NRC Monthly Operations Sumary n
Peach Botten Atomic Power Station January, 1988 UNIT 2_
Unit 2 remained shut down throughout the report period in compliance with the March 31,1937_ Shutdown Order, with maintenance and restart activities in progress.
Unit 3 Unit 3 remained shut down throughout the report period in compliance with the March 31, 1987 Shutdown Order, with recirculation system pipe replacement activities in progress.
Docket No. 50-277 Attachment to Monthly Operating Report for January, 1988 UNIT 2 REFUELING INFORMATION 1.
Name of facility:
Peach Bottom Unit 2 2.
Scheduled date for next refueling shutdown:
Reload 7 in progress 3.
Scheduled date for restart following refueling:
Indeterminate due to Shutdown Order 4.
Will refueling or resumption of operation thereafter require a technical specification change or other license amendment?
No If answer is yes, what, in general, will these be?
Modifications to reactor core operating limits.
(Reload 7 amendment approved September 11,1987.)
5.
Scheduled date(s) for submitting proposed licensing action and supporting information:
l l
Not applicable 6.
Important licensing considerations associated with refueling, e.g., new or different fuel design or supplier, unreviewed design or performance t
analysis methods, significant changes in fuel design, new operating procedures:
i None expected.
7.
The number of fuel assemblies (a) in the core and (b) in the spent fuel storage pool:
(a) Core-764FuelAssemblies (b) Fuci Pool - 1734 Fuel Assemblics, 58 Fuel Rods 8.
The present licensed spent fuel pool storage capacity and the size of any increase in licer st.d storage capacity that has been requested or is planned, in number of fuel assemblies:
The spent fuel pool storage capacity has been relicensed for 3819 fuel assemblies.
I e
Docket No. 50-277 Attachment to Month 13 Operating Report for January,1988 Page 2 UNIT 2 REFUELING INFORMATION (Continued) 9.
The projected date of the last refueling that can be discharged to the spent fuel pool assuming the present capacity:
September,1998 (September 1995, with reserve full coredischarge)
.e
, ~ -. - - + -, - - - - -
n,,
,,g---
Docket No. 50-278 i
Attachment to Monthly Operating Report for January, 1988 l
l UNIT 3 REFUELING INFORMATION 1.
Name of facility:
Peach Botton Unit 3 2.
Scheduled date for next refueling shutdown:
Reload 7inprogress(MajorPipeReplacementOutage) 3.
Scheduled date for restart following refueling Indeterminate due to Shutdown Order 4.
Will refueling or resumption of operation thereaf ter require a technical specification change or other license amendment?
Yes.
If answer is yes, what, in general, will these be?
Technical Specifications to accomodate reload fuel. Modifications to reactor core operating limits.
5.
Scheduled date(s) for submitting proposed licensing action and supporting information:
Reload 7 License Amendment to be submitted April,1988 6.
Important licensing considerations associated with refueling, e.g., new or different fuel design or supplier, unreviewed design or perfomance analysis methods, significant changes in fuel design, new operating procedures:
None expected.
7.
The number of fuel asserblies (a) in the core and (b) in the spent fuel storage pool:
(a) Core - 0 Fuel Assemblies (764 assemblies offloadedduringoutage)
(b) Fuel Pool - 2260 Fuel Assentlies, 6 Fuel Rods
Docket No. 50-278 Attaciment to Monthly Operating Report for January, 1988 Page 2 UNIT 3 REFUELING INFORMATION (Continued) 8.
The present licensed spent fuel pool storage capacity and the size of any increase in licensed storage capacity that has been requested or is planned, in number of fuel assemblies:
The spent fuel pool storage capacity has been relicensed for 3819 fuel assemblies. This modification began on February 20, 1987. The cogletion date for this modification has been rescheduled for February,1989 to accomodate the Unit 3 pipe replacement outage.
9.
The projected date of the last refueling that can be discharged to the spent fuel pool assuming the present capacity, prior to the completion of the new fuel racks installation:
March,1993 (reserve full core discharge cannot be acconunodated af ter the restart following the cogletion of the October,1987 refueling outage un'cil the completion of the new fuel racks)
- 10. The projected date of the last refueling that can be discharged to the spent fuel pool assuming the relicensed capacity, subsequent to the completion of the new fuel racks installation:
September, 2000 (March,1996, with reserve full core discharge) l l
l l
l f
n
' AVERAGE DAILY UNIT PCHER LEVEL.
' DOCKET NO. 50 - 277
...................... g....
