Informs That Util Will Not Be Able to Provide Response to RAI Re Review of IPEEE within 60 Days Due to Unavailablity of HCLPF Calculations.Response to All Questions in RAI Will Be Provided by Apr 1998
ML20197G330
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 12/22/1997
From: Hunger G
PECO ENERGY CO., (FORMERLY PHILADELPHIA ELECTRIC
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9712300435
Download: ML20197G330 (1)


Text

-_

Stat 6on Support Department j

s,,,,

cf.5fp 10CFR50.54(f) y PECO NUCLEAR n w r c-as creuwtmo stoww.ro A Unit of PECO Energy ware a wount December 22,1997 Docket Nos. 50-277 50-278 License Nos. DPR-44 DPR 56 U. S. Nucles Regulatory Commission ATTN: Docen;snt Control Desk Washington,DC 20555

SUBJECT:

Peach Bottom Atomic Power Station, Units 2 and 3 Response to Request for Additional Information Regarding Review of Individual Plant Examination of Extemal Events

Dear Sir:

Your Request for Additional Information (RAI) which was transmitted by letter dated November 12,1997, requested a response within 60 days. We are unable to provide a response within 60 deys, i.e., by January 12,1998. The high confidence in low probability of failure (HCLPF) calculations requested by seismic analysis questions 1,2 and 7 will not be available until

)

sometime after January 12,1998. PECO Energy Company (PECO Energy) proposes to provide a response to all questions in your RAI by April,1998. This schedule provides sufficient time for p

PECO Energy to receive and to review HCLPF calculations and incorporate them into a complete and accurate response is the RAI.

If you have any questions, please contact us.

Sincerely,

[.f,)[f

<A,

G. A. Hunger, Jr../

Director Licensing cc:

H. J. Miller, Administrator, Region I, USNRC A. -

Murtray, USNRC Senior Resident inspector, PBAPS 9712300435 971222 PDR ADOCK 05000277 l.liI.lll.lll.!!. Il.Ii.i