oe,Aeod, Res,Nrr & Regional Offices of Selected Events That Occurred Since 961023 Briefing.List of Attendees Encl ML20210N3761996-08-12012 August 1996 Informs About Meeting on 960513 to Brief Chairman Jackson on Comed Response to Deregulation ML20217D4761996-07-31031 July 1996 Forwards Background Briefing Package in Prepartion of 960813 Meeting Between Commonwealth Edison Co & Chairman Jackson. Purpose of Visit to Discuss Recent Organizational Changes at Comed & Company Mgt Focus for Immediate Future ML20210N3381996-05-14014 May 1996 Discusses Courtesy Visit to Ceco on 960513 Re Listed Plants ML20210N2681995-11-13013 November 1995 Discusses Paritially Withheld Chairman Briefing by Ceco on 951116 ML20217D5321995-11-0909 November 1995 Forwards Partially Withheld Background Briefing Package in Preparation for 951116 Meeting Between Commission & Senior Comed Mgt.Purpose of Visit to Discuss Performance at Each of Sites & Challenges & Issues Needed to Be Addressed ML20210N3971995-10-12012 October 1995 Informs of Courtesy Visit on 951011 to Util to Discuss Listed Topics.List of Attendees Encl ML20210N3701995-10-0505 October 1995 Forwards Background Briefing Package in Preparation for 951011 Meeting W/Company Executives & Chairmam Jackson ML20134B5061994-04-13013 April 1994 Submits Plants Which Will Be Discussed in Categories Indicated Re Results of Screening Meetings for June 1994. Partially Deleted ML20059H2941994-01-21021 January 1994 Notification of Significant Licensee Meeting W/Util on 940201 in Lisle,Il to Discuss Failure to Take Prompt C/A for Hardened Grease in 4 Kv & 6.9 Kv Circuit Breakers Following 10CFR21 Notification & Oct 1992 Breaker Failure ML20058N4811993-12-15015 December 1993 Informs of Decision to Expand Senior Mgt Oversight of Selected Plants,Per Recent Meeting W/J Martin & H Miller. Lists Assignment of Managers,Effective Immediately IR 05000373/19930331993-11-23023 November 1993 Notification of 931130 Enforcement Conference in Region III Ofc to Discuss Fitness for Duty Issue as Discussed in Insp Repts 50-373/93-33 & 50-374/93-33 ML20062J4501993-10-27027 October 1993 Requests Addl Info Re Proposed EAL Changes in Util Generating Station Emergency Plan Annexes.Proposed EALs Reviewed Against Guidance in NUMARC/NESP-007,rev 2, Methodology for Development of Eals ML20059A4651993-10-20020 October 1993 Notification of Significant Licensee Meeting W/Util in Glen Ellyn,Il on 931104 to Review Status of Util Initiatives on QA & Corporate Engineering Support ML20057F2751993-10-13013 October 1993 Notification of 931021 Meeting W/Util in Rockville,Md to Discuss Util Mod to Address NRC Bulletin 93-03, Resolution of Issues Re Reactor Vessel Water Level Instrumentation in BWR, for Plant ML20057C9801993-09-27027 September 1993 Discusses 930927 Press Conference Re J O'Connor Announcement That Util Settled Six Rate Matters & Appeals Before Illinois Courts & Commerce Commission by Agreeing to Refund Listed Amount to Customers Over Next 12 Months ML20128E4961993-02-0505 February 1993 Notification of 930211 Meeting W/Util in Chicago,Il to Discuss Elimination of Operating Basis Earthquake Requirements for Pipe Ruptures ML20128C2901993-01-29029 January 1993 Notification of 930201 Meeting W/Licensee in Rockville,Md to Discuss Current Status of Licensing Activities at Plant ML20058K1361989-08-29029 August 1989 Lists Conclusions Reached at 890822 Meeting on Owners Group Improved Tech Specs,Including Surveillance Requirement 3.0.5 & pressure-temp Limits & Leakage Detection Sys ML20245C5871989-04-24024 April 1989 Notification of 890509 Meeting W/Util in Rockville,Md to Discuss Static O-Ring Differential Pressure Switches ML20245B6191989-04-15015 April 1989 Forwards Evaluation Rept Re BWR Overfill Events Resulting in Steam Line Flooding.All Events Included Reactor Depressurization Followed by Uncontrolled Condensate or Condensate Booster Pumps Injection or Both ML20245B7501989-04-15015 April 1989 Forwards Engineering Evaluation Rept on BWR Overfill Events Resulting in Flooding of Steam Lines.Potential for Equipment Damage Believed to Exist & Any Damage Occurring Should Be Fixed Prior to Restart 1999-09-01
[Table view] Category:MEMORANDUMS-CORRESPONDENCE