UNIT PEACH BOTTOM UNIT 2 DATE FEBRUARY 12, 1988 COMPANY PHILADELPHIA ELECTRIC COMPANY L. L. MIDDLETON TECHNICAL ASSISTANT LICEPGING SECTION NUCLEAR SUPPORT DEPARTt4ENT TELEPHONE I2151 841 6374 MONTH JANUARY 1908 1
DAY AVERAGE DAILY PONER LEVEL DAY AVERAGE DAILY P0HER LEVEL (INE-NET)
(fME-NET) 1 0
17 0
2 0
18 0
3 0
19 0
0 0
to 0
5 0
21 0
6 0
22 0
7 0
23 0
8 0
24 0
9 0
25 0
x 10 0
26 0
AA 0
27 0
18 0
28 0
13 0
29 0
14 0
30 0
. A5 0
31 0
16 0
~
l
'l i AVERAGE DAILY LMIT PONER LEVEL-
- . i :
DOCKET NO. 50 - 278 UNIT PEACH BOTTON UNIT 3 DATE FEBRUARY 12, 1988-COMPW PHILADELPHIA ELECTRIC COMPANY L. L. MIDDLETON TECHNICAL ASSISTANT LICENSING SECTION NUCLEAR SUPPORT DEPARTMENT TELEPHONE ( 215) 841-6374 MONTH JANUARY 1988 4
DAY AVERAGE DAILY P0HER LEVEL DAY AVERAGE DAILY P0HER LEVEL (MNE-NET)
(ME-NET) 1 0
17 0
2 0
18 0
3 0
19 0
4 0
20 0
5 0
21 0
6 0
22 0
7 0
23 0
8 0
'24 0
9 0
25 0
80 0
26 0
Ba 0
27 0
At 0
28 0
13 0
29 0
10 0
30 0
15 0
31 0
16 0
l
OPERATING DATA REPORT DOCKET No. 50 - 277 DATE FEBRUARY 12, 1968 COMPLETED BY PHILADELPHIA ELECTRIC COMPANY
.L. L. MIDDLETON TECHNICAL ASSISTANT LICENSING SECTION NUCLEAR SUPPORT DEPARTMENT TELEPHONE (2151 841-6374 OPERATING STATUS
- 1. UNIT NAMEt PEACH BOTTON UNIT 2 l NOTES: UNIT 2 REMAINED SHUTDO>N l
g
- 2. REPORTING PERIOD:
JANUARY, 1988 l
UNDER NRC ORDER HITH j
l l
- 3. LICENSED THERMAL POHER(NMR):
3293 i
RESTART ACTIVITIES I
l l
- 4. NAMEPLATE RATING (GROSS PNEll 1152 l
CONTINUING.
l l
l l
- 5. DESIGN ELECTRICAL RATING (NET MHE):
1065 l
t
[
l
- 6. MAXIMUM DEPENDABLE CAPACITY (GRDSS MHE): 1098 l
l l
l
- 7. MAXIMUM DEPENDABLE CAPACITY (NET HHE ll 1051 l
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS IITEMS PAkeER 3 THROUGH 7) SINCE LAST REPORT, GIVE REASON $t
- 9. PONER LEVEL TO HHICH RESTRICTED, IF ANY (NET PNE)*
- 10. REASoldS FOR RESTRICTIONS, IF ANY8 THIS MONTH YR-TO-DATE CUMULATIVE 8
744 744 119.016 al. HOURS IN REPORTING PERIOD p.
0 0
74.196.8
- 12. NUMBER OF HOURS REACTOR KAS CRITICAL 0.0 0.0 0.0
- 83. REACTOR RESERVE SHUT 00HN HOURS 0.0 0.0 71 866.8
- 14. HOURS GENERATOR ON-LINE 0.0 0.0 0.0
- 15. UNIT RESERVE SHUTD@ti HOURS 0
0 212 810,745
- 20. GROSS THERMAL ENERGY GENERATED (MKH) 0 0
70,019,230
- 17. GROSS ELECTRICAL ENERGY GENERATED (MHH)
=
-4,235 4.235 67,036,681
- 18. NET ELECTRICAL ENERGY GENERATED IMHH)
PAGE 1 0F 2 l
)
.m 3
OPERATING DATA REPORT (CONTINUED)
DOCKET No. 50'- 277 DATE FEBRUARY 12. 1968 -
THIS HONTH YR-TO-DATE CUMULATIVE
~
. 0.0 0.0 60.4
-19. UNIT SERVICE FACTOR
- 20. UNIT AVAILABILITY FACTOR 0.0 0.0 60.4
- 21. UNIT CAPACITY FACTOR (USING HDC NET)
'0.0 0.0 53.6
.22. UNIT CAPACITY FACTOR (USING DER NET) 0.0 0.0 52.9
- 23. UNIT FORCED DUTAGE RATE 0.0 0.0
.14.6
- 24. SHUTDODNS SCHEDULED DVER NEXT 6 HONTHS (TYPE, DATE, AND DURATION OF EACH18 REFUELING OUTAGE -
- 15. IF SHUTDOHN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP*
i
- 26. UNITS IN TEST STATUS (PRIOR TO Cott1ERCIAL OPERATION):
FORECAST ACHIEVED INITIAL CRITICALITY 09/16/73 INITIAL ELECTRICITY 02/18/74 COMMERCIAL OPERATION 07/05/74 L
l PAGE 2 0F 2 s - NEGATIVE VALUE REPORTED FOR CONSISTDCY HITH FEDERAL ENERGY REGULATORY Corf GSSION REPORTS.
