i November 30, 1998 Mr. Oliver'D. Kingsley, President -
Nuclear Generation Group Commonwealth Edison Company Executive Towers West ill I
r l
1400 Opus Place, Suite 500 L
Downers Grove, IL 60515 l
~
l
SUBJECT:
RELIEF REQUESTS CR-21, CR-22, CR-23 AND CR-24: IMPLEMENTATION l_
OF ASME, SECTION XI, SUBSECTION IWE, FOR CONTA!NMENT INSPECTION (TAC NOS. MA2257 AND MA2258)
Dear Mr. Kingsley:
-By letter dated July 2,1998, as supplemented on September 3,1998, Commonwealth Edison
- Company (Comed) submitted Relief Request Nos. CR-21, CR-22, CR-23 and CR-24 seeking relief from some of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (Code),Section XI, Subsection IWE, requirements for Quad Cities Nuclear Power
[
Station,' Units 1 and 2. The September 3,1998, letter withdrew relief request CR-22.
The NRC staff, with assistance from our contractor Idaho National Engineering and
. Environmental Laboratory (INEEL), has reviewed and evaluated the requests for relief submitted for Quad Cities. The NRC staff adopts the evaluations and conclusions contained in the Technical Letter Report (TLR) prepared by INEEL. The enclosed Safety Evaluation (SE)
I
- incorporates the TLR (attached) and its findings.
i Based on the above information, the staff concluded that for Rel;ef Requests CR-21 and CR-24, the proposed altematives provide an acceptable level of quality and safety and are authorized
. pursuant to 10 CFR 50.55a(a)(3)(i). For Relief Request CR-23, the proposed alternative provides reasonable assurance of structural integrity of containment repairs and replacements, and compliance with the Code requirement would result in hardship without a compensating increase in the level of quality and safety. Therefore, the proposed alternative is authorized J
pursuant to 10 CFR 50.55a(a)(3)(ii).
This completes the review of the subject relief requests and closes TAC Nos. MA2257 and l
MA2258.
Sincerely, 9812030001 981130 a.
PDR ADOCK 05000254
- b
'0 RIG. SIGNED BY:
Stuart A. Richards, Director i
Ej@f kf hh
\\,
Project Directorate ill-2 IdaJ 13 L Division of Reactor Projects - lililV Office of Nuclear Reactor Regulation Docket Nos. 50-254,50-265 Distribution : Docket File PUBLIC
- PDlll-2 r/f
,1 EAdensam SRichards l
Enclosure:
SE w/att TLR CMoore
_ ' RPulsifer OGC,015B18 GGrant, Rlli ACRS, T2E26 MRing, Rlli i
_'cc w/ encl: See next page
- DOCUMENT NAME: G:\\CM\\ QUAD \\QC2257.RLF lz~
To receive e cop i of this document, l#Milcate in th h "C" = Copy without enclosures "E"MboDyndtil enclosures "N* = No copy OFFICE PM:PDill-2 lC
'LAllllll-2 l
OGCW JdGt" D:PDill-2 lC NAME RPULjlFF F Q46MtE J/JN/vf SRICHARDS Eg DATE 11/A(/ /98 11/ W /98
~11/2 6/98 11/.3 0 /98 OFFICIAL RECORD COPY
.~-
p Kit c
UNITED STATES s
y NUCLEAR REGULATORY COMMISSION a
WASHINGTON O.C. 20066 0001
,%,,,,,/
November 30, 1998 Mr. Oliver D. Kingsley, President Nuclear Generation Group Commonwealth Edison Company Executive Towers West lil 1400 Opus Place, Suite 500 Downers Grove,IL 60515
SUBJECT:
RELIEF REQUESTS CR-21, CR-22, CR-23 AND CR-24: IMPLEMENTATION i
OF ASME, SECTION XI, SUBSECTION IWE, FOR CONTAINMENT j
INSPECTION (TAC NOS. MA2257 AND MA2258)
Dear Mr. Kingsley-By letter dated July 2,1998, as supplemented on September 3,1998, Commonwealth Edison j
Company (Comed) submitted Relief Request Nos. CR-21, CR-22, CR-23 and CR-24 seeking 1
relief from some of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (Code),Section XI, Subsection IWE, requirements for Quad Cities Nuclear Puwer Station, Units 1 and 2. The September 3,1998, letter withdrew relief request CR-22.
