Center for Nuclear Waste Regulatory Analyses 6220 CULEBRA ROAD a P.O. DRAWER 28510
- SAN ANTONIO, TEXAS. U.S.A. 78228-0510 (210) 522 5160
- FAX (210) 522-5155 March 26,1999 Contract No. NRC-02-97-009 Account No. 20-1402-158 U.S. Nuclear Regulatory Commission Attn: Mr. John J. Linehan, Director j
Office of Nuclear Material Safety and Safeguards Program Management, Policy Development and Analysis Staff Mail Stop 8-A23 Washington, DC 20555
Subject:
CNWRA Program Manager's Periodic Report on Activities of the Center for Nuclear Waste Regulatory Analyses for Period 6--FY1999
Dear Mr. Linehan:
The enclosed " Program Manager's Periodic Report"(PMPR) documents the progress and financial status of the Center for Nuclear Waste Regulatory Analyses for the period February 13-March 12,1999. Its contents comply with the requirements of section F.1.5 of the referenced contract. A diskette containing the PMPR in Wordperfect 8 format is also enclosed.
Cost variance analyses are pr ovided for the Division of Waste Management (D1035), Tank Waste Remediation System (J5164), Three Mile Island Unit 2 Independent Spent Fuel Storage Installation (15186), Dry Transfer System (J5206), Centralized Interim Storage Facility (D1035), Private Fuel Storage Facility (J5226), and Savannah River Site Aluminum-Based Spent Fuel (J5210) Job Codes, as well as for composite spending on this contract. All variances are expressed with regard to the current operations plans.
During period 6, three new intermediate milestones were introduced and six schedule changes were made as reflected in table 2. Six deliverables were transmitted as indicated in table 3.
j Please contact me or Mr. Henry Garcia if you have questions regarding this re rt.
/
Sincer ours
[ $['f
-d' f
f\\/lf) b Wesley C. Pat k Presidcat
[
g I [l HFG/lg Enclosures cc:
B. Meehan J. Greeves S. Shankman C. Paperiello J. Holonich S. Bahadur D. DeMarco E. Ten Eyck M. Federline B. Stiltenpole (38)
J. Piccone CNWRA Directors / Element Managers E. Brach F. Miraglia S. Boyanowski (SwRI Contracts) 9904020191 990326
(
i MO PDR WASTE 9
l Washington Office
- Twinbrook Metro Plaza. #210 *12300 Twinbrook Parkway
- Rockville. Maryland 20852-1606 1
, g 'gk) (f._6 (lf*//,h (?l/l[ f,6If N N lfEOV' b f bDW/
b bli kf