L F
l
OPERATING DATA REPORT
- ~
DOCKET NO. 50 - 278 DATE FEBRUARY 12, 1988 COMPLETED BY PHILADELPHIA ELECTRIC COMPANY L. L. MIDDLETON TECHNICAL ASSISTANT LICENGING SECTION PAJCLEAR SUPPORT DEPARTMENT TELEPHONE ( 215) 841-6374 OPERATING STATUS
- 1. UNIT NAME8 PEACH BOTTOM UNIT 3 i NOTES UNIT 3 REMAINED SHUTDOW l
l l
- 2. REPORTING PERIOD JANUARY, 1988 i
UNDER NRC ORDER HITH l
l l
- 3. LICENSED THERMAL PONERIMT):
3293 l
REFUEL AND PIPE REPLACEMENT l
1 I
O. NAMEPLATE RATING IG8 TOSS t94E):
1152 l
IN PROGRESS.
l l
l
- 5. DESIGN ELECTRICAL RATING INET 794E )
1065 l
l l
l
- 6. MAXIMikt DEPENDABLE CAPACITY IGROSS P94E 18 1098 l
l l
l
- 7. MAXIMUM DEPENDABLE CAPACITY INET 794E):
1035 l
l
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS (ITEMS NUPSER 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS 8
- 9. POWER LEVEL TO MHICH RESTRICTED, IF At# INET 794E):
- 10. REASONS FOR RESTRICTIONS, IF ANY:
THIS MONTH YR-TO-DATE CUMULATIVE AA. HOURS IN REPORTING PERIOD 744 744 114,912
- 88. NLMBER OF HOURS REACTOR HAS CRITICAL 0
0 76,357.4
- 13. REACTOR RLSERVE SHUTDOHN HOURS 0.0 0.0 0.0
- 10. HOURS GENERATOR ON-LINE 0.0 0.0 73,929.3
- 85. UNIT RESERVE SHUTDOHN HOURS 0.0 0.0 0.0 lo. GROSS THERMAL ENERGY GENERATED (t94HJ 0
0 215,278,901
- 87. GROSS ELECTRICAL ENERGY GENERATED (MKH) 0 0
70,611,432
=
4,235
-4,235 67,697,920
- 18. NET ELECTRICAL ENERGY GENERATEC (t94H)
PAGE 1 0F 2
DOCKET NO. 50 - 278 DPERATING DATA REPORT (CONTINUED)
DATE FEBRUARY 12, 1968 THIS MONTH YR-TO-DATE CtK1ULATIVE 0.0 0.0 54.3
'19. UNIT SERVICE FACTOR 0.0 0.0 64.3
- 20. UNIT AVAILABILITY FACTOR
- 21. UNIT CAPACITY FACTOR (USING HDC NET) 0.0 0.0 56.9
- 22. UNIT CAPACITY FACTOR (USING DER NET) 0.0 0.0 55.3 0.0 0.0 13.3
- 23. UNIT FORCED OUTAGE RATE
- 24. SHUTDOWS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH)2 INDETERMINATE UNTIL NRC ORDER IS SATISFIED.
- 25. IF SHUTDOW AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUPt
- 20. UNITS IN TEST STATUS (PRIOR TO COMKERCIAL OPERATION)*
FORECAST ACHIEVED 08/07/74 INITIAL CRITICALITY 09/01/74 INITIAL ELECTRICITY I2/23/74 COMMERCIAL OPERATION
- w I
1 I
i PAGE 2 0F 2 i
l l.
l
y.
,{
UNIT.SHUTD0694S AND POWER REDUCTIONS DOCKET No. 50 - 277 LNIT NAME PEACH BCTTOH UNIT 2 DATE FEBRUARY 12, 1988 REPORi NONTH JANUARY, 1980 COMPLETED BY PHILADELPHIA ELECTRIC COMPANY L. L. MIDDLETON TECHNICAL ASSISTANT LICENSING SECTION NUCLEAR SUPPORT DEPARTHENT TE LEPHONE ( 215 ) 841 6374 l
l l
l l NETH00 0F l LICENSEE ISYSTEMICOMPONENTI CAUSE AND CORRECTIVE j
jTYPElDURATION!REASONISHUTTING D06fil EVENT l CODE I CODE l ACTION TO 3.1 DATE I (1)I (HOURS)I (2) 1 REACTOR (3) l REPORT 8 l (4) l (5) l PREVENT RECURRENCE I
I l
l 1
1 I
I i
7 l 880101 }. S l 744.0 1 C l 1
l N/A I RC l FUELXX l CONTINUATION OF RESTART ACTIVITIES.
I I
I ----- 1 I
I I
i 1
1 I
i 744.0 I I
I i
l I
(3)
(4)
(1)
(2)
- FORCED REASON METHOD EXHIBIT G - INSTRUCTIONS
- - SCHEDULED A - EQUIPMEtn FAILURE (EXPLAIN) 1 - MAffJAL FOR PREPARATION OF DATA 2 - MAINTENANCE OR TEST 2
MANUAL SCRAM.
ENTRY SHEETS FOR LICENSEE C - REFUELING 3. AUTOMATIC SCRAM.
EVENT REPORT ILER)
D - REGULATORY RESTRICTION 4 - OTHER (EXPLAIN)
FILE INUREG-0161)
E. OPERATOR TRAINING + LICENSE EXAMINATION (5)
F - ADMINISTRATIVE G - OPERATIONAL ERROR (EXPLAIN)
EXHIBIT I - SArtE SOURCE H - OTHER(EXPLAIN) u
-t-T T
-'W:-
- ~
t c.
J UNIT SHUTDO E AND P0HER REDUCTIONS DOCKET No. 50 - 278 UNIT NAME PEACH BOTTOM UNIT 3 DATE FEBRUARY 12, 1988 REPORT MONTH JANUARY, 1988 COMPLETED BY PHILADELPHI4 ELECTRIC COMPANY ~
L. L. MIDDLETON TECHNICAL ASSISTANT LICENSING SECTION NUCLEAR SUPPORT DEPARTMENT TELEPHONE ( 215) 841-6374 1
l l
l l METHOD OF l LICENSEE ISYSTEMICOMPONENTI CAUSE AND CORRECTIVE I
ITYPElDURATIONlREAS4NISHUTTING DONNI EVENT l CODE l CODE I ACTION TO 3.1 DATE l (lli (HOURS)! (2 1 REACTOR (3) l REPORT 8 I (4) l (5) l PREVENT RECURRENCE I
I i
1 I
i 1
I i
7 l 88D101 1 S l 744.0 l C l 1
I N/A I RC l FUELXX l CONTINUATION OF REFUEL AND PIPE REPLACEMENT I
I l
l l
1 l
l l ACTIVITY.
I I
I ----- 1 I
I I
I I
I I
l 744.0 I
l I
l l
l (1)
(2)
(3)
(4)
- FORCED REASON METHOD EXHIBIT G - INSTRUCTIONS
- SCHEDULED A - EQUIPMENT FAILURE (EXPLAIN) 1 - MDJUAL FOR PREPARATION OF DATA B - MAINTENANCE OR TEST C - MANUAL SCRAM.
ENTRY SHEETS FOR LICENSEE C - REFUELING 3 - AUTOMATIC SCRAM.
EVENT REPORT (LER)
D - REGULATORY RESTRICTIDN 4 - OTHER (EXPLAIN)
FILE INUREG-0161)
E - CDERATOR TRAINIPG + LICENSE E>, AMINATION (5)
F - ALMINISTRATIVE G - OPERATIONAL ERROR (EXPLAIN)
EXHIBIT I - SAME SOURCE H - C1HER(EXPLAIN) l l
t i
l
e PHILADELPHIA ELECTRIC COMPANY 2301 M ARKET STREET P.O. BOX 8699 PHILADELPHI A. PA.19101 (215184l4000 February 11, 1988 Docket Nos. 50-277 50-278 Director Office of Inspection & Enforcement US Nuclear Regulatory Consission Washington, DC 20555 Attention: Document Control Desk
SUBJECT:
Peach Botton Atomic Power Station Monthly Operating Report Gentlemen:
Attached are twelve copies of the monthly operating report for Peach Botton Units 2 and 3 for the month of January,1988 forwarded pursuant to Technical Specification 6.9.1.d under the guidance of Regulatory Guide 10.1, Revision 4.
Very truly yours, W. M. Alden Director Licensing Section Nuclear Support Division
?
Attachment cc:
W. T. Russell, Administrator, Region I. USNRC T. P. Johnson, PBAPS Resident Inspector S. P. Mangi, n pt. of Envir. Resources e
P. A. Ross, W.0 (2 copies)
R. E. Martin, NRC Project Manager Thomas Magette, Maryland Power Plant Siting INP0 Records Center
\\