Submits Daily Highlight.On 840111,LaSalle Unit 2 Completed Fuel Loading.Wppss Unit 2 Completed Fuel Loading on 840112. Initial Criticality Projected for 840301 for Both Facilities
ML20197G215
Person / Time
Site: Columbia, LaSalle, 05000000
Issue date: 01/17/1984
From: Rajender Auluck, Bournia A
Office of Nuclear Reactor Regulation
To: Carter J, Case E, Harold Denton
Office of Nuclear Reactor Regulation
References
CON-WNP-0724, CON-WNP-724 NUDOCS 8401250004
Download: ML20197G215 (1)


Text

, _ -

k -l _.

7 '

January 17, 1984

.cr

' Doc ket No s. :

50-374 and 50-397 f4ENORANDUM FOR:

H. R. Denton, NRR E. G. Case, NRR J. Carter, NRR D. G. Eisenhut, DL R. A. Purple, DL H. Thompson, DHFS R. Vollmer, DE R. Mattson, DSI T. Speis, DST J. Sniezek, IE G. Holahan, ORAB T. Novak, DL F. Miraglia, DL THRU:

A. Schwencer, Chief Licensing Branch No. 2 Div.ision of Licensing FROM:

R. Auluck, Project Manager A. Bournia, Project Manager Licensing Branch No. 2 Licensing Branch No. 2 Division of Licensing Division of Licensing

SUBJECT:

DAILY HIGHLIGHT - FUEL LOADING SCHEDU' 5 -

LA SALLE, UNIT 2 AND WNP-2 La Salle, Unit 2 Fuel loading, which started. on December 30, 1983, was completed on January 11, 1984, at 10:00 am CST.

The licensee is projecting March 1,1984, as the most probable initial criticality date, and ready to exceed;5 percent power on March 15, 1984.

WNP-2 Fuel loading, which started on December 25, 1983, was completed on January 12, 1984, at 5:15 pm PST.

The licensee expects. initial criticality on March 1,1984 and ready to exceed five (5) percent power on March 10, 1984.

b

%W' R. Auluck, Project Manager A. Bournia, Project Manager Licensing Branch No. 2 Licensing Branch No. 2 Division of Licensing Division of Licensing 14