Text
.
BOSTON EDISON COMPANY BOO BoYLsTON 57REET BOSTON. MAssACHusErrs 02199 WILLIAM D. HARRINGTON s4meon vece passios=,
nuo6 san BECo Ltr. #86-063 May 15, 1986 Mr. John A. Zwolinski, Director BHR Project Directorate #1 Division of Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D. C.
20555 License DPR-35 Docket 50-293 Ref. 1) Long Term Plan - January 1986, dated 3/24/86
- 2) Confirmatory Action Letter No. 86-10, dated 4/12/86
Dear Sir:
This letter is to inform you of potential slippage in dates provided in Boston Edison's Long Term Program, (Ref. 1) and the rescheduling of Refueling Outage
- 7.
A number of unscheduled short maintenance outages and a relatively long unscheduled maintenance outage (Ref. 2) have impacted our schedules.
The impact of these outages has been amplified by various job actions by the contract labor force employed at Pilgrim.
These job actions could not have been anticipated by Boston Edison, and have resisted timely remedy.
Th1 most immediately imperilled commitment is that of the extended test program for hydrogen injection.
This was to begin May 31, 1986.
The above events have delayed this, and we are unable to provide a new date at this time.
In addition to the contract labor job actions, the potential exists for a job action by Boston Edison employees who are members of the three collective bargaining units associated with us.
This may begin at the expiration of the current contract at midnight of May 15, 1986.
Naturally, a job action by Boston Edison employees would have a major affect on all schedules and commitments previously provided to you.
If00 8605190096 860515 tiI PDR ADOCK 05000293 lO P
pm
BOSTON EDISON COMPANY Mr. John A. Zwolinski, Director Page 2 We cannot accurately forecast the impact of these events; currently we believe RF0 #7 will begin in October, 1986.
However, it may be desirable to delay commencement of the refueling outage until January, 1987. We will, of course, keep you informed of any significant development and apprise you of our new schedule when it can be accurately formulated.
Very truly yours, K
William D. Harrington PMK/kmc cc: Dr. Thomas E. Murley Regional Administrator Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Region I 631 Park Avenue King of Prussia, PA 19406 4