MONTHYEARML20217M5311999-10-25025 October 1999 Notification of 991103 Meeting with Util in Rockville,Md to Discuss Licensee Analytical Approach in Design of Pipe Supports at Plant ML20217C9051999-10-12012 October 1999 Forwards SER Input Approving License Request for Amend to Plant,Units 1 & 2.Licensee Proposal to Modify Definition of Core Alteration in Section 1.0 of TS & Update Sections 3/4.1,3.4.3 & 3/4.9 to Reflect Proposed Definition Change ML20211K8611999-09-0101 September 1999 Informs That There Has Been Some Confusion Re Recently Issued ODCM Generic Section Rev Which Needs to Be Clarified. Clarifications Are Listed ML20210P1361999-08-0404 August 1999 Notification of 990817 Meeting with Util in Rockville, Maryland to Discuss Status of Licensing Actions Submitted by Comm Ed & Plan for Proposed Licensing Workshop ML20237E3131998-08-26026 August 1998 Forwards for Public Release,Info Re NRC SMM Held on 980714-15.Summary of January 1998 NRC SMM & Watch List Removal Evaluation Factors Also Encl ML20237D9721998-08-11011 August 1998 Notification of Cancelled Licensee Meeting W/Util on 980903 to Discuss Effectiveness of Performance Improvement Initiatives & Progress Toward LaSalle Unit 1 Restart ML20237D9751998-08-11011 August 1998 Notification of Cancelled Licensee Meeting W/Util to Discuss Effectiveness of Performance Improvement Initiatives & Progress Toward LaSalle Unit 1 Restart ML20237D9821998-08-11011 August 1998 Notification of Licensee Meeting W/Util on 980915 to Discuss Status of LaSalle Unit 1 & Performance Improvement & Restart Plans for LaSalle Unit 2 ML20216H6971998-03-17017 March 1998 Notification of 980326 Meeting W/Commonwealth Edison Co in Lisle,Il to Discuss Comed Request to Consolidate near-site Emergency Operations Facility Into Single Central EOF ML20198N7961998-01-13013 January 1998 Confirms Rev to Time of NRC Oversight Panel Meeting for LaSalle County Station.Meeting Will Be Conducted on 980126 in Lisle,Il to Discuss Status & Effectiveness of Restart Plan Plant Performance Improvement Actions ML20197A8901997-12-16016 December 1997 Forwards Plant Restart Action Plan,For Review & Approval. Restart Action Plan Status Will Be Updated on as Required Basis ML20217D4261997-09-30030 September 1997 Informs of Scheduled Visits W/Nuclear Services at Gpu on Nov 14th & Visit at Commonwealth Edison on Dec 3rd & Would Like to Receive Any Info Available.Supporting Documentation Encl ML20211D6721997-09-15015 September 1997 Provides NRR Concurrence to Remove Big Rock Point from SALP Program,To Extend Current Point Beach SALP Cycle from 15 to 19 Months & to Extend Current LaSalle County Station SALP Cycle to Approx Six Months Following Restart of Either Unit ML20211D7661997-09-0303 September 1997 Informs of Intent & Rationale for Extending Current LaSalle County Station SALP Cycle to Approx Six Months Following Restart of Either Unit ML20217D5461997-04-18018 April 1997 Forwards Partially Withheld Background Briefing Package in Preparation for 970425 Meeting Between Comed & Commission IA-97-178, Forwards Partially Withheld Background Briefing Package in Preparation for 970425 Meeting Between Comed & Commission1997-04-18018 April 1997 Forwards Partially Withheld Background Briefing Package in Preparation for 970425 Meeting Between Comed & Commission ML20147J2391997-04-0909 April 1997 Notification of Meeting on 970416 W/Util in Rockville,Md to Discuss Overall Response & Present Addl Details Re Performance Indicators Used to Monitor Performance Stations ML20136C1031997-03-0606 March 1997 Forwards Correspondence Transmitted Via Internet to J Zwolinski from P Blanch During 970102-31.Requests Correspondence Be Placed in PDR ML20138J7671997-02-0505 February 1997 Informs That NRC Plans to Administer Generic Fundamentals Exam Section of Written Operator Licenseing Exam on 970409. Ltr W/Copy to Chief,Operator Licensing Branch Must Be Submitted to Listed Address in Order to Register Personnel ML20149M6901997-01-19019 January 1997 Notification of 970128 Meeting W/Commonwealth Edison Co to Discuss Licensee Proposed Program for Use of Mixed Oxide Fuel ML20134E8811996-12-27027 December 1996 Submits Dates Requested Re Plants ML20134E9141996-12-18018 