The NRC staff, with assistance from our contractor Idaho National Engineering and Environmental Laboratory (INEEL), has reviewed and evaluated the requests for relief submitted for Quad Cities. The NRC staff adopts the evaluations and conclusions contained in the Technical Letter Report (TLR) prepared by INEEL. The enclosed Safety Evaluation (SE) incorporates the TLR (attached) and its findings.
Based on the above information, the staff concluded that for Relief Requests CR-21 and CR-24, i
the proposed attematives provide an acceptable level of quality and safety and are authorized pursuant to 10 CFR 50.55a(a)(3)(i). For Relief Request CR-23, the proposed alternative provides reasonable assurance of structural integrity of containment repairs and replacements, and compliance with the Code requirement would result in hardship without a compensating increase in the level of quality and safety. Therefore, the proposed attemative is authorized pursuant to 10 CFR 50.55a(a)(3)(ii).
This completes the review of the subject relief requests and closes TAC Nos. MA2257 and MA2258.
Sincerely, Stuart A. Richards, Director Project Directorate 111-2 Division of Reactor Projects - lil/IV i
Office of Nuclear Reactor Regulation Docket Nos. 50-254,50-265
Enclosure:
SE w/att TLR cc w/ encl: See next page
- - -. -. - - - - -. - ~ -
O. Kingsley Quad Cities Nuclear Power Station.
{
Commonwealth Edison Company Units 1 and 2 cc:
Michael I. Miller, Esquire Commonwealth Edison Company-Sidley and Austin Site Vice President-Quad Cities i.
j-One First National Plaza 22710 206th Avenue N.
1 Chicago, Illinois 60603 Cordova, Illinois 61242-9740 Commonwealth Edison Company.
Document Control Desk-Licensing Quad Cities Station Manager
- Commonwealth Edison Company.
l 22710 206th Avenue N.
1400 Opus Place, Suite 400
- Cordova, Illinois 61242-9740 Downers Grove, Illinois 60515 l
U.S. Nuclear Regulatory Commission Mr. David Helwig
- Quad Cities Resident inspectors Office Senior Vice President -
22712 206th Avenue N.
Commonwealth Edison Company Cordova, Illinois 61242 Executive Towers West lli 1400 Opus Place, Suite 900 Chairman
_ Downers Grove, IL 60515 Rock Island County Board of Supervisors Mr. Gene H. Stanley 1504 3rd Avenue PWR's Vice President
. Rock Island County Office Bldg.
Commonwealth Edison Company Rock Island, Illinois 61201 Executive Towers West lll 1400 Opus Place, Suite 900 lilinois Department of Nuclear Safety Downers Grove,IL 60515
_ Office of Nuclear Facility Safety 1035 Outer Park Drive Mr. Steve Peny Springfield, Illinois 62704 BWR's Vice President Commonwealth Edison Company Regional Administrator Executive Towers West lit U.S. NRC, Region ill 1400 Opus Place, Suite 900 801 Warrenville Road Downers Grove,IL 60515 Lisle, Illinois 60532-4351 Mr. Dennis Farrar.
William D. Leach Regulatory Services Manager Manager-Nuclear Commonwealth Edison Company MidAmerican Energy Company Executive Towers West lll 907 Walnut Street 1400 Opus Place, Suite 500
~ P.O. Box 657 Downers Grove,IL 60515 Des Moines, Iowa 50303 Ms. Irene Johnson, Licensing Director Vice President - Law and Nuclear Regulatory Services L
Regulatory Affairs Commonwealth Edison Company l
MidAmerican Energy Company Executive Towers West lli One River Center Place 1400 Opus Plece, Suite 500 106 E. Second Street Downers Grove,IL 60515 L
P.O. Box 4350 l
Davenport, Iowa 52808