Forwards Changes to Initial Test Program,Per License Condition 2.C(4) & 10CFR50.49,including All Changes Made for 860905-1017
ML20197C053
Person / Time
Site: Perry 
Issue date: 10/21/1986
From: Edelman M
CLEVELAND ELECTRIC ILLUMINATING CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
PY-CEI-OIE-0249, PY-CEI-OIE-249, NUDOCS 8610310170
Download: ML20197C053 (4)


Text

.

b m e.

f THE CLEVELAND ELECTR P.O. BOX 5000 - CLEVELAND. OHIO 44101 - TELEPHONE (216) 622-9800 - lLLUMINATING BLOG - 55 PUBLICSOUARE Serving The Best Location in the Nation MURRAY R. EDELMAN FRICRIlfY ROUTIES SR VCE PRESCENT (Qg gpg NUCLE A R A ' F RC DlLiid

  • ['h-%f October 21, 1986 PY-CEI/01E-0249 L frg>s qt OMA Ol~

PA0 FILE F Mr. James G. Keppler Director, Region III Office of Inspection and Enforcement U.S.

Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137 Perry Nuclear Power Plant Docket No. 50-440 Report of 10 CFR 50.59 Changes to the Initial Test Program

Dear Mr. Keppler:

Enclosed is a report of changes to the Initial Test Program made in accordance with Operating License Condition 2.C(4) and 10 CFR 50.59.

This report includes all such changes made since September 5, 1986 through October 17, 1986.

If you have any questions, please feel free to call.

Very trul us, Murray R. Ede an Senior Vice President Nuclear Group MRE:njc Enclosure cc:

J. M. Taylor (39)

H. R. Denton J. Stefano J. Silberg K. A. Connaughton Document Control Desk (USNRC) 8610310170 861021 ADOCK 0500 0

yDR 3g Ist i Ih(

M Attachment

~

PY-CEI/0IE-0249 L SAFETY EVALUATION MONTHLY

SUMMARY

~

1.

GENERAL INFORMATION FINAL APPROVAL FSAR DOCUMENT DATE SECTION STI-025B 09/24/86 TABLE 14.2-2 II.

DESCRIPTION This safety evaluation was performed to evaluate a dif ference between STI-B21-025B, Rev. 2, Full Reactor Isolation and FSAR Table 14.2-2, Startup Tests.

FSAR Table 14.2-2 states that the Startup Test Instruction is performed in Test Condition 6.

The STI has been changed to perform testing in Test Condition 8.

Test Conditions 7 and 8 were added to FSAR Figure 14.2-4 to reflect additional testing along the licensed Icad line at low and high flow conditions (see PY-CEI/01E-0231 L, dated August 28, 1986).

(

FSAR Table 14.2-2 will be changed to indicate performance of the MSIV Functional Test in Test Condition 8.

SSER 8 Section 15.1 approved operation in this extended operating I

domain for plant startup testing.

III.

SUMMARY

A change is required in Table 14.2-2 to reflect a change in test conditions required for testing in the Maximum Extended Operating Domain (MEOD) to comply with the latest GE Test Specifications.

1 15 1

.m 4

Attachment

[.

PY-CEI/0IE-0249 L SAFETY EVALUATION MONTHLY

SUMMARY

i I.

GENERAL INFORMATION FINAL APPROVAL FSAR DOCUMENT DATE SECTION STI-029B 09/24/86 14.2.12.2.26, TABLE 14.2-2 1

i II.

DESCRIPTION

.This safety evaluation was performed to evaluate a difference between STI-B21-029B, Rev. 2, Recirculation Flow Control and the FSAR Section 14.2.12.2.26.2 and Table 14.2-2, Startup Tests.

FSAR Section 14.2.12.2.26.2 states that the Startup Test Instruction is performed along the 100% tod line. The STI has been changed to perform testing along the bounding licensed load line.

FSAR Table 14.2-2 states that the Startup Test Instruction is performed in Test Condition 3 and 6.

The STI has been changed to perform testing in Test Conditions 3, 6, and 8.

j Test Conditions 7 and 8 were added to FSAR Figure 14.2-4 to reflect additional testing along the licensed load line at low and high flow

+

conditions (see PY-CEI/0IE-0231 L, dated August 28, 1986).

FSAR Section 14.2.12.2.26.2 and Table 14.2-2 will be changed to indicate testing of the Recirculation Flow Control along the bounding licensed load line and in Test Conditions 3, 6, and 8.

4 l

SSER 8 Section 15.1 approved operation in this extended operating domain for plant startup testing.

i i

i III.

SUMMARY

A change is required in FSAR Section 14.2.12.2.26.2 and Table 14.2-2 to reflect additional test conditions required for testing in the i

Maximum Extended Operating Domain (MEOD) to comply with the latest GE Test Specifications.

l 1

i 2

_ _ __.__.-_ _ _. _ _ _ _ _ =, - _ _ _ _.

.. 3;2%W"W ~ "

'^~

~

^~

~

' ~ ~ ~ ~ '

Attachment PY-CEI/01E-0249 L SAFETY EVALUATION MONTHLY

SUMMARY

I.

GENERAL INFORMATION FINAL APPROVAL FSAR DOCUMENT DATE SECTION

p. ~ _.

STI-030C 09/24/86 TABLE 14.2-2

- * ~:

II.

DESCRIPTION This safety evaluation was performed to evaluate a difference between STI-B21-030C, Rev. 2, Recirculation System Performance and the FSAR Table 14.2-2, Startup Tests.

FSAR Table 14.2-2 states that the Startup Test Instruction is performed in Test Condition 2, 3, 4, and 6.

The STI has been changed to perform testing in Test Conditions 2, 3, 4, 6, and 8.

Test Conditions 7 and 8 were added to FSAR Figure 14.2-4 to reflect additional testing along the licensed load line at low and high flow coaditions (see PY-CEI/01E-0231 L, dated August 28, 1986).

FSAR Table 14.2-2 will be changed to indicate performance of the Recirculation System Performance Test in Test Conditions 2, 3, 4, 6, and 8.

SSER 8 Section 15.1 approved operation in this extended operating domain for plant startup testing.

III.

SUMMARY

A change is required in FSAR Table 14.2-2 to reflect additional test conditions required for testing in the Maximum Extended Operating Domain (MEOD) to comply with the latest GE Test Specifications.

3