December 1996 Discusses Highlights of Independent Self Assessment Exit Meeting ML20134E9071996-12-17017 December 1996 Submits Draft Highlights on Licensee Independent Self Assessment Exit Meeting & Decision to Extend Outages ML20134E8261996-12-16016 December 1996 Forwards Highlights from Exit Meeting for LaSalle Independent Safety Assessment ML20134E8401996-12-16016 December 1996 Discusses Highlights from LaSalle Independent Safety Assessment Exit Mtg ML20134E8581996-12-16016 December 1996 Forwards Highlights from Exit Meeting for LaSalle Independent Safety Assessment ML20210N4271996-12-0202 December 1996 Informs About Drop in Meeting on 961203 for Update on Industry Restructuring & Deregulation,Unicom Strategic Planning & Mixed Oxide Fuel ML20217D5421996-11-27027 November 1996 Forwards Partially Withheld Background Briefing Package in Preparation for 961203 Meeting Between Comed,Nuclear Strategic Services & Chairman Jackson ML20129J4781996-11-0404 November 1996 Summarizes 961030 Operating Reactors Events Briefing 96-14 Re Notification of Senior Managers from Commission,Oe,Aeod, Res,Nrr & Regional Offices of Selected Events That Occurred Since 961023 Briefing.List of Attendees Encl ML20210N3761996-08-12012 August 1996 Informs About Meeting on 960513 to Brief Chairman Jackson on Comed Response to Deregulation ML20217D4761996-07-31031 July 1996 Forwards Background Briefing Package in Prepartion of 960813 Meeting Between Commonwealth Edison Co & Chairman Jackson. Purpose of Visit to Discuss Recent Organizational Changes at Comed & Company Mgt Focus for Immediate Future ML20210N3381996-05-14014 May 1996 Discusses Courtesy Visit to Ceco on 960513 Re Listed Plants ML20210N2681995-11-13013 November 1995 Discusses Paritially Withheld Chairman Briefing by Ceco on 951116 ML20217D5321995-11-0909 November 1995 Forwards Partially Withheld Background Briefing Package in Preparation for 951116 Meeting Between Commission & Senior Comed Mgt.Purpose of Visit to Discuss Performance at Each of Sites & Challenges & Issues Needed to Be Addressed ML20210N3971995-10-12012 October 1995 Informs of Courtesy Visit on 951011 to Util to Discuss Listed Topics.List of Attendees Encl ML20210N3701995-10-0505 October 1995 Forwards Background Briefing Package in Preparation for 951011 Meeting W/Company Executives & Chairmam Jackson ML20134B5061994-04-13013 April 1994 Submits Plants Which Will Be Discussed in Categories Indicated Re Results of Screening Meetings for June 1994. Partially Deleted ML20059H2941994-01-21021 January 1994 Notification of Significant Licensee Meeting W/Util on 940201 in Lisle,Il to Discuss Failure to Take Prompt C/A for Hardened Grease in 4 Kv & 6.9 Kv Circuit Breakers Following 10CFR21 Notification & Oct 1992 Breaker Failure ML20058N4811993-12-15015 December 1993 Informs of Decision to Expand Senior Mgt Oversight of Selected Plants,Per Recent Meeting W/J Martin & H Miller. Lists Assignment of Managers,Effective Immediately IR 05000373/19930331993-11-23023 November 1993 Notification of 931130 Enforcement Conference in Region III Ofc to Discuss Fitness for Duty Issue as Discussed in Insp Repts 50-373/93-33 & 50-374/93-33 ML20062J4501993-10-27027 October 1993 Requests Addl Info Re Proposed EAL Changes in Util Generating Station Emergency Plan Annexes.Proposed EALs Reviewed Against Guidance in NUMARC/NESP-007,rev 2, Methodology for Development of Eals ML20059A4651993-10-20020 October 1993 Notification of Significant Licensee Meeting W/Util in Glen Ellyn,Il on 931104 to Review Status of Util Initiatives on QA & Corporate Engineering Support ML20057F2751993-10-13013 October 1993 Notification of 931021 Meeting W/Util in Rockville,Md to Discuss Util Mod to Address NRC Bulletin 93-03, Resolution of Issues Re Reactor Vessel Water Level Instrumentation in BWR, for Plant ML20057C9801993-09-27027 September 1993 Discusses 930927 Press Conference Re J O'Connor Announcement That Util Settled Six Rate Matters & Appeals Before Illinois Courts & Commerce Commission by Agreeing to Refund Listed Amount to Customers Over Next 12 Months ML20128E4961993-02-0505 February 1993 Notification of 930211 Meeting W/Util in Chicago,Il to Discuss Elimination of Operating