ss p gfp, 0 6 1993 Applied Management Systems, Inc.
Attn: Margaret Hutchison 6116 Executive Boulevard - Suite 440 Rockville, MD 20852
Dear Ms. Hutchison:
Subject:
Modification No 4 To Task Order No. 8 Under Contract No. NRC-33-92-203 The subject task order expired on September 30,1993, and we are initiating closeout action.
However, pending completion of all required closeout requirements, it is necessary to deobligate excess funds remaining under this contract for other immediate agency requirements, Therefore, this modification is issued to deobligate unexpended funds in the A
amount of S644,92 which thereby decreases the obligated amount of this task order from
$207,702.57 to $207,057.65.
Accordingly the first sentence of the fourth paragraph of this task order definitization letter dated September 21,1992, is hereby deleted in its entirety and the following substituted in lieu thereof:
"The amount presently obligated with respect to this task order is $207,057.65 of which
$198,903.80 represents the total estimated reimbursable cot,ts and the amount of $8,153.85 represents the fixed fee."
All other terms and conditions of this task order remain unchanged.
Appropriation Data for this Modific.ation No. 4 to Task Order No. 8 is as follows:
APPN Nou 31X0200.310 B&R No.:
310-20-615-202 FIN No.:
D1391 Deobligated Amount:
$644.92 BOC:
2542 4
A summary of obligations for this task order, from award date through the date of this action is given below.
Totti FY92 Obligation Amount:
$178,000.00 Total FY92 Deobligation Amount:
$ 4,297.43 Total FY93 Obligation Amount:
$ 34,000.00 Total FY93 Deobligation Amount:
644.92 Cumulative Total of NRC Obl%ations:
$207,057.65
()
ea 9803110288 90C306 PDR CONTR NRC-33-93-203 PDR A r?.
,.7 kJ/\\j ! I -'
g
NRC-33-92-203 Task Order No. 8 Modification No. 4 Page 2 of 2 Please have an appropriate official sign all three (3) copies and retum two (2) copies to the aoaress below within ten (10) days from date of this letter. You should retain one (1) fully executed copy for your files U. S Nuclear Regulatory Commission Division of Contracts and Property Management Office of Administration CLOSEOUT, MS T-712 Washington, D C 20555 In addition, please complete the enclosed Property Certification form as well as the reports required by the clauses on the contract related to Patents, Copyrights and Royalties and return them to the above mentioned address if negative reports are appropriate, statements to that effect are required.
You are also requested to complete the enclosed forms regarding Final Release, General Assignments and Certification of proceeds from refunds, rebates, credits and other amounts as required by the cortract.
When the final cost determination has been,made, you will be notified and asked to submit your finalinvoice if you have any questions or need further information regarding the subject modification, please centact Edna Knox-Davin, Contract Specialist on (301) 415-6577.
Sincerely, Sharon D. Mearse, Contracting Officer Contract Management Branch 3 Division of Contracts and Property Management Office of Administration
Enclosures:
As stated ACCEPTANCE:
NAME:
TITLE:
DATE:
Distributiort EKDavin CMB3 r/f Closecut Contract File DCPM r/f JBurton. PO J Cucura Kim Parrott DCD PDR ACCTG Document Name:P-\\close\\203TO8M4 OFFICE DCPM/CMB3 DCPM/CMB3 i,
NAME EKnox Davinj SQNdrsh DATE
$ [ /98 b /t/98 OFFICIAL RECORD C OPY l