Basis Earthquake Requirements for Pipe Ruptures ML20128C2901993-01-29029 January 1993 Notification of 930201 Meeting W/Licensee in Rockville,Md to Discuss Current Status of Licensing Activities at Plant ML20058K1361989-08-29029 August 1989 Lists Conclusions Reached at 890822 Meeting on Owners Group Improved Tech Specs,Including Surveillance Requirement 3.0.5 & pressure-temp Limits & Leakage Detection Sys ML20245C5871989-04-24024 April 1989 Notification of 890509 Meeting W/Util in Rockville,Md to Discuss Static O-Ring Differential Pressure Switches ML20245B6191989-04-15015 April 1989 Forwards Evaluation Rept Re BWR Overfill Events Resulting in Steam Line Flooding.All Events Included Reactor Depressurization Followed by Uncontrolled Condensate or Condensate Booster Pumps Injection or Both ML20245B7501989-04-15015 April 1989 Forwards Engineering Evaluation Rept on BWR Overfill Events Resulting in Flooding of Steam Lines.Potential for Equipment Damage Believed to Exist & Any Damage Occurring Should Be Fixed Prior to Restart 1999-09-01
[Table view] |
Text
S
'. .~ . j .-
..no! I puau -
/ o g UN11 ED STATES E,} g NUCLE AR REGULATORY COMMISSION
'4 -l W ASHINGTON,0. C. 20655 l k.....,/ /lft l MEMORANDUM FOR: C. E. Norelius Director l Division of Reactor Projects. Region III FROM: R. Bernero, Director Division of BWR t.icensing, NRR
SUBJECT:
TO RESOLVE ISSUES 9 ELATIVE TO SCRAM RESPONSE TIME TESTING FOR LASfLLE COUNTY NUCLEAR STATION AND POSSIBLE
, INDUSTRY WIDE CONCERNS IN THIS AREA (TAC No. 57194, TIA NO. 83-52) i Your letter dated April 22, 1983 to D. G. Eisenhut raises concerns regarding i response time testing v. Turbine Stop Valve Closure 'TSVC), reactor scram and End-of-Cycle Recirculatien Pump Trip (E0C-RPT) functions at LaSalle Nuclear Power Station. Due to the NRR re-organization, this request which was originally issued to ICSB in DS!, in May 1983 was recently transferred to E!CSB/ DBL for necessary action.
E!CSB/ DBL, has reviewed the concerns raised by you and has concluded the following: .
Technical Specification 1.33 defines the reactor protection system response time as the time interval from when the monitored parameter exceeds its trip set point at the channel sensor until de-energization of the scram pilot valve solenoids. The channel sensor for turbine stop valve closure (TSVC) function is its limit switch. The same limit switch which initiates the TSVC scram also . initiates the TSVC EOC-RPT. The actual measurement of response time of the limit switch is not practicable as this test is done during the refueling outage when the turbine stop valves are fully closed and thus the limit switch in the RPS circuitry is open. In order to do RPS response time of TSVC, the licensee has installed a test switch in parallel with the limit switch to simulate the limit switch function and allows 10 ms for the response time of the limit switch. Table 3.3.1-2 of Technical Specifications specifies the response time of TSVC to be 60 ms and the records kept by the licensee show the average response time of TSVC as 48 ms. The licensee states that General Electric has conducted tests for similar type limit switches and the response time of those limit switches was consistently found to be in the range of 0-1 ms. Therefore, we believe that the response time of the test switch conservatively models the response time of the limit switch.
Based on the above, we conclude that the current method of performing the response time verification test for TSVC at LaSalle is reasonable and will provide CONTACT: N. Trehan EICSB/ DBL X27589 3 . '3 M 9812140074 981204-PDR FOIA GRABER99-41 PDR
2 HON 14 $6 adequate assurance that scram responsa timo for this function is within technical specification limit.
This closes TAC 57194 and TIA 83-52.
cn;:- /
, ;g a~......., .
R. Bernero. Director i
Division of BWR Licensing l
Office of'Huclear Reactor Regulation cc: E. Jordan IE G. Lainas M. Srinivasan G. Holahan E. Adensam A. Bournia N. Trehan ,
DISTRI6UTION Central Files EICSB R/F RBernero DVassallo
- See previous concurrence g i n
E!CSB: DBL
- AD R: DBL Al 1 EICSB: DBL ,
A'NTrehan:vjb MSrinivasan DVassallo ,
GL nas , rnero ll /i2./86 11/ 5/86 11/ 7 /86 ,/ /86 ag